Cleveland v. Griffen

17 Ohio C.C. Dec. 167, 5 Ohio C.C. (n.s.) 473
CourtOhio Circuit Courts
DecidedNovember 7, 1904
StatusPublished

This text of 17 Ohio C.C. Dec. 167 (Cleveland v. Griffen) is published on Counsel Stack Legal Research, covering Ohio Circuit Courts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cleveland v. Griffen, 17 Ohio C.C. Dec. 167, 5 Ohio C.C. (n.s.) 473 (Ohio Super. Ct. 1904).

Opinion

MARVIN, J.

The plaintiff in error was the defendant below. The defendants in error were plaintiffs below. The terms plaintiff and defendant as used in this opinion refer to the parties as they stood in the original case.

[168]*168The plaintiffs are parties doing business under the firm name of Griffin, Norton & Co.

The defendant is a municipal corporation organized under the laws of Ohio.

On July 12, 1899, the plaintiff, C. N. Griffin, and the defendant, the latter acting by and through its proper officers and proceeding in all respects according to law for that purpose, entered into a contract in writing under which the said Griffin w'as to construct a masonry arch at Edgewater park in said city. By the terms of said contract the said Griffin was to do all the work and furnish all the machinery, tools and materials, and do everything requisite to the complete construction of said arch, in the manner and under the conditions specified in the contract and in accordance with plans and directions made and to be made from time to time by the defendant, and the said Griffin was to receive therefor from the defendant different prices for the different parts of the work, such various prices being specified in the contract.

Among the prices so specified are the following:

“3. For all'stone masonry in the work, except the arch masonry, including the furnishing of all materials, tools and labor, the sum of $7.50 per cubic yard.
“4. For all arch masonry in the work, including the furnishing of all materials, tools and labor, forms and centers, the sum of $11.50 per cubic yard. ”

The sáid Griffin assigned to the plaintiffs all his rights under this contract.

The work was fully completed. Payments were made by the defendant from time to time, upon estimates furnished by thé engineer acting for the city.

On October 26, 1901, the proper engineer furnished a final estimate for the work done and materials furnished in the construction of said arch.

Said estimate fixed the amount of stone masonry in said arch at 3,734.76 cubic yards, and the amount of arch masonry at 644.46 cubic yards. As to these estimates the plaintiffs complain that, though the aggregate amount of masonry is properly given, the division between the two classes is wrong.

Other items in this final estimate were complained of by the plaintiffs, but no claim is here made that the judgment of the court below as to such items was erroneous.

The petition prayed for a correction of the so-called final estimate of the engineer, that an accounting might be had upon such corrected [169]*169estimate, and that plaintiffs have judgment for the amount found due them upon such accounting.

The result in the court of common pleas was a finding that 939 cubic yards classified in the estimate as stone masonry should have been classified as arch masonry, thus increasing the amount of arch masonry to 1,583 cubic yards and reducing the amount of stone masonry to 2,795.76 cubic yards, an accounting then being taken and fixing the amount due plaintiffs upon such amended estimate.

As the price of arch masonry was fixed in the contract at $11.50 per cubic yard while stone masonry was fixed at $7.50, the court therefore added to the engineer’s estimate on this item $4 per yard on 939 yards, and the only question before this court is whether the court erred in making this addition.

One of the items in the contract hereinbefore mentioned reads:

“8. To prevent all disputes and litigation, it is further agreed by and between the parties to this contract that the engineer shall be referee, in all cases, to decide upon the amount, quality, acceptableness and fitness of the several kinds of work and materials which are to be paid for under this contract, and upon all questions which may arise, relative to the fulfillment of the contract on the part of the contractor, and his estimates shall be final and conclusive, and such estimate and decision, in case any question shall arise, shall be a condition precedent to the right of said contractor to receive any money under this agreement.”

A further provision of the contract, under the heading “general requirements,” is as follows:

“It is further mutually agreed that whenever, in the opinion of the engineer, the said contractor shall have completely performed this contract, the said engineer shall proceed, with all reasonable diligence to measure up the work, and shall make out the final estimate for the same, ’ ’ etc.

It was in pursuance of this clause of the agreement that the estimate herein first mentioned was made out.

On the part of the defendant (plaintiff in error), it is urged that under this contract plaintiffs were absolutely bound by the final estimate of the engineer, no claim being made that there was any purpose or intention on his part to defraud the plaintiffs, or that he acted in bad faith in making his estimates. Authorities are cited in support of this contention. Among them is the case of Martinsburg & P. Ry. v. March, 114 U. S. 549 [5 Sup. Ct. Rep. 1035; 29 L. Ed. 255]. The provisions of the contract in that ease are substantially as the one under consideration here. In that case there was no allegation in the [170]*170bill that the engineer had made the final estimate provided for, but the court say, on page 553:

“Upon the supposition that the engineer made such a certificate as that provided by the contract, there is no allegation that entitled the plaintiff to go behind it; for, there is no averment that the engineer had been guilty of fraud, or had made such gross mistake in his estimates as necessarily implied bad faith; or had failed to exercise an honest judgment in discharging the duty imposed upon him. The first count of the declaration was, therefore, defective for the want of proper averments showing plaintiff’s right to sue on the contract, and the demurrer to that count should have been sustained. ’ ’

From this case and the cases cited in its support, it seems clear that if the 'rule there laid down is to be applied to the present case, the plaintiffs must fail and the judgment of the court of common pleas must be reversed on that ground, but our own Supreme Court seem to have modified this rule somewhat.

In the case of Balt. & O. Ry. v. Stankard, 56 Ohio St. 224 [46 N. E. Rep. 577; 49 L. R. A. 381; 60 Am. St. Rep. 745], suit was brought by the parents of Michael Stankard who, having be.en an employe of the railroad company, died, and the claim was made that he was such employe at the time of his death. Suit was to recover for death benefits provided under certain regulations of the company. The claim was presented to the superintendent of the relief department, who did not allow it but referred it to the advisory committee, who rejected it because of his failure to report in accordance with the regulations. On the part of the company it was urged that the suit was barred under rule 11 of the relief department, which reads, page 229:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Martinsburg & Potomac Railroad v. March
114 U.S. 549 (Supreme Court, 1885)

Cite This Page — Counsel Stack

Bluebook (online)
17 Ohio C.C. Dec. 167, 5 Ohio C.C. (n.s.) 473, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cleveland-v-griffen-ohiocirct-1904.