Clark Construction Group, Inc. v. Eagle Amalgamated Service, Inc.

190 F. Supp. 2d 1077, 2002 U.S. Dist. LEXIS 5598, 2002 WL 480933
CourtDistrict Court, W.D. Tennessee
DecidedMarch 25, 2002
Docket01-2478 DB
StatusPublished

This text of 190 F. Supp. 2d 1077 (Clark Construction Group, Inc. v. Eagle Amalgamated Service, Inc.) is published on Counsel Stack Legal Research, covering District Court, W.D. Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Clark Construction Group, Inc. v. Eagle Amalgamated Service, Inc., 190 F. Supp. 2d 1077, 2002 U.S. Dist. LEXIS 5598, 2002 WL 480933 (W.D. Tenn. 2002).

Opinion

ORDER GRANTING PLAINTIFF’S MOTION FOR PARTIAL SUMMARY JUDGMENT

DONALD, District Judge.

Plaintiff, the Clark Construction Group, Inc. (“Plaintiff’), filed a complaint against Eagle Amalgamated Services, Inc. (“Eagle”) and Capitol Indemnity Corporation (“Capitol”) and moved for partial summary judgment as to the liability of Capitol and Eagle. Capitol and Eagle submitted a joint response to Plaintiffs motion for partial summary judgment.

For the reasons stated herein, the Court GRANTS Plaintiffs motion for partial summary judgment on the issue of liability.

I. Factual Background

Plaintiff alleges that, in February of 1999, Plaintiff entered into a written contract with the City of Memphis and the Memphis Cook Convention Commission (collectively “the Owners”) for the renovation, expansion, and construction (the “Project”) of the Memphis Cook Convention Center in Memphis, Tennessee. The Project included demolition of the Concourse Hall, a structure attached to the existing Convention Center.

On or about February 16, 1999, Plaintiff and Eagle entered into a written subcontract (the “Subcontract”). Under the terms of the Subcontract, Eagle agreed to undertake demolition of the Concourse Hall, as well as other selective demolition and asbestos abatement work at the Project site. Eagle also assumed “the entire responsibility and liability for all work, supervision, labor and materials provided [under the Subcontract].... and other things provided by [Eagle] until final acceptance of the work by the [City of Memphis and the Memphis Convention Center Commission].” (Plaintiffs Mem. in Support of Plaintiffs Mot. for Partial Summ. J. Against Defendants Eagle Amalgamated Services, Inc. and Capitol Indemnity Corp., at Att. F, ¶ 6(a)). Eagle further agreed to defend, indemnify, and hold harmless Plaintiff from and against all “claims, expenses, damages, and losses arising out of its work.” Id. at Att. C, ¶ 45.

On or about March 4, 1999, Capitol Indemnity Corporation (“Capitol”) issued Clark a performance bond (the “Performance Bond”) as required by the Subcontract. The Performance Bond obligated Capitol, as a surety, to assure Eagle’s full and complete performance of the Subcontract. It also required Capitol to hold Plaintiff harmless for any loss, damage, or expense that Plaintiff might incur if Eagle failed to satisfy its contractual obligations.

Eagle retained Engineered Demolition, Inc. (“Engineered Demolition”) to assist with demolition of the Concourse Hall. With its agents and subcontractors, Eagle performed all of the preparatory work associated with the implosion of the Concourse Hall.

On October 10, 1999, Eagle and Engineered Demolition performed the scheduled implosion of the Concourse Hall. This action unexpectedly damaged the adjacent Convention Center. Engineered Demolition employees subsequently left the Project site without participating in the complex clean-up efforts necessitated by the unexpected results of their demolition work. Several months later, Eagle also *1079 abandoned the Project prior to fulfilling the terms of the subcontract.

On October 11, 1999, the Owners informed Plaintiff that it would hold Plaintiff responsible for all costs associated with repairing the damage resulting from the October 10th implosion. Plaintiff claims to have spent over a million dollars addressing damages caused by the demolition work it subcontracted to Eagle.

On October 12, 1999, Plaintiff alleges that it notified Eagle of the Owners’ claims and demanded that Eagle defend, indemnify, and hold Plaintiff harmless from and against all claims, damages, and losses arising from the accident. Eagle rejected Plaintiffs October 12th demand.

On October 18, 1999, Plaintiff notified Capitol of the Owners’ claims and demanded that Capitol fulfill its responsibilities under the performance bond. Capitol rejected Plaintiffs October 18th demand.

On June 20, 2001, Plaintiff filed the instant complaint alleging claims against Eagle and Capitol. Eagle asserted counterclaims against Engineered Demolition alleging that the subcontractor negligently performed the implosion work.

On November 15, 2001, Plaintiff filed a motion for partial summary judgment on the issue of liability. Although the Amended Complaint against Eagle includes claims for breach of contract, negligence, and contractual and common law indemnity, Plaintiff moves for summary judgment against Eagle solely on the question of Eagle’s liability for the contractual indemnity claim. As to Capitol, Plaintiff seeks summary judgment only with respect to liability for breach of the Performance Bond. Eagle and Capitol filed a joint response to Plaintiffs motion for partial summary judgment on January 25, 2002. Plaintiff submitted a reply memorandum on February 7, 2002. Neither Eagle nor Capitol disputes the relevant, material allegations asserted by Plaintiff. Accordingly, the Court accepts the following facts as true for purposes of this motion.

II. Legal Standards

Summary judgment is proper “if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to judgment as a matter of law.” Fed. R.Civ.P. 56(c). In other words, summary judgment is appropriately granted “against a party who fails to make a showing sufficient to establish the existence of an element essential to that party’s case, and on which that party will bear the burden of proof at trial.” Celotex Corp. v. Catrett, 477 U.S. 317, 322, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986).

The party moving for summary judgment may satisfy its initial burden of proving the absence of a genuine issue of material fact by showing that there is a lack of evidence to support the nonmoving party’s case. Id. at 325, 106 S.Ct. 2548. This in turn may be accomplished by submitting affirmative evidence negating an essential element of the nonmoving party’s claim, or by attacking the opponent’s evidence to show why it does not support a judgment for the nonmoving party. 10a Charles A. Wright et al., Federal Practice and Procedure § 2727, at 35 (2d ed. Supp.1996).

In evaluating a motion for summary judgment, all the evidence and facts must be viewed in a light most favorable to the non-moving party. Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 587, 106 S.Ct. 1348, 89 L.Ed.2d 538 (1986); Walborn v. Erie County Care Facility, 150 F.3d 584, 588 (6th Cir.1998). Justifiable inferences based on facts are also to be drawn in favor of the non-movant. Kalamazoo River Study Group *1080 v. Rockwell Intern. Corp.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
190 F. Supp. 2d 1077, 2002 U.S. Dist. LEXIS 5598, 2002 WL 480933, Counsel Stack Legal Research, https://law.counselstack.com/opinion/clark-construction-group-inc-v-eagle-amalgamated-service-inc-tnwd-2002.