Clark v. Hansen

206 P. 808, 35 Idaho 449, 1922 Ida. LEXIS 52
CourtIdaho Supreme Court
DecidedApril 29, 1922
StatusPublished
Cited by4 cases

This text of 206 P. 808 (Clark v. Hansen) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Clark v. Hansen, 206 P. 808, 35 Idaho 449, 1922 Ida. LEXIS 52 (Idaho 1922).

Opinion

RICE, C. J.

This action was brought for the purpose of obtaining an adjudication as to the respective rights of appellant and respondents to the use of the waters of Cedar Creek, in Custer county.

Appellant sets out as a basis for his claim that he is the owner of 525 acres of agricultural lands, arid in character, and requiring the usq of water for the irrigation thereof; that between the years 1889 and 1901, he and his predecessors in interest had appropriated, diverted and beneficially used in irrigation of his land water amounting to 7,025 inches, measured under a four-inch pressure, or 140.5 second-[452]*452feet. Appellant further alleges that on May 31, 1906, the state engineer of the state of Idaho issued to him permit No. 2020, authorizing him to construct certain irrigation works and to divert thereby thirty second-feet of the waters of Cedar Creek for the irrigation of 1,485 acres of land described in said permit; that he has fully complied with the terms and conditions of the permit, so as to entitle him to divert and use thirty second-feet under said permit, with priority as of the date thereof.

Respondents claim under various permits issued to them by the state engineer at various dates subsequent to the date of appellant’s permit No. 2020. They allege that certain of the respondents, prior to May 31, 1911, filed with the state engineer a petition for the cancelation of permit No. 2020, upon the ground that one-fifth of the work provided for in said permit was not done by November 30, 1908, as required by said permit, and also upon the ground that appellant had wholly abandoned his right under permit No. 2020; that upon the hearing the state engineer refused to cancel the permit and this action was begun within ninety days thereafter. Respondents seek by this action to obtain a judgment of the court canceling permit No. 2020, upon the same grounds presented to the state engineer.

The court found that appellant did not “construct or complete the irrigation works or ditch mentioned and described in said permit No. 2020, according to the terms or conditions, or provisions, of said permit, or according to or in compliance with or as required by the law of this state applicable to such permit, and that defendant did not acquire and has not acquired the right to use for any purpose any of the waters of said creek under or by virtue of said permit.” The judgment decreed to appellant the right to the use of 4.1 second-feet of the waters of Cedar Creek, based upon actual diversion and application to a beneficial use, which right is prior in time and superior in right to any decreed to respondents. Respondents were adjudged to have the right to the use of the waters of Cedar Creek in accordance with their various permits. The remaining [453]*453rights awarded to appellant were of a date subsequent to the rights decreed to respondents.

The appeal is from the order of the court denying a new trial.

Appellant makes thirteen specifications of error. Aside from those hereafter considered, they all relate to the sufficiency of the evidence to support the findings of the court. It is sufficient to say that in all matters referred to, there was substantial evidence to support the findings and they will therefore not be disturbed.

Appellant insists that the court erred in making its finding that he did not construct or complete the irrigation works or ditch mentioned in permit No. 2020 in accordance with the provisions of the permit or in compliance with the statutes of the state.

The law in force at the time the permit was issued is found in Sess. Laws 1905, page 357 et seq. The law contains the following provision: “In his indorsement of approval on any application, the state engineer shall require that actual construction work shall be completed within a period of five years from date of such approval, and that one-fifth of such work of construction shall be done within one-half the period of time allowed for the completion of such works.”

And further provides: “The holder of any permit who shall fail to comply with the provisions of this section within the time or times specified, shall be deemed to have abandoned all right under his permit.”

At the time the permit was granted, about two miles of canal was constructed and was to become a portion of the completed works under the permit. Appellant testified that he expended, in two and one-half years, or one-half of the five-year period, about $800 in labor, repairing and enlarging the portion of the ditch which was already completed. The evidence showed that no serious attempt at construction was begun until April, 1911. Appellant testified that the new portion of the work was completed at a cost to him of something over $21,000. It is clear that [454]*454the evidence showed that one-fifth of the new construction was not performed within two and one-half years after the issuance of the permit.

At the time respondents instituted the contest before the state engineer for the cancelation of permit No. 2020, the law governing the procedure in such cases is found in Séss. Laws 1909, page 299. It would appear from the showing made in this ease that respondents were entitled to a cancelation of the permit on account of the failure of appellant to complete one-fifth of the work of construction within one-half of the period allowed for the completion of the entire work, unless appellant was entitled to credit for the portion of the ditch already constructed when the permit was issued. In the eases of Joyce v. Rubin, 23 Ida. 296, 130 Pac. 793, and Newport Water Co. v. Kellogg, 31 Ida. 574, 174 Pac. 602, it was held that one who had obtained a water right for the diversion and application of water to a beneficial use did not waive his priority or his right by subsequently posting a notice or applying for a permit and perfecting a record in the office of the state engineer. The law in force at the time the permit was issued, however (Sess. Laws 1903, p. 223), contained the following provision: “Whenever it shall be desired to enlarge or extend existing works, or complete works not completed on the date set for such completion, all applications for a permit to make such enlargement, extension or completion shall be filed with the state engineer, the same as for original construction, and the priority of all rights resulting from such enlargement, extension or completion shall relate to such application.”

This provision of the statute is still the law, and is found in C. S., sec. 5575. While, therefore, one does not waive his pre-existing rights by applying to the state engineer for a permit to enlarge or extend existing works, under the statute the permit must be issued for the enlargement or extension and fix the time for the completion thereof. Under this' statute, one to whom a permit for extension or enlargement is issued must complete one-fifth of such extension or enlargement within one-half of the time granted [455]*455for the completion of the works, and cannot claim credit for the construction already done at the time the permit was issued.

Under the statutes above quoted, the evidence adduced at the trial was sufficient to sustain the finding that appellant failed to construct the works in compliance with permit No. 2020 or with the statutes in force at the time.

It is contended further that the court erred in failing to find on the water rights acquired by purchase from the various parties as shown by the record.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Pocatello v. Idaho
275 P.3d 845 (Idaho Supreme Court, 2012)
Syster v. Hazzard
229 P. 1110 (Idaho Supreme Court, 1924)
Basinger v. Taylor
211 P. 1085 (Idaho Supreme Court, 1922)

Cite This Page — Counsel Stack

Bluebook (online)
206 P. 808, 35 Idaho 449, 1922 Ida. LEXIS 52, Counsel Stack Legal Research, https://law.counselstack.com/opinion/clark-v-hansen-idaho-1922.