Cleveland v. Connelly
This text of 23 Ohio C.C. Dec. 64 (Cleveland v. Connelly) is published on Counsel Stack Legal Research, covering Cuyahoga Circuit Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
The facts in this ease are that on August 6, 1900, the Cleveland Steam Boiler Works, by D. Connelly, proprietor, entered into a contract with the city of Cleveland to furnish seven steam fire engines, five being of the second size and two of the third size, for the use in the fire department of the city. The contract was made pursuant to competitive bidding, the advertisement being authorized by resolution of the council passed in June, 1900. The advertisement required bids to be tendered not later than 12 o’clock M., July 12, 1900, and contained a stipulation that each bid should be accompanied by a certified check on a solvent bank in the -sum of $2,000 as a guarantee, if the bid were accepted, that a contract would be entered into, that the performance of the contract would, be secured to the satisfaction of the city, and that, in addition to such guarantee, said check should be forfeited to the city as liquidated damages for any failure to comply with the terms of the proposal. By resolution of the council, of July, 1900, [66]*66the bid of the Cleveland Steam Boiler Works was declared the lowest and best bid, and the director of fire, service was authorized to enter into a contract svith that bidder to furnish the engines. The bid of D. Connelly was then attached to certain specifications and writing, and signed as a contract. This contract appears, as defendant’s exhibit “D,” the first page of it being the bid of D. Connelly, the remainder being the rest of the contract. After being duly signed, the contract svas certified to by the city auditor, as is required by the Burns law, approved by the board of control and the corporation counsel, and subsequently by the committee on fire, and on August 20, 1900, received the final approval of the council and became a valid and binding contract.
The bidding pursuant to the advertisement, was required to be upon blanks furnished by the board of control and Connelly’s bid, partly printed and partly written, stipulated that the bidder proposed to furnish one or more second and third size -steam fire engines, in accordance with specifications and guarantee accompanying the proposal, at fire station No. 1, within 210 days after the execution of the contract for the same; that for each day that the contractor shall fail to deliver said engine or engines, within the time specified, it is agreed that the contractor shall pay to the order of the director of fire service of the city, $25 per day as liquidated damages for such failure; and, in the itemized specifications as to price for the several sizes of engines, that deliveries are proposed to be made, two engines in 120 days, two engines in 160 days, two engines in 200 days and one engine in 210 days.
The contract was made on August 6, 1900, and the engines were not delivered until May 21, 1901, fifty-one days over and ' above the 210 days within which the 'proposal accepted by the council agreed that they should be furnished. The city of Cleveland thereupon paid the agreed price for the engines, less the sum of $1,275 which it retained as liquidated damages for the delay. Subsequently, the council of the city o.f Cleveland passed a resolution directing the payment of this $1,275. It was not paid and suit was brought.
[67]*67The questions raised on this state of facts ate as follows: 1. Is the proposition made by D. Connelly and physically attached to the contract a part of the contract? 2. If the proposal is a part of the contract, is the provision for $25 per day as liquidated damages a provision for stipulated damáges or a penalty? 3. Has the council of the city of Cleveland power by resolution to exonerate the plaintiff from the payment of stipulated damages after default in his contract? i'
It is evident that if any one of these questions is decided! adversely to the city, such decision disposes of the whole case. The court below held that the proposition made by D. Connelly and physically attached to the contract, was in law no part of the contract. Passing, however, to the question whether the provision for $25 per day as liquidated damages is to be construed as a provision for stipulated damages, or as in the nature of a mere penalty, as upon a bond given for faithful performance of the contract, the tests applied in such cases are usually these: 1. Is .the subject-matter of the contract of such a nature that the actual damages in case of breach will be entirely uncertain and indeterminate? 2. Were damages evidently the subject of calculation and adjustment between the parties at the time the contract was made? 3. Is the stipulation reasonable? 4. What was the intent of the parties? 5. What was the language employed?
Without attempting formally to discuss or apply these tests in their order, we may note some significant facts shown in the record. The circumstance that the formal contract, as distinguished from the proposition attached thereto, contains no reference to this subject nor any express reference to the paper which does mention it, is itself an indication that the parties did not have the subject of damages so prominently before their minds when they made their agreement as to make it a matter of deliberate calculation and adjustment. Moreover, if the attached paper is properly a part of the contract, the reference therein to the subject of damages is contained in the original form or blank furnished to bidders and not in the portion thereof afterwards filled in. It is a formal provision which does not apply with precision to the plan of installment [68]*68deliveries which was written into the blank by Connelly when he presented his bid. It is on that account admittedly ambiguous and uncertain. Does it mean $25 per day forfeiture for each engine, the delivery of which is delayed? If so, it is manifestly exorbitant. The city insists that it has adopted the construction most favorable to Connelly. But, suppose he had been in default as to but one engine; or had made some ■ deliveries punctually and had delayed others only until the ■day for delivering the last engine. If provision is made for some delays and not for others, what reason is there for the «distinction? We cannot ascertain from the language employed that the parties had any definite intent on the subject. It is true that damages in a matter of this kind are not easily susceptible of ascertainment, but we cannot discover, from the ■contract or from any evidence in the record, that the parties, in order to meet this difficulty, deliberately set about in advance to estimate and adjust the damage to flow from a breach •of this contract, and to stipulate and agree formally upon the .rule or measure thereof. We think, therefore, that the court below was quite right in holding this action to be maintainable. As there was no attempt to prove actual damages, we do not find it necessary to pass upon any of the other grounds urged as productive of the same result that we have reached on this ground alone.
It is claimed by the city, however, that there was error in the rejection of certain evidence, which it tendered to show •.that Connelly, by exacting from his subcontractor a contract ¡similar in this respect to the one in question here, and by claiming thereunder the same rights that the city claims here, has evinced his construction of the contract here to be what the city claims. It is not contended that this evidence of res inter alios actae was admissible in order to prevent an unjust result here, but as tending to show how the parties themselves interpreted this contract. We think the evidence was properly excluded.
Free access — add to your briefcase to read the full text and ask questions with AI
Cite This Page — Counsel Stack
23 Ohio C.C. Dec. 64, 14 Ohio C.C. (n.s.) 433, 1905 Ohio Misc. LEXIS 319, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cleveland-v-connelly-ohcirctcuyahoga-1905.