Clifford Edward Sexton v. Commonwealth of Virginia

Court of Appeals of Virginia·Decided April 16, 2013·No. 0352122·Unpublished

Opinion

COURT OF APPEALS OF VIRGINIA

Present: Judges Humphreys, Kelsey and Beales UNPUBLISHED

Argued at Richmond, Virginia

CLIFFORD EDWARD SEXTON

MEMORANDUM OPINION * BY

v. Record No. 0352-12-2 JUDGE RANDOLPH A. BEALES APRIL 16, 2013

COMMONWEALTH OF VIRGINIA

FROM THE CIRCUIT COURT OF CHESTERFIELD COUNTY Frederick G. Rockwell, III, Judge

Ryan T. Spetz (Gordon, Dodson, Gordon & Rowlett, on briefs), for appellant.

Robert H. Anderson, III, Senior Assistant Attorney General (Kenneth T. Cuccinelli, II, Attorney General, on brief), for appellee.

Clifford Edward Sexton (appellant) was convicted in a bench trial before the Circuit Court of Chesterfield County of construction fraud in violation of Code § 18.2-200.1. 1 Appellant argues on appeal that the trial court erred by (1) not applying all of the necessary

*

Pursuant to Code § 17.1-413, this opinion is not designated for publication.

1

Code § 18.2-200.1 reads in pertinent part:

If any person obtain from another an advance of money, merchandise or other thing, of value, with fraudulent intent, upon a promise to perform construction, removal, repair or improvement of any building or structure permanently annexed to real property, or any other improvements to such real property . . . and fail or refuse to perform such promise, and also fail to substantially make good such advance, he shall be deemed guilty of the larceny of such money, merchandise or other thing if he fails to return such advance within fifteen days of a request to do so sent by certified mail, return receipt requested, to his last known address or to the address listed in the contract.

elements of Code § 18.2-200.1 when it found appellant guilty of violating Code § 18.2-200.1, and by (2) holding the evidence sufficient to find appellant guilty of violating Code § 18.2-200.1. We find that appellant’s first assignment of error is waived on appeal under Rule 5A:18 and that his second assignment of error, as stated, is inadequate under Rule 5A:12(c)(1)(ii). Accordingly, we affirm in part and dismiss in part.

I. BACKGROUND

On September 23, 2010, William R. Patterson, who resided in Chester, Virginia, entered into a contract with appellant’s company, Hall-Sexton General Contracting, to make repairs to the exterior of his home. Patterson dealt solely with appellant with regard to the repairs. The contract, which both Patterson and appellant signed, recited that the work would begin on the following day, September 24, 2010, and would be completed by October 14, 2010. The contract called for Patterson to make a deposit of 50%, and the remaining 50% would be paid when the work was completed. The contract also required Patterson to supply all of the materials for the work. On September 23, 2010 Patterson gave appellant a check in the amount of $2,070 as an advance, which appellant then cashed. On that same day, Patterson and appellant also signed a one-page document entitled “Agreement.” That document also recited a start date of September 24, 2010, and a finish date of October 14, 2010, and noted that Patterson had given appellant the check for the advance in the amount of $2,070.

Even though the contract and agreement stated that appellant would begin his work on the very next day, September 24, 2010, Patterson testified that “no one showed up” at that time. Patterson had already paid appellant the advance and provided the materials for the project, as the contract required. However, appellant did not fulfill any of his obligations under the contract.

Patterson called appellant on the phone the afternoon of September 24, 2010 after “no one showed up” to begin work on the start date. Patterson testified that during that phone call, appellant told him that “the crew that he was using was running behind on a project that they were working on, and that [they] would reschedule the work for the following week.” Appellant told Patterson that he would inform him when he would be able to start the repairs. Appellant subsequently did not call Patterson to tell him when the project would begin. At some point between Tuesday and Thursday of the following week, Patterson left appellant a message expressing his concern about the delay in starting the work. Patterson testified that he was “beginning to get worried because of the water restriction coming up” as a county mandatory restriction on using water would likely be imposed when appellant still needed to “power wash the house before [he could] do any of the other work.” Appellant later called Patterson back, but the work still did not begin.

Patterson explained that, when he attempted to call appellant, it usually took “three to six days between the time I initiated communication until I got some sort of response back.” Patterson testified that appellant gave him an explanation for the delays once. Patterson testified that on that occasion, appellant explained to him that “he was having the loss of some personnel that would adversely impact his ability to do things, and that he would get with me and set a date for the work to be done.”

Patterson testified that after that, appellant’s “telephone calls were sketchy, so [Patterson]

started using email as communication.” Patterson said that several times appellant responded to his emails with “commitments . . . to start the work, and then [appellant] would miss his target.” For example, Patterson stated that he received an email from appellant on a Tuesday, in which appellant said that he would start work “the next Wednesday.” Patterson testified that he construed appellant’s response to indicate that he would be at his home the following day, but

appellant did not show up on that day or the Wednesday of the following week. Patterson noted that there was “no communication” from appellant, “[s]o [he] [s]ent another email, and this kept going on and on and on.” Patterson testified at trial that “at least 95 percent of the time I was the one who initiated the conversations or attempted conversations.”

After appellant repeatedly promised to start the repairs, work had not even begun on the project by the date that the contract called for the project to be completed – October 14, 2010. Patterson filed a complaint with the Better Business Bureau and on November 15, 2010, sent a certified registered letter to the address for appellant’s contracting company, which was returned unclaimed. In that letter, Patterson requested that appellant return the advanced payment of $2,070, for failure to undertake the agreed-upon repairs. Appellant had closed his business two days prior to the certified letter being sent and testified that he was unaware of Patterson’s certified letter until December. As of the time of the trial on October 17, 2011, appellant had not returned Patterson’s money or started the repairs.

Patterson testified that he had spoken with appellant prior to Christmas in December of 2010, and appellant indicated for the first time that he was having “problems with his business [and] was going to close down” and that he needed additional time to pay back the money. Patterson testified that he agreed to give him “some time to make arrangements.” Patterson spoke with the Better Business Bureau, and its representatives talked with appellant. However, appellant never returned Patterson’s money.

Appellant admitted at trial that he had financial problems as far back as 2008 and “was having trouble staying afloat.” Specifically, appellant testified:

So as things got leaner, leaner and leaner, you were doing work for less and less and less, so your profit was less, but your bills were still the same. Because I was so much in the red, I was - I was doing what a lot of people don’t like to do. I was robbing from Peter to pay Paul. And I was doing that, and successfully, I was looking like I was going to get out of it, and then it turned on me

again, and I just - I couldn’t. I had robbed everything from my family, my wife’s 401K, my savings, it all just went.

Free access — add to your briefcase to read the full text and ask questions with AI

Clifford Edward Sexton v. Commonwealth of Virginia, (Va. Ct. App. 2013).

Clifford Edward Sexton v. Commonwealth of Virginia (Clifford Edward Sexton v. Commonwealth of Virginia) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Rushing v. Com.
726 S.E.2d 333 (Supreme Court of Virginia, 2012)
Davis v. Commonwealth
717 S.E.2d 796 (Supreme Court of Virginia, 2011)
Carroll v. Com.
701 S.E.2d 414 (Supreme Court of Virginia, 2010)
Edwards v. Commonwealth
589 S.E.2d 444 (Court of Appeals of Virginia, 2003)
Redman v. Commonwealth
487 S.E.2d 269 (Court of Appeals of Virginia, 1997)