Clegg v. Seaboard Steel Casting Co.

34 Pa. Super. 63, 1907 Pa. Super. LEXIS 80
Supreme Court of Pennsylvania·Decided October 7, 1907·No. Appeal, No. 224·Published·Cited by 5 cases

Opinion

Opinion by

Head, J.,

In his charge to the jury the learned trial court stated most of the material facts on which the plaintiff’s claim was based, and the two questions as to which the defendant craved special instructions, in the following language, viz.: “ It appears that on December 3, 1902, this plaintiff, who was an employee of the Seaboard Steel Casting Company, was going to his work in the morning somewhere near 7 o’clock, quarter ’before 7, or somewhere about that time, and while passing over the route, the usual route I think he said he took, he slipped into, or fell into this ditch. It appears that on the day before, there being something the matter with the steam that heated one of the departments of this establishment, a ditch was dug along the line of the steam pipe to ascertain a leak, and near this pathway over which the plaintiff traveled, an opening was left which had been dug, he said, four or five feet long. Some of the other witnesses say ten or twelve feet long and about fifteen or eighteen inches wide. He says that on this morning he was passing along this pathway and when he got to what has been termed the comer of the scrap pile where he turned short around to the left, he there stepped into this ditch. The great battle has been fought here over two questions: First, whether the plaintiff did exercise due and reasonable care; and next, whether the defendant did all that it was reasonable it should do under the circumstances ? ” The court concluded that both of these questions were questions of fact and submitted the whole case, on both branches, to the jury.

The learned counsel for the defendant did not then contend and does not now argue that the court should have declared, as matter of law, that the plaintiff was guilty of contributory negligence. The evidence on this point was conflicting. There was indeed very strong and persuasive testimony from which the jury might well have reached a different conclusion on this question, and the' tenor of the general charge and the answer to the defendant’s first point show that the trial court was duly impressed by it. But that court had no right, nor have we any, to usurp functions which, from time immemorial, [67] the law has committed to another tribunal. We may therefore dismiss this subject without further consideration.

By its second point the defendant asked the court to hold, as matter of law, that “ the negligence in this case, if any, was that of a coemployce of the plaintiff, and the plaintiff, therefore, is not entitled to recover.” This was refused for the reason that “to affirm that point would be to take the case from the jury. ... It is a question for you whether, under all the circumstances, the verdict shall be or shall not be for the defendant.”

Here was a distinct specific request for the application by the court to the case, as it then stood, of the well-established rule of law “ which holds that the master is not responsible for an injury received by an employee caused by the negligence of a coemployee or fellow workman.” Here we may pause to observe that it is obvious this point of the defendant, the only one inviting a ruling on a distinct legal proposition, necessarily assumed as' a fact in this case, that the plaintiff, at the time of his injury, was an employee of the defendant. The court refused the point, not because of any question as to the relation then existing between the parties, but for the reason quoted. The only point presented by the counsel fo.r the plaintiff himself, and the answer thereto, clearly indicate that both counsel and court regarded it as an undisputed fact in the case that the plaintiff was in the service of the defendant. The onlj- reference made to this question in the general charge is in the opening sentence already quoted where the plaintiff is called “ an employee.” It seems clear, therefore, to us that throughout the trial the case proceeded on the assumption, unquestioned by anybody, that the relation of the parties, at the time of the plaintiff’s injury, was that of master and servant, and the verdict of the jury, on the questions of fact submitted, cannot now be fairly said to have been induced or in any way influenced, by any different idea of that relation that later was suggested to or adopted by the court below. The significance of these remarks we will refer to later on and now return to a consideration of the question raised by the second point and the answer thereto. This will involve the statement of some additional facts. It is of course conceded that the place where the accident happened was within the premises and plant of the de[68] fendant, the path, along which the plaintiff was then traveling, leading from the main entrance to the pattern shop where he was employed. The obligation of his service required the plaintiff to be at his post prepared to begin work at seven o’clock. He had reached the plant about eighteen minutes before that hour and the accident occurred at approximately ten minutes later.

The repairs to the buried steam pipe which necessitated the opening of the ditch, into which the plaintiff stepped at the turn of the path, had been ordered by one Witsil. They were begun the day before the accident and were conducted under his personal supervision, although there was a foreman in immediate charge of the men. Witsil describes in his testimony how the work was done, and admits that they left a section of the ditch unfilled about twelve feet long. Who was Witsil? What were the nature and extent of his authority? Did he occupy towards the plaintiff the relation of a fellow-servant- or a vice principal ? He was the master mechanic of the defendant, and in his own testimony, not contradicted, we find the following :

“ Q. I am asking you what are your general duties at the Seaboard? A. As.chief engineer and as master over all the works of all work pertaining to the work. Q. Do you mean repair work ? A. Repair work. Q. You have charge of all the repair men, have you? A. Yes, sir. Q. And hire and discharge them ? A. Yes, sir.”

From this testimony it may be fairly deduced that as to one important branch of the defendant’s business, the keeping of its plant and machinery in a state of efficiency and repair, Witsil was invested with the full authority of his principal. He appears to have determined, without being required to consult any higher officer, when and what repairs were necessary, and to have selected his own means for executing his plans. Doubtless he was responsible to his superiors for the results obtained, but there is no evidence from which a jury could find that within his sphere of action his work was regulated by any discretion or oversight but his own. This would bring him within the first branch of the definition of a vice principal announced by Mr. Justice Mitchell in Prevost v. Citizens’ Ice. etc.. Co., 185 Pa. 617.

Free access — add to your briefcase to read the full text and ask questions with AI

Clegg v. Seaboard Steel Casting Co., 34 Pa. Super. 63, 1907 Pa. Super. LEXIS 80 (Pa. 1907).

34 Pa. Super. 63 (Clegg v. Seaboard Steel Casting Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Shuster v. Jaffola & Mark, Inc.
22 Pa. D. & C. 556 (Philadelphia County Court of Common Pleas, 1935)
Rudman Et Ux. v. City of Scranton
173 A. 892 (Superior Court of Pennsylvania, 1934)
Glenn v. Kittanning Iron & Steel Mfg. Co.
62 Pa. Super. 163 (Superior Court of Pennsylvania, 1916)
Mingak v. Vesta Coal Co.
51 Pa. Super. 584 (Superior Court of Pennsylvania, 1912)
Ready v. Smith & Furbush Machine Co.
51 Pa. Super. 294 (Superior Court of Pennsylvania, 1912)