Claybourn Corp. v. Cuneo Press, Inc.

27 F. Supp. 231, 1939 U.S. Dist. LEXIS 2862
CourtDistrict Court, N.D. Illinois
DecidedApril 8, 1939
DocketNo. 41918
StatusPublished
Cited by1 cases

This text of 27 F. Supp. 231 (Claybourn Corp. v. Cuneo Press, Inc.) is published on Counsel Stack Legal Research, covering District Court, N.D. Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Claybourn Corp. v. Cuneo Press, Inc., 27 F. Supp. 231, 1939 U.S. Dist. LEXIS 2862 (N.D. Ill. 1939).

Opinion

WOODWARD, District Judge.

This case was once tried before a jury. A judgment was entered on the verdict for the plaintiff, from which judgment an appeal was taken. The cause was reversed with directions to grant a new trial. Cuneo Press v. Claybourn Corporation, 7 Cir., 90 F.2d 233.

After the case was remanded to the District Court the plaintiff filed an amended complaint. By its amended complaint the plaintiff averred that on April 8, 1931 the plaintiff and defendant entered into a written contract which is hereinafter more particularly referred to. The complaint further averred that the written contract was modified by an oral agreement entered into by the parties in April, 1932. After the alleged modification in April, 1932 the presses were delivered to the defendant and retained by it. The plaintiff seeks to recover the contract price of the presses, together with interest thereon, less certain amounts advanced to plaintiff by the defendant and less certain amounts due by the plaintiff to the defendant on a promissory note.

To this complaint the defendant filed an answer in substance denying that the contract of April 8, 1931 was modified and insisting, by way of recoupment, on damages for breach of warranty.

By stipulation a jury was waived and the cause submitted to the Court -for trial. [232]*232Evidence was heard by the Court, the cause was argued both as to facts and as to law, orally and in writing, and the matter now comes up for decision.

Plaintiff, a Wisconsin corporation, in 1931 and for several years prior thereto, was engaged in the manufacture of printing presses in Milwaukee, Wisconsin. The defendant, an Illinois corporation, during the same period, was engaged in the printing business in Chicago with branches, or wholly owned subsidiaries, located at various points, among others, a plant in Brooklyn, New York.

A contract was entered into by which .the plaintiff was to manufacture, sell and deliver, and the defendant was to buy two printing presses. This contract is evidenced by two letters dated, respectively, April 1, 1931 and April 8, 1931. So far as material to this controversy, the contract may be summarized as follows:

The price of each press was $42,000. Each press was guaranteed to run at a maximum speed of not less than 5500 sheets per hour, with a guaranteed production speed of 4200 sheets per hour of good commercial printing, equal to work then being produced on flat bed types of presses which were then utilized in the printing of Harper’s Bazaar magazine at defendant’s Brooklyn plant. The presses were to be erected and tested on plaintiff’s floor in Milwaukee before shipment and should be subject to inspection by representatives of the defendant, after which they should be crated, loaded on cars and shipped to designation specified by the defendant f. o. b. cars Milwaukee. Plaintiff was to begin shipment about five or six months after the date of the contract. Twenty-five per cent of the purchase price of each press was to be paid when the press was fully erected, tested and inspected on the floor of plaintiff, and the remainder was to be paid after the presses, installed, had attained the speed and quality guaranteed.

Pursuant to the contract the plaintiff proceeded to construct the presses. It had not proceeded far with the construction until it became apparent to the plaintiff that the presses would not attain the speed guaranteed in the contract. During the summer or fall of 1931, at least before the time specified in the contract for the delivery of the presses, the fact was communicated to the defendant that the presses would not operate at 5500 sheets per hour. However, the plaintiff continued with the construction of the presses. During the fall of 1931 and the winter of 1932, conversations were being had between the representatives of the plaintiff and those of the defendant, the purport of which was that the presses would not meet the guaranteed speed. In the meantime the presses had not been delivered, nor were they completed ready for shipment.

Before April 25, 1932 the Brooklyn plant of the defendant had been moved to Philadelphia, Pennsylvania.

On or about April 25 or 26, 1932 a conference was held in the Chicago office of the defendant. Present at that conference were Albert H. Halstead, Jr., and L. W. Claybourn, representing the plaintiff, and John F. Cuneo and J. F. Snyder, representing the defendant.

As the Court understands the testimony of the witness who participated in that conversation, there is no substantial disagreement as to its purport. The plaintiff knew that it could not construct presses which would operate with the speed and quality specified in the original contract of April 8, 1931 and had communicated to the defendant the fact of its inability to comply with the contract. Both the plaintiff and the defendant, the officers of each being experienced and competent business men, knew that the failure of the plaintiff to deliver presses which would meet the guaranty of the contract of April 8, 1931, would subject the plaintiff to damages, probably in a very substantial sum. Up to that time the relations between the parties had been amicable. The plaintiff at that time was, and for many years previous thereto had been, a large and substantial manufacturer of printing presses and machinery used in connection with printing plants. The defendant operated a large printing plant in Chicago and printing plants elsewhere and had been a valued customer of the plaintiff, had large contracts for printing which required printing presses which would operate with speed and efficiency. Having been apprised that the presses contracted for by the contract of April 8, 1931 could not be made to operate at the guaranteed speed, a conference was held in the office of defendant’s president at Chicago to discuss the subject matter of the contract of April 8, 1931 in view of the facts as both parties knew them to exist.

What transpired at this conference between the responsible officers of each company is the crucial point of this lawsuit. [233]*233Both Halstead and Claybourn testified that there was some conversation about damages which the defendant had sustained, or had sustained by reason of the presses not being able to come up to the guaranty. Both Claybourn and Halstead testified that Cuneo said that he could sue the plaintiff for damages, to which the response in substance was that if that were the situation there would be no reason for further conversation. That the subject of damages was discussed is not denied by Cuneo. Whether that happened or not is, so far as the Court views the situation, immaterial. The fact is, however, that Cuneo was in an advantageous position to have made such a statement. The conversation; however, according to Halstead’s testimony, was resumed and Cuneo was advised that the presses had been running 2400 to 2800 sheets an hour. Halstead further testified that the plaintiff did send the presses to Philadelphia on approval. He stated that he said to Cuneo: “If you do not like them (referring to the presses) you can return them and we will refund your money.” (Rec. p. 85.)

The record further shows that Halstead stated; “I said we would do the best we could to get as good quality of production as possible and, if he didn’t like them, (the presses) he could send them back.”

He further stated that Cuneo said: “All right, get them down to Philadelphia as fast as you can.” (Rec. p. 86).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Land O'Lakes Creameries, Inc. v. Commodity Credit Corp.
185 F. Supp. 412 (D. Minnesota, 1960)

Cite This Page — Counsel Stack

Bluebook (online)
27 F. Supp. 231, 1939 U.S. Dist. LEXIS 2862, Counsel Stack Legal Research, https://law.counselstack.com/opinion/claybourn-corp-v-cuneo-press-inc-ilnd-1939.