Clarke Contracting Co. v. City of New York

182 A.D. 835, 170 N.Y.S. 136, 1918 N.Y. App. Div. LEXIS 4994

This text of 182 A.D. 835 (Clarke Contracting Co. v. City of New York) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Clarke Contracting Co. v. City of New York, 182 A.D. 835, 170 N.Y.S. 136, 1918 N.Y. App. Div. LEXIS 4994 (N.Y. Ct. App. 1918).

Opinion

Smith, J.:

This action is brought for damages against the defendant for a breach of contract. The counterclaim is for damages claimed to have been suffered by the defendant for a breach of the same contract claimed to have been committed by the plaintiff. The contract undertaken by the plaintiff’s assignor was in loading and trimming deck scows, deep sea dumpers and other vessels used for the receipt and transportation of ashes, street sweepings and rubbish in the borough of Manhattan at fourteen water front dumps of the department of street cleaning. The contract called for the payment by the plaintiff of the weekly sum of $1,401.21 after January 2, 1914, when the contract was to go into effect. It was recited that a consideration for this should be the privilege granted to the contractor to pick over, sort, reclaim and appropriate from the materials handled whatever it might deem of value for a period of three years from January 2, 1914, with a right to the city to renew the contract for another period of two years. The plaintiff was required to make a deposit of $15,000, and the recovery of that deposit is a part of the relief asked for. The contract was made on August 12, 1913, although it was not to go into effect until January 2, 1914. This contract was assigned by the contractor to the plaintiff, which entered upon the performance thereof on January 2, 1914, and continued therein until April eleventh of that year, at which time the plaintiff gave to the defendant a notice of its rescission of the contract.

First. The first ground' upon which plaintiff bases its right of rescission is for the failure of the city to furnish the plaintiff fourteen water front dumps at the date that the plaintiff was to enter upon the performance of the contract. In the information to bidders, there were fourteen dumps stated to be the water front dumps of the city. The contract was made on August twelfth. At that time there were three of those water front dumps that could not be used, but were in the process of repair. These were out of repair by reason of fires, which had occurred prior thereto. In the proposals for bids or estimates it was stated: Bidders must satisfy themselves by personal examination and by such other means as they may select as to the quality, quantity and nature of the work to be [838]*838done under this contract and as to the value of the privilege involved and shall not at any time after the submission of a bid or estimate dispute or complain of the foregoing statements as to the amounts or kinds of materials to be handled or assert that there was any misunderstanding in regard to the nature and kind of the work to be done or in regard to the value of the said privilege.”

The plaintiff made personal examination and discovered that these three dumps were not in condition for use but were in process of repair. The plaintiff claims that it was told that the repairs would be completed before January second, when work was to be commenced under the contract. The trial judge submitted to the jury whether those repairs were made with reasonable diligence by the city, and the jury has found that they were. It is further provided in the specifications: The Commissioner may cause any water-front dump to be temporarily closed for the purpose of necessary dredging, or for the purpose of needed repair to the dumping structure, and he may cause the diversion of the material ridden to such closed dump to be diverted to another dump, and the said temporary closing of the dump and diversion of material shall not be taken as a basis for a claim by the Contractor for damages or for prospective profits or for any other reason.”

The contention of the plaintiff is that this provision in the contract refers only to dumps that shall be found in need of repairs after January 2, 1914. The trial court has held, however, that the city was not required to have these dumps in condition upon January 2, 1914, provided the city had used reasonable diligence to put them in condition for use. With this construction of the contract we are fully in accord. Whether or not this special provision in the contract refers to dumps that became out of repair prior to January second, with full knowledge of the plaintiff of the conditions existing upon August twelfth, we are of opinion that the city has in this respect violated none of its obligations assumed in the contract to such an extent as to authorize plaintiff to rescind the contract.

The city was undoubtedly bound after January 2, 1914, to furnish to the plaintiff such dumps as reasonably could [839]*839be substituted for the dumps that were out of repair. One of the plaintiff’s complaints is that the city was to furnish dumps which would give to the plaintiff equal facilities for obtaining the pickings from the ashes and rubbish that were dumped, and that in place of the dumps which were thus withheld for necessary repairs, the city furnished only cellar dumps and inferior dumps, by reason of which the plaintiff was deprived of a large part of the value of its contract because of the impossibility of reclaiming and appropriating the pickings and the material from said dumps. But the city had no other water front dumps which could be furnished, except those which were withheld for necessary repairs. This was known to the plaintiff, as the manager of the plaintiff, Dewilde, had formerly been in the employ of the city and had full knowledge of existing conditions. When, therefore, it was stipulated that the refuse and ashes should be ridden to other dumps, the city might use such other dumps as it could find, giving to the plaintiff the right to the pickings from those dumps wherever they might be found. It is not shown that the city had other or better dumps which it could have furnished to the plaintiff as substitute dumps. There was nothing in the contract compelling them to furnish water front dumps in substitution, and in view of all these conditions known to the plaintiff, the city could not be charged with default in furnishing cellar dumps or other dumps, provided it furnished the best dumps available for the purposes of the contract.

Second. Another complaint, upon which the plaintiff strongly relies, is that there were furnished for the carrying off of these ashes what were called sea dumpers,” instead of deck scows,” and that the plaintiff was deprived, therefore, of from twenty-five to thirty per cent of the value of its right of picking because of the construction of these sea dumpers as not furnishing the opportunity for picking that could be had upon the deck scows. The contract stated that it was the purpose of the contract to provide for the loading and trimming of the deck scows, dumpers and other vessels at the water front dumps of the department of street cleaning in the" borough of Manhattan. There is no provision in the contract that deck scows should be furnished either exclusively or mainly. [840]*840It may be that standing alone this privilege of picking would imply an obligation upon the part of the city to furnish within reasonable limits the best scows upon which the picking could be had. It had been the custom to furnish deck scows instead of the deep sea dumpers, except in case of emergency. Ashes and rubbish put upon these deck scows were taken to Hiker’s island and there placed for the purpose of filling in,” while these deep sea dumpers were used for the purpose of taking the refuse far out into the ocean, which they were required to do before the rubbish could be dumped.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Harding v. Austin
93 A.D. 564 (Appellate Division of the Supreme Court of New York, 1904)

Cite This Page — Counsel Stack

Bluebook (online)
182 A.D. 835, 170 N.Y.S. 136, 1918 N.Y. App. Div. LEXIS 4994, Counsel Stack Legal Research, https://law.counselstack.com/opinion/clarke-contracting-co-v-city-of-new-york-nyappdiv-1918.