Cleveland, Cincinnati, Chicago & St. Louis Railway Co. v. Scott

79 N.E. 226, 39 Ind. App. 420, 1906 Ind. App. LEXIS 149
Indiana Court of Appeals·Decided November 20, 1906·No. No. 5,782·Published·Cited by 4 cases

Opinion

Comstock, P. J.

Appellees, subcontractors, filed their complaint in three paragraphs against appellants, the Shutt Improvement Company, railway contractors, and the Cleveland, Cincinnati, Chicago & St. Louis Railway Company, and sought a judgment against the appellant Shntt Improvement Company for work and labor performed under a certain contract with appellees, and sought to enforce a mechanic’s lien, for the value of said work and labor, against the railroad company.

[422] The complaint was first filed in one paragraph, to which the appellants filed their separate demurrers, which were overruled by the court. Afterwards, the appellees filed their second and third paragraphs of complaint, in which they set out a contract between themselves and the Shntt Improvement Company, alleging a failure on the part of the Shutt Improvement Company to make payment, as provided in said contract, and asking judgment against said Shutt Improvement Company for the value of the work and labor up to the time of the alleged default, and praying for the enforcement of a mechanic’s lien against the appellant railroad company for the value of said work and labor. The second and third paragraphs of complaint are practically of the same tenor. The complaint avers that, while there was a contract between appellees and appellant Shutt Improvement Company, yet, appellant improvement company violated the contract by failure to pay as provided, after appellees had' done the less remunerative work, and they sought to recover the value of their work without regard to the contract price. The court sustained the demurrer of the railroad company to the first paragraph of the original complaint, overruled the demurrer of the Shutt Improvement Company to said paragraph, #and overruled the demurrers of both appellants to the’ second and third paragraphs. The appellants thereupon filed their separate and sever.al answers in three paragraphs, the first being a general denial, the second a plea of payment, and the third alleging that the appellees abandoned the contract, set out as an exhibit to their complaint, left a large portion of the work thereunder undone, and that, by reason thereof, the appellant Shutt Improvement Company was entitled to damages amounting to more than any unpaid sum due the appellees, and praying for a set-off, and that said improvement company have judgment over for damages. At the time of filing the answers, appellant improvement company filed its cross-complaint, in which it set out the contract [423] between itself and said railroad company, and averred that said improvement company was thereby compelled to complete the same; that appellees have been overpaid for the amount actually done by them, and praying for damages in the sum of $3,000 on account of the abandonment of the contract by appellees.

The court made a special finding of facts, which may be summarized as follows: Prior to October 10, 1903, said defendant railway company began the work of relocating its track in Dearborn county, Indiana. The defendant Shutt Improvement Company, a corporation engaged in the business of railroad construction, from October 1, 1903, to October 1, 1904, was engaged as general contractor, under a written contract with the defendant railway company, in the construction of a new roadbed upon the right of way of the defendant railway company, in Dearborn county, Indiana, and said contract included the excavation of a great number of yards of earth and the making of fills therewith, and included all excavations and fills hereinafter mentioned as contracted to be done by the plaintiffs herein between bridges No. 147 and No. 163. The plaintiffs, Scott and.Walker, partners doing business under the firm name and style of Scott & Walker, were engaged in the contracting business, and on October 10, 1903, they entered into a contract with the defendant Shutt Improvement Company to do the excavating that then remained undone between bridges No. 147 and No. 163. Said contract, which was in writing, was as follows:

“Cincinnati, Ohio, October 10, 1903.
Shutt Improvement Company,
Cincinnati, Ohio.
Gentlemen:
We propose to do the excavation for you on the work Bird is now on for twenty cents per cubic yard and one cent per cubic yard per each 100 feet from east side of creek, extra for all work that goes over Tanner’s [424] creek, you to finish and build the bridge over Tanner’s creek.
Any portion of the work which we are unable to complete by reason of uncompleted bridge piers, or present railroad tracks, or for any other cause over which we have no control, is to be omitted. In other 'words, our work is to be continuous and completed at once. Payment of ninety per cent to be made monthly, and balance on completion of contract.
Yours very truly,
Scott & Walker.
Accepted with the understanding that sufficient force is to be put on to complete by Eebruary 1, 1904.
Shutt Improvement Company, by E. W. Shutt.”

Free access — add to your briefcase to read the full text and ask questions with AI

Cleveland, Cincinnati, Chicago & St. Louis Railway Co. v. Scott, 79 N.E. 226, 39 Ind. App. 420, 1906 Ind. App. LEXIS 149 (Ind. Ct. App. 1906).

79 N.E. 226 (Cleveland, Cincinnati, Chicago & St. Louis Railway Co. v. Scott) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Kokomo Steel & Wire Co. v. Macomber & Whyte Rope Co.
128 N.E. 362 (Indiana Court of Appeals, 1920)
Cullen-Friestedt Co. v. Turley
97 N.E. 946 (Indiana Court of Appeals, 1912)
Mug v. Ostendorf
96 N.E. 780 (Indiana Court of Appeals, 1911)
Ferdinand Railway Co. v. Link
95 N.E. 274 (Indiana Court of Appeals, 1911)