Opinion
This is an action for the conversion of wood and sawed lumber. On April 12, 1917, Clark executed a bill of sale in familiar form of “all the standing timber” on a designated lot of Clark’s land in Framingham, “said Aldrich to have 2% years to cut and remove said timber, and during said time to have use of part of the pasture adjoining, not exceeding one acre, to pile lumber on, and to have a free passage to said state road.” Aldrich cut all the timber within the time limit, but at the expiration of the 2J/2-year period there were still on Clark’s land .about 425 cords of wood, 25 cords of slabs,' and 150,000 feet of sawed lumber. Clark thereupon claimed that the wood and lumber were forfeited to him by reason of Aldrich’s failure to remove them from his land within the 2%-year period. He excluded Aldrich from his premises and, as is conceded, converted the wood and lumber to his own use. The District Court, On the plaintiff’s motion, [942]*942directed the jury to return a verdict for the plaintiff, and submitted the case to the jury for assessment of damages, instructing the jury that, in order to avoid multiplicity of actions, they were also to assess such damages, if any, as the defendant suffered by reason of the plaintiff’s failure to remove his property from the defendant’s land on or before the agreed date, October 12, 1919, and for his failure to store his property upon the agreed lot and to leave the premises in such condition as it was agreed that they should be left in.
Most of the cases cited by the defendant’s learned counsel have on fair analysis no application to this case. We have no occasion to undertake to reconcile the numerous and somewhat conflicting rulings as to contracts for the cutting and removal of timber; it is enough to note that the overwhelming weight of authority applicable to such a contract as'was .made,by these parties is in support of the view taken by the court below. See Wimbrow v. Morris, 118 Md. 91, 84 Atl. 238, 47 L. R. A. (N. S.) 882, and note, in which most of the authorities are reviewed. On page 888, in this note, it is stated:
“It seems to be tbe rule, even In those jurisdictions which hold that all the rights of the parties to the timber terminated at the expiration of the time limit, if the timber is manufactured in to lumber, tbe owner of the timber does not lose his right thereto by the expiration of the time limit.”
See, also, Fletcher v. Livingston, 153 Mass. 388, 390, 26 N. E. 1001; Claflin v. Carpenter, 4 Metc. (Mass.) 580, 38 Am. Dec. 381; Giles v. Simonds, 15 Gray (Mass.) 441, 77 Am. Dec. 373; Drake v. Wells, 11 Allen (Mass.) 141 (Hill v. Hill, 113 Mass. 103, 105, 18 Am. Rep, 455; United Society v. Brooks, 145 Mass. 410, 14 N. E. 622.
There is no “Massachusetts rule” that supports the defendant’s position in this case.
The judgment of the District Court is affirmed, with costs to the defendant in error.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
278 F. 941, 1922 U.S. App. LEXIS 2894, Counsel Stack Legal Research, https://law.counselstack.com/opinion/clark-v-aldrich-ca1-1922.