Climastor IV, L.L.C. v. Marshall Construction, L.L.C.

4 So. 3d 452, 2008 Ala. LEXIS 188, 2008 WL 4097589
CourtSupreme Court of Alabama
DecidedSeptember 5, 2008
Docket1051833
StatusPublished
Cited by6 cases

This text of 4 So. 3d 452 (Climastor IV, L.L.C. v. Marshall Construction, L.L.C.) is published on Counsel Stack Legal Research, covering Supreme Court of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Climastor IV, L.L.C. v. Marshall Construction, L.L.C., 4 So. 3d 452, 2008 Ala. LEXIS 188, 2008 WL 4097589 (Ala. 2008).

Opinion

BOLIN, Justice.

ClimaStor IV, L.L.C. (“ClimaStor”), appeals from an order of the Montgomery Circuit Court denying its motion to compel arbitration.

Facts and Procedural History

On July 5, 2002, ClimaStor, a Louisiana limited liability company, contracted with Goodwyn, Mills, & Cawood, Inc. (“GMC”), an architectural and engineering firm, to design an 80,000-square-foot climate-controlled storage facility to be constructed in Montgomery. On January 21, 2003, Cli-maStor entered into a contract with Marshall Construction, L.L.C. (“Marshall”), an Alabama limited liability company, to construct the climate-controlled storage facility designed by GMC for a contract price of $1,855,900. The contract between Cli-maStor and GMC required GMC to administer the construction contract. The contract between ClimaStor and Marshall required Marshall to have substantially completed construction of the storage facility by July 4, 2003. The contract also contained the following arbitration agreement:

“4.6.1 Any Claim arising out of or related to the Contract, except, Claims relating to aesthetic effect and except those waived as provided for in Subpara-graphs 4.3.10, 9.10.4 and 9.10.5, shall, after decision by the Architect [GMC] or 30 days after submission of the Claim to the Architect, be subject to arbitration. Prior to arbitration, the parties shall endeavor to resolve disputes by media[454]*454tion in accordance with the provisions of Paragraph 4.5.
“4.6.2 Claims not resolved by mediation shall be decided by arbitration which, unless the parties mutually agree otherwise, shall be in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association currently in effect. The demand for arbitration shall be filed in writing with the other party to the Contract and with the American Arbitration Association, and a copy shall be filed with the Architect.”

After Marshall had completed construction of the storage facility and ClimaStor had taken possession, Marshall submitted its final two applications for payment to ClimaStor, each of which had been approved by GMC, as the administrator of the construction contract. However, Cli-maStor withheld payment of the final two applications because of certain alleged deficiencies in the construction of the storage facility.

On July 1, 2004, Marshall filed in the Probate Court of Montgomery County a verified statement of lien against Clima-Stor in the amount of $114,548.15 plus interest. On January 3, 2005, Marshall sued ClimaStor in the Montgomery Circuit Court under § 35-11-222, Ala.Code 1975, seeking to satisfy its lien.

On February 8, 2005, ClimaStor’s Louisiana-based counsel notified Marshall’s counsel by letter that ClimaStor would “take steps to have the litigation stayed and the matter referred to arbitration” in accordance with the terms of the contract between ClimaStor and Marshall. However, rather than have the matter stayed and referred to arbitration, ClimaStor’s Alabama counsel, on February 10, 2005, filed a notice of removal to the United States District Court for the Middle District of Alabama. ClimaStor specifically stated in its notice of removal that the removal was being filed “with full reservation of any and all defenses, objections and exceptions, including its right to seek arbitration of the claims asserted in the Complaint .... ”

On February 17, 2005, ClimaStor filed an answer and a counterclaim in the United States District Court for the Middle District of Alabama. ClimaStor specifically stated that in submitting its answer, it was “reserving all of its rights and defenses, including its right to seek arbitration of the claims asserted in the Complaint .... ” ClimaStor also asserted in paragraph 11 of its answer the following:

“The Complaint is premature in light of the terms of [Marshall’s] contract with ClimaStor which provides for arbitration. This action should be dismissed or, in the alternative, stayed, pending final, binding arbitration between Clima-Stor and Marshall.”

ClimaStor alleged in its counterclaim that Marshall had breached the construction contract by failing to achieve substantial completion of the project by July 4, 2003; by failing to construct the storage facility according to the plans, specifications, and building codes; by failing to construct a storage facility that was free from defects; and by failing to make permanent repairs to cure the defects. ClimaStor further asserted in the counterclaim that it had withheld payment of the balance due Marshall under the construction contract. ClimaStor expressly stated in the counterclaim that it was asserting the counterclaim “without intending to waive, and expressly reserving, its right to have the claims asserted by Marshall and the claims asserted in this counterclaim decided by final, binding arbitration.”

On March 14, 2005, Marshall answered ClimaStor’s counterclaim and asserted counterclaims against ClimaStor alleging breach of contract and failure to make [455]*455timely payments pursuant to § 8-29-2 et seq., Ala.Code 1975. Marshall also moved on that same date to have the matter remanded to the Montgomery Circuit Court.

On March 29, 2005, ClimaStor filed a memorandum in opposition to Marshall’s motion to remand. On April 5, 2005, Marshall filed a reply to ClimaStor’s memorandum in opposition to the motion to remand. On May 24, 2005, the United States District Court entered an order finding that ClimaStor had faded to sufficiently demonstrate diversity of citizenship necessary for jurisdiction in the district court. However, the district court allowed ClimaStor the opportunity to submit supplemental pleadings disclosing its citizenship and that of Marshall. On June 1, 2005, ClimaStor filed its supplemental memorandum in opposition to the motion to remand. On June 8, 2005, the United States District Court entered an order granting Marshall’s motion to remand.

On August 23, 2005, ClimaStor’s counsel again notified Marshall’s counsel by letter that ClimaStor would “take steps to have the litigation stayed and the matter referred to arbitration” in accordance with the terms of their contract. On September 19, 2005, ClimaStor filed demands for arbitration against both Marshall and GMC with the American Arbitration Association seeking damages totaling $787,431.46.

On October 4, 2005, Marshall moved the circuit court to for a temporary restraining order and a preliminary injunction enjoining ClimaStor and the American Arbitration Association from participating in arbitration proceedings. Marshall contended that ClimaStor had waived its right to arbitration by substantially invoking the litigation process. On that same date, the circuit court entered an order granting Marshall’s temporary restraining order.

On October 7, 2005, ClimaStor moved the circuit court to stay the proceedings and to compel arbitration. On November 1, 2005, ClimaStor filed its brief in opposition to Marshall’s motion for a preliminary injunction and in support of its motion to compel arbitration. On that same day, Marshall filed its brief and evidentiary submission in opposition to the motion to stay and to compel arbitration. On November 7, 2005, Marshall filed its response to ClimaStor’s brief in opposition to the motion for a preliminary injunction and in support of the motion to compel arbitration.

Following a hearing, the circuit court, on November 8, 2005, ordered the parties to mediate their claims. Mediation was unsuccessful.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
4 So. 3d 452, 2008 Ala. LEXIS 188, 2008 WL 4097589, Counsel Stack Legal Research, https://law.counselstack.com/opinion/climastor-iv-llc-v-marshall-construction-llc-ala-2008.