CleanSoils Wisconsin, Inc. v. State of Wisconsin Department of Transportation

599 N.W.2d 903, 229 Wis. 2d 600, 1999 Wisc. App. LEXIS 803
CourtCourt of Appeals of Wisconsin
DecidedJuly 27, 1999
Docket98-3374
StatusPublished
Cited by6 cases

This text of 599 N.W.2d 903 (CleanSoils Wisconsin, Inc. v. State of Wisconsin Department of Transportation) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CleanSoils Wisconsin, Inc. v. State of Wisconsin Department of Transportation, 599 N.W.2d 903, 229 Wis. 2d 600, 1999 Wisc. App. LEXIS 803 (Wis. Ct. App. 1999).

Opinion

CANE, C. J.

The State Department of Transportation (DOT) and the State Department of Commerce (DOC) appeal from the circuit court's order holding that the State had consented to suit, therefore denying the State's motion to dismiss for lack of personal jurisdiction based on the sovereign immunity of the State and its agencies. 1 This appeal presents three issues: (1) whether legislative adjournment constitutes a refusal of claim, thereby mandating a finding that CleanSoils Wisconsin, Inc. (CleanSoils) had satisfied the statutory conditions precedent for bringing suit against the State; (2) whether cross-claimants 2 must satisfy the *603 conditions precedent for bringing suit against the State where they are asserting a claim for indemnification, arising out of CleanSoils' claims, rather than an independent claim; and (3) whether, assuming the conditions precedent have been satisfied, the State consented to suit based on either unjust enrichment or breach of contract.

Because legislative adjournment constitutes refusal of CleanSoils' claim, which had been properly filed with the claims board and brought before the legislature, CleanSoils satisfied the conditions precedent for bringing suit against the State. Further, because cross-claimants failed to comply with the statutory conditions precedent, their derivative claims against the State are dismissed. Finally, the State has consented to suit by CleanSoils, as a third-party beneficiary, based on breach of contract, but not, however, on the theory of unjust enrichment.

I. BACKGROUND

In its opinion denying the State's motion to dismiss, the trial court found that in 1995, the Department of Transportation (DOT) planned a highway improvement project on Highway 97 near Edgar, Wisconsin. As part of its plan, the DOT identified a parcel of land, owned by Harold and Audrey Bean (Bean), that was necessary for an intersection improvement. Consequently, the DOT entered into a purchase agreement with Bean. Shortly thereafter, it was discovered that the parcel was contaminated with petroleum from a leaking underground storage tank.

To begin a remediation project on the land, Bean retained Central Wisconsin Engineers and Architects (CWE), a state consultant, as environmental engineers for the cleanup. CWE invited CleanSoils, a business *604 that engages in the thermal remediation of petroleum contaminated soil, to bid on the remediation project. This invitation to bid stated that it was DOT's intention to undertake a remediation project.

After CleanSoils' bid was accepted, Bean had difficulty securing funding for the remediation project and consequently applied for funding under the Petroleum Environmental Cleanup Fund Act (PECFA), an Act creating a State fund managed by the Department of Commerce (DOC) to reimburse owners who remediate contaminated land. Anxious to begin the road improvements, the DOT arranged to serve as Bean's agent for the cleanup, financing and managing the cleanup process and thereafter receiving reimbursement under PECFA for the cleanup costs.

During this time, James Peterson Sons, Inc. (Peterson), was a state contractor working on an unrelated highway project near the contaminated site. In order to avoid a lengthy bidding process and expedite the remediation project, the DOT asked Peterson to serve as contractor for the remediation and issued a change order directing Peterson to hire CleanSoils as the subcontractor. Although Peterson was technically the contractor for the remediation, Peterson was not involved in the actual cleanup. As the subcontractor, CleanSoils' work was directed and supervised by CWE and the DOT.

As the cleanup progressed, CleanSoils discovered that the contamination affected far more land than the original contract allowed. CleanSoils consequently requested a change order to complete the project and remediate the additional soil. Believing CWE to be acting as the DOT's agent, CleanSoils obtained approval for the change order from CWE. After the work was completed, however, the DOT disputed the approval of *605 the additional work and argued that CleanSoils had not adequately performed the remediation. The DOT thereafter severed all relations with CleanSoils and contracted elsewhere for completion of the remediation project.

Peterson, relying on a "pay when paid" provision of its contract with CleanSoils, declined to pay CleanSoils because Peterson had not been paid by the DOT. Clean-Soils consequently filed suit against the various parties, excluding the DOT and DOC and, pursuant to § 16.007, Stats., filed a claim against the DOT with the claims board. After denial of its claim by the claims board, CleanSoils arranged for 1997 Senate Bill No. 442, authorizing payment to CleanSoils, to be introduced in the legislature. The legislature, however, never acted on the bill before its March 26, 1998 adjournment. CleanSoils thereafter amended its complaint to include its claim against the DOT and DOC. Subsequently, Peterson, Bean and Employers Insurance of Wausau filed a cross-claim against the State for indemnification of the amounts sought by CleanSoils.

The circuit court, holding that the State had waived its sovereign immunity and consented to suit under the theories of unjust enrichment and breach of implied contract, denied the State's motion to dismiss.

II. ANALYSIS

Where the underlying facts are essentially undisputed, an appeal of an order denying a motion to dismiss for lack of personal jurisdiction based on sovereign immunity is a question of law that we will review without deference to the trial court. See Elliott v. Donahue, 169 Wis. 2d 310, 316, 485 N.W.2d 403, 405 (1992).

*606 A. CLEANSOILS AND THE STATUTORY CONDITIONS PRECEDENT

Article IV, § 27, of the Wisconsin Constitution, also known as the sovereign immunity clause, states: "The legislature shall direct by law in what manner and in what courts suits may be brought against the state." State v. P.G. Miron Constr. Co., 181 Wis. 2d 1045, 1052, 512 N.W.2d 499, 503 (1994). The Miron court noted that "[t]his language has been construed repeatedly to mean that the legislature has the exclusive right to consent to a suit against the state." Id. The Miron court further recognized that, "the state has 'consented' to suit with the establishment of a specific claims procedure," under §§ 16.007 3 and 775.01, 4 Stats. Id. at 1053, 512 N.W.2d at 503. Under § 16.007:

*607 [A] party may present a claim to the state claims board, which first holds a hearing and then makes a recommendation to the legislature to grant or deny the claim.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Weis v. Board of Regents of the University of Wisconsin System
837 F. Supp. 2d 971 (E.D. Wisconsin, 2011)
Abbott v. Marker
2006 WI App 174 (Court of Appeals of Wisconsin, 2006)
Koshick v. State
2005 WI App 232 (Court of Appeals of Wisconsin, 2005)
Panzer v. Doyle
2004 WI 52 (Wisconsin Supreme Court, 2004)
Brown v. State
602 N.W.2d 79 (Court of Appeals of Wisconsin, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
599 N.W.2d 903, 229 Wis. 2d 600, 1999 Wisc. App. LEXIS 803, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cleansoils-wisconsin-inc-v-state-of-wisconsin-department-of-wisctapp-1999.