Clay Island Farms, Inc. v. St. Johns River Water Management District

23 Fla. Supp. 2d 187
CourtState of Florida Division of Administrative Hearings
DecidedJuly 22, 1983
DocketCase No. 82-2517
StatusPublished

This text of 23 Fla. Supp. 2d 187 (Clay Island Farms, Inc. v. St. Johns River Water Management District) is published on Counsel Stack Legal Research, covering State of Florida Division of Administrative Hearings primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Clay Island Farms, Inc. v. St. Johns River Water Management District, 23 Fla. Supp. 2d 187 (Fla. Super. Ct. 1983).

Opinion

OPINION

CHARLES C. ADAMS, Hearing Officer.

[188]*188 RECOMMENDED ORDER

Pursuant to written notice, a Subsection 120.57(1), Florida Statutes, hearing was held before Charles C. Adams, a Hearing Officer with the Division of Administrative Hearings. The initial session of the administrative hearing was conducted on February 28 and March 1, 1983, in the Putnam County Courthouse, 400 St. Johns Avenue, Palatka, Florida. The concluding session of the hearing was conducted on April 5 and 6, 1983, at the St. Johns Water Management District Headquarters on Highway 100 West, Palatka, Florida. This Recommended Order is being entered following the receipt and review of exhibits and excerpts of the transcript of proceedings. The transcript excerpts were filed with the Division of Administrative Hearings on May 18, 1983. The parties, in the person of counsel, have submitted proposed recommended orders with accompanying argument and those materials have been reviewed prior to the entry of the Recommended Order. To the extent that the proposals are consistent with this Recommended Order, they have been utilized. To the extent that the proposals are inconsistent with the Recommended Order for reason of irrelevancy, immateriality, cumulative effect or inadequacy of proof, they are rejected.

ISSUES

The issues presented in this matter concern the request by the Petitioner to be granted a management and storage of surface waters permit by Respondent. Respondent proposes to deny the permit based upon the perception that the activities contemplated by Petitioner: (1) are not consistent, with the public interest as envisioned by Section 373.016, Florida Statutes, and 40C-44.301(l)(b), Florida Administrative Code, (2) are not a reasonable and beneficial activity, per Section 40C-4.301(l)(a), Florida Administrative Code, (3) alter the peak discharge rate of runoff from the proposed activity or the downstream peak stage or duration for the 1 in 10 year design storm, per Section 40C-4.301(3)(a), Florida Administrative Code, (4) cause an increase in velocity or flood stage on lands other than those owned, leased, or otherwise controlled by the applicant for the design storm, per Section 40C-4.301(3)(b), Florida Administrative Code, (5) cause an increase in flow or stage such that it would adversely affect lands other than those owned, leased, or otherwise controlled by the applicant, per Section 40C-4.301(3)(c), Florida Administrative Code.1

[189]*189 FINDINGS OF FACT

A predecessor applicant had requested permission to construct and operate the water management system which is the subject of this controversy. The approximate acreage involved was 197 acres in Lake County, Florida. This acreage and requested activity was subject to the regulatory requirements of St. Johns River Water Management District. Clay Island Farms, Inc., hereinafter referred to as CIF, was substituted for the initial applicant and this matter has been litigated before the Division of Administrative Hearings on the continuing application of the Petitioner. The permit application number is 4-8089. This application was considered with application number 4-8088, pertaining to property owned by A. Duda and Sons, Inc. Subsequently, the latter application shall be referred to as the Duda request for permit.

Certain additional information was sought by Respondent from the applicants, CIF and Duda, in the permit review, by correspondence dated October 2, 1981. A copy of that correspondence may be found as Petitioner’s Exhibit No. 16 admitted into evidence. In particular, CIF was requested to prepare pre and post-development runoff rates in the 1 in 10, 1 in 25, and 1 in 100-year storms, to include stage-storage and stage-discharge rates for any and all retention facilities within the project design. Petitioner’s Compositive Exhibit No. 1 admitted into evidence contains a copy of the engineering report by CIF which are CIF’s responses to the request for information. The date of the engineering report is July 12, 1982.

The CIF application, as originally envisioned, called for the construction of exterior and interior ditches to be placed around a dike of 71 feet of MSL elevation. The dike would enclose a proposed farm operation of approximately 197 acres, should the permit be granted. Within the 197 acre plot, would be found numerous drainage ditches to include major ditches and minor arterial ditches. The purpose of those ditches found in the 197 acres would be to serve as a conveyance for rainfall runoff. The system of conveyance would be connected to an existing conveyance system already in place and related to farm operations of A. Duda and Sons. The runoff would be eventually placed in a retention pond and at times discharged from that retention pond or basin into Lake Apopka by means of gravity flow. The particulars of the development of the 197 acre plot and its service dike, canals, and ditches are more completely described in Petitioner’s [190]*190Exhibit No. 1, which is the engineering report for the surface water management permit application.

The CIF application was reviewed by the staff of the Respondent. Recommendations was made to deny the permit. Details of that denial may be found in Respondent’s Exhibit No. 1. In the face of the denial, CIF requested an administrative hearing. This request was made on August 27, 1982, by petition for formal Subsection 120.57(1), Florida Statutes, hearing to determine Petitioner’s entitlement to the requested permit. St. Johns River Water Management District, in the person of its governing board, determined to refer this matter to the Division of Administrative Hearings to conduct the formal proceeding and the request for the assignment of a hearing officer was received by the Division of Administrative Hearings on September 13, 1982, leading to the final hearing in this cause.

During the course of the final hearing, the CIF permit application was modified in a fashion which reduced the amount of acreage sought for cultivation. Now, approximately 122 acres would be farmed per the amended proposal. A general depiction of the design of the project in its amended form may be found in the engineer’s sheet, which is Petitioner’s Exhibit No. 20 admitted into evidence. When contrasted with the engineering drawings set out in Petitioner’s Compositive Exhibit No. 1, the new design is essentially the same as contemplated in the original permit application, on a lesser scale. Other than dimensions, the basic concepts of the CIF operation would remain the same under the amended proposal.

At present, Petitioner proposes to remove the vegetation which covers the subject 122 acre plot and to conduct a muck farming operation. That vegetation is mostly mixed hardwood with the primary species being red maple. The soil in this area is constituted of monteverde muck, which is conducive to the production of corn and carrots, the crops which Petitioner would plant. To prepare the land for the operation, the system of ditches, dikes and canals described would be installed following the cleaning, draining, and leveling of the 122 acres. Petitioner’s Exhibit No. 10 admitted into evidence depicts land which has been cultivated and the subject 122 acres in its undisturbed state. Petitioner’s Exhibit No. 4 admitted into evidence shows the overall CIF area to include the 122 acres.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
23 Fla. Supp. 2d 187, Counsel Stack Legal Research, https://law.counselstack.com/opinion/clay-island-farms-inc-v-st-johns-river-water-management-district-fladivadminhrg-1983.