Clark County School District v. Rolling Plains Construction, Inc.

16 P.3d 1079, 117 Nev. 101, 117 Nev. Adv. Rep. 10, 2001 Nev. LEXIS 9
CourtNevada Supreme Court
DecidedFebruary 5, 2001
Docket33283
StatusPublished
Cited by7 cases

This text of 16 P.3d 1079 (Clark County School District v. Rolling Plains Construction, Inc.) is published on Counsel Stack Legal Research, covering Nevada Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Clark County School District v. Rolling Plains Construction, Inc., 16 P.3d 1079, 117 Nev. 101, 117 Nev. Adv. Rep. 10, 2001 Nev. LEXIS 9 (Neb. 2001).

Opinion

OPINION

Per Curiam:

In this case, Clark County School District (“CCSD”) breached its contract with general contractor Richardson Construction Company (“Richardson”), thereby causing Richardson to breach its contract with subcontractor Rolling Plains Construction, Inc. (“Rolling Plains”). In subsequent arbitration proceedings involving all of these parties, the arbitrator awarded Rolling Plains its attorney fees as consequential damages for Richardson’s breach of contract. The arbitrator also found that CCSD was responsible for the fees expended by Richardson in connection with Rolling Plains’ arbitration claims and other damages. The issues presented here are whether CCSD can be held responsible for these attorney fees because: (1) it was foreseeable that CCSD’s breach would result in Richardson’s breach of its contract with Rolling Plains, and (2) attorney fees are a valid form of consequential damages. We conclude that the arbitrator’s decision was not a manifest abuse of discretion, and so affirm the district court’s order confirming the arbitration award.

FACTS

Clark County School District entered into a contract with Richardson Construction Company whereby Richardson was to *103 perform services as a general contractor for specific retrofit and reconstruction work to Basic High School. Richardson then subcontracted with Rolling Plains Construction to perform the fireproofing improvements at the school.

A controversy between the parties arose when CCSD refused to pay for additional work it ordered Richardson to provide, including certain fireproofing performed by Rolling Plains. Rolling Plains had already completed the work for Richardson, but reserved its right to claim additional compensation associated with the performance of work outside the scope of its subcontract. When the payment issue went unresolved, Rolling Plains commenced proceedings against Richardson with the American Arbitration Association (“AAA”), as was required in the contract as a prerequisite to litigation.

The arbitration demand by Rolling Plains included an attempt to enforce a subcontract agreement which stated that the prevailing party in any dispute between Richardson-Rolling Plains would be awarded “all reasonable attorney fees, costs and expenses incurred in enforcing or attempting to enforce any of said subcontract’s provisions.” Richardson then joined CCSD as a party in the arbitration under the provisions of the CCSD-Richardson contract.

Following the arbitration hearing, the arbitrator issued an award, opinion, and order concluding that CCSD breached its agreement with Richardson, which in turn caused Richardson to breach its agreement with Rolling Plains. As a result of the determination, the arbitrator held that Rolling Plains’ damage award of $168,142.09 against Richardson, which included attorney fees, was to be paid in part by CCSD since CCSD was found to be the cause of Richardson’s breach with Rolling Plains. 1

The district court confirmed the award and this appeal followed.

DISCUSSION

In Nevada, both “[cjommon law grounds and statutory grounds exist for the review of arbitration decisions.” Graber v. Comstock Bank, 111 Nev. 1421, 1426, 905 P.2d 1112, 1115 (1995). As to statutory law, an arbitration decision can be reviewed and vacated, pursuant to NRS 38.145, for a variety of reasons, including instances in which the arbitrator has exceeded his power or shown a propensity for misconduct.

*104 Under common law grounds, we have held that an arbitration award may be reviewed in order to determine whether the arbitrator’s decision represents a “manifest disregard of the law.” See Graber v. Comstock Bank, 111 Nev. at 1426, 905 P.2d at 1115. This court has defined the “manifest disregard” standard as error that is “obvious and capable of being readily and instantly perceived by the average person qualified to serve as an arbitrator.” Graber, 111 Nev. at 1426, 905 P.2d at 1115 (quoting Williams v. Cigna Financial Advisors Inc., 197 F.3d 752, 762 n.2 (5th Cir. 1995)) (citation omitted). Or, in other words, it is a decision that is “arbitrary, capricious, or unsupported by the agreement.” Wichinsky v. Mosa, 109 Nev. 84, 89, 847 P.2d 727, 731 (1993) (citing Exber, Inc. v. Sletten Constr. Co., 92 Nev. 721, 731, 558 P.2d 517, 523 (1976)).

However, it should be noted that “[r]eview under the manifest disregard standard does not entail plenary judicial review.” Graber, 111 Nev. at 1428, 905 P.2d at 1116 (citing City of Boulder v. General Sales Drivers, 101 Nev. 117, 694 P.2d 498 (1985)). To the contrary, the standard should direct courts to focus only on arbitration awards which imply that the arbitrator was aware “of clearly governing legal principles but decide[d] to ignore or pay no attention to those principles.” 2 Id. (citing Merrill Lynch, Pierce, Fenner & Smith, Inc. v. Bobker, 808 F.2d 930, 933 (2d Cir. 1986)). Thus, “courts are not at liberty to set aside arbitration awards because of an arguable difference regarding the meaning or applicability of laws.” Id. “A district court’s application of the manifest disregard standard is a legal determination that we review de novo.” Greenberg v. Bear, Stearns & Co., 220 F.3d 22, 28 (2d. Cir. 2000).

In this instance, CCSD contends that the arbitrator’s decision to hold CCSD partially responsible for Rolling Plains’ attorney fees award from Richardson was a manifest disregard of the law, and thus, should be set aside. Specifically, CCSD argues that Nevada recognizes the “American Rule” which prohibits attorney fees from being awarded to the prevailing party absent an agreement, statute, or rule to the contrary. Because the CCSD-Richardson agreement did not contain a fee-shifting provision, CCSD contends that there is no basis for ordering CCSD to pay part of the award. Further, CCSD points to NRS 38.125 and AAA *105 Rule 43 as legal support for the award being prohibited absent an agreement between the parties. 3

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sanzaro v. Ardiente Homeowners Assoc.
Nevada Supreme Court, 2015
Hrpv v. Nevada Property 1
Nevada Supreme Court, 2015
Canyon Constr. Co. v. City of Elko
Nevada Supreme Court, 2015
Thomas v. City of North Las Vegas
127 P.3d 1057 (Nevada Supreme Court, 2006)
California Commercial Enterprises v. Amedeo Vegas I, Inc.
67 P.3d 328 (Nevada Supreme Court, 2003)
Sandy Valley Associates v. Sky Ranch Estates Owners Ass'n
35 P.3d 964 (Nevada Supreme Court, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
16 P.3d 1079, 117 Nev. 101, 117 Nev. Adv. Rep. 10, 2001 Nev. LEXIS 9, Counsel Stack Legal Research, https://law.counselstack.com/opinion/clark-county-school-district-v-rolling-plains-construction-inc-nev-2001.