Clarke Contracting Co. v. . City of New York

128 N.E. 241, 229 N.Y. 413, 1920 N.Y. LEXIS 695
CourtNew York Court of Appeals
DecidedJuly 7, 1920
StatusPublished
Cited by13 cases

This text of 128 N.E. 241 (Clarke Contracting Co. v. . City of New York) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Clarke Contracting Co. v. . City of New York, 128 N.E. 241, 229 N.Y. 413, 1920 N.Y. LEXIS 695 (N.Y. 1920).

Opinions

Hiscock, Ch. J.

The plaintiff is the assignee of a contract made with the city of New York. The purpose *415 of this contract as stated therein was “ to provide for the loading and trinrming of the deck scows, dumpers and other vessels at the water front dumps of the Department of Street Cleaning in the Borough of Manhattan, of the ashes, rubbish and street sweepings delivered at said, dumps ” for the term of three years commencing January 2, 1914, with the right of renewal. In addition to fmnishing the labor necessary for loading and trimming the various vessels by which this material was to be taken to sea or to the appointed dumping ground, the contractor was to pay the sum of $1,401.21 a week for the privilege. The consideration and benefit secured from the city in return for the performance of this labor and the payment of this sum was the privilege to pick over the ashes, rubbish, etc., and reclaim therefrom certain articles. Only a few of the provisions of this contract are material in the present controversy.

There is no question but that under the contract the city primarily agreed to furnish fourteen specified dumps at which this material should be delivered, picked over and loaded by the contractor on the vessels which were to transport it and which were operated by another and independent contractor. This was held by the trial court as matter of law. There were contained, however, the further clauses that these dumps might “ be increased by not more than two, and the commissioner might (may) change the location of any water front dump to any other location in the said Borough, which in his judgment the interests of the Department or The City shall require; ” also that “ The Commissioner may cause any water front dump to be temporarily closed for the purpose of necessary dredging or for the purpose of needed repair to the dumping structure and he may cause the diversion of the material ridden to such closed dump to be diverted to another dump;” and also that the material delivered at the dump should be loaded and trimmed on deck scows, dumpers and other vessels at the water front *416 dump,” furnished, as already stated, by another contractor.

As a matter of fact the city under its contract did not furnish for use by the contractor in picking and loading and trimmming, and make deliveries at, the fourteen water-front dumps as it agreed to. Owing to various mishaps, at the time the contract went into operation it was able to furnish only ten of these, supplying in the place of three of those originally specified, dumps located at other points and of a character less advantageous for the contractor in his work, and in the place of another one supplying no .dump but diverting the ashes, etc., to a private dump. The city undertook to repair and replace the lacking dumps, and three of them ultimately, but after the rescission of the contract hereinafter mentioned, were made fit for use.

Of the vessels which were to be provided for loading and trimming those designated as dumpers,” and which were used for dumping at sea, were less advantageous and convenient for the contractor than scows which were used for conveying material to the various dumping grounds. It was and is the claim of the plaintiff that defendant supplied it with a much larger proportion of dumpers than was permissible under its contract.

Notwithstanding plaintiff’s claim of - default upon the part of the city in the two respects above mentioned, it entered upon and continued in the performance of the contract from January second to April eleventh, fully performing its work of loading and trimming at the water fronts which were furnished and making its weekly payment of $1,401.21. It did this, however, under protest, each week serving upon the proper official a written notice in effect calling to his attention and notifying him that the city had failed to furnish specified dumps and was using unauthorized dumpers, depriving plaintiff of its rights under the contract, causing it substantial loss, and that it reserved all rights, claims and privileges *417 under its contract for loss or damage arising out of the breach of the contract, and on April eleventh it served upon said official a notice that it elected to rescind its contract upon the ground that the city had made breach thereof and had substantially impaired its rights and rendered performance impossible.

When thereafter it brought this action based on such rescission it originally claimed damages aggregating a large amount for breach of the entire contract extending over three years. On the trial of the case, however, by acquiescence in the rulings of the court as well as by its own attitude it limited its claim to a right to recover with interest the sum of $15,000 deposited as security for the performance of its contract and the damages which it had suffered by reason of the alleged default of the city during the period which intervened the commencement of work under the contract and the rescission.

The trial court in ruling upon plaintiff’s claims held as matter of law that it had established no claim to damages because of 'failure to supply proper vessels for loading and trimming. I agree with this disposition and shall dismiss this feature with the brief statement that in my opinion however much plaintiff’s expectations may have been disappointed, it entirely failed to produce any evidence from which a jury could say 'that the city had violated its contract by furnishing more dumpers than was proper.

In respect of the other claim predicated upon failure to furnish dumps, the court held that under the clause relating to repairs already quoted, the city at the very inception of performance under the contract could withhold dumps for repairs, and charged that if these repairs were then effected with reasonable diligence there could be no recovery. In the second place it peimitted the jury to say, if it found against the defendant on the preceding question, that the failure to furnish four *418 dumps out of fourteen was not a substantial failure of performance or material breach of the contract upon the part of the city and, therefore, could be disregarded and a verdict rendered in its favor. Thus there were presented the questions whether the failure to furnish dumps when the contract called for performance could be excused under the repair clause and, second, whether failure to furnish the same could be disregarded as inconsequential. Since the trial court permitted the jury to find the verdict which it subsequently did find in favor of the defendant upon either theory, if either theory was incorrect the judgment must fall provided the questions are open to our consideration. While the correctness of these rulings of the court perhaps was not challenged in as plain or precise a manner as might have been done, still taking into account the entire charge of the court which stated various propositions in favor of the plaintiff, and the exceptions which were taken to the charge as made and the various refusals to charge, I think the questions are fairly within our consideration, and entertaining this view I reach the conclusion that the court ruled erroneously upon both propositions.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Markham Gardens L.P. v. 511 9th LLC
38 Misc. 3d 325 (New York Supreme Court, 2012)
National Medical Health Card Systems, Inc. v. Fallarino
21 Misc. 3d 304 (New York Supreme Court, 2008)
Hayduk v. Rent-All Uniforms Co.
203 A.D.2d 104 (Appellate Division of the Supreme Court of New York, 1994)
Southland Corp. v. Mir
748 F. Supp. 969 (E.D. New York, 1990)
Trapkus v. Edstrom's, Inc.
489 N.E.2d 340 (Appellate Court of Illinois, 1986)
Picotte Realty, Inc. v. Gallery of Homes, Inc.
66 A.D.2d 978 (Appellate Division of the Supreme Court of New York, 1978)
Cycleway, Inc. v. Kawasaki Motors Corp., U. S. A.
77 Misc. 2d 829 (New York Supreme Court, 1974)
Collins v. Sears, Roebuck & Co.
321 A.2d 444 (Supreme Court of Connecticut, 1973)
Coughlin v. Blair
262 P.2d 305 (California Supreme Court, 1953)
Peaslee v. Press Ass'n Compilers, Inc.
168 Misc. 126 (Appellate Terms of the Supreme Court of New York, 1938)
Rubel Corp. v. Rosoff
248 A.D. 826 (Appellate Division of the Supreme Court of New York, 1936)
Smith v. Johannsen
199 A.D. 823 (Appellate Division of the Supreme Court of New York, 1922)

Cite This Page — Counsel Stack

Bluebook (online)
128 N.E. 241, 229 N.Y. 413, 1920 N.Y. LEXIS 695, Counsel Stack Legal Research, https://law.counselstack.com/opinion/clarke-contracting-co-v-city-of-new-york-ny-1920.