Claim of the Estate of Klee v. State

94 Misc. 2d 284, 404 N.Y.S.2d 772, 1976 N.Y. Misc. LEXIS 2891
CourtNew York Court of Claims
DecidedApril 8, 1976
DocketClaim No. 48634
StatusPublished
Cited by4 cases

This text of 94 Misc. 2d 284 (Claim of the Estate of Klee v. State) is published on Counsel Stack Legal Research, covering New York Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Claim of the Estate of Klee v. State, 94 Misc. 2d 284, 404 N.Y.S.2d 772, 1976 N.Y. Misc. LEXIS 2891 (N.Y. Super. Ct. 1976).

Opinion

OPINION OF THE COURT

Jeremiah J. Moriarty, J.

Claimant seeks to recover damages from the State for the wrongful death of her husband, as well as for the conscious pain and suffering he sustained prior to his death. The claim [286]*286was timely filed, and has not been assigned or previously submitted.

The facts are not seriously in dispute. On June 19, 1967, Andrew Klee was employed as a laborer by Secord Bros., Inc., and in the course of his employment on that date, he sustained bodily injuries which resulted in his immediate death, caused by the cave-in of a trench in which he was working.

Secord Bros, as engaged, under contract, by the Erie County Water Authority to install a 20-inch transmission line along the north side of Jewett Holmwood Road, from Chestnut Ridge Road to a point 500 feet west of Timber lake Drive, Town of Orchard Park. Construction began at the westerly terminus of the project, at or near the intersection of Chestnut Ridge Road and Jewett Holmwood Road, and proceeded easterly.

Essentially, the construction entailed the excavation of a trench to a predetermined depth, into which 20-foot sections of the water main were placed. The excavation was accomplished by a power shovel with a 36-inch bucket. The length of the trench was limited to approximately 20 feet at any one time, so that a section of the pipe was lowered into the trench by cable, joined with the previously laid line, and then the trench was back filled before another was started.

This operation was in progress on the date of the accident. Testimony of coworkers of the decedent clearly establishes that no safeguards had been taken, on this day at least, to protect the excavation from a cave-in. In fact, this testimony establishes that cave-ins on the project were commonplace, and that the workers, including the decedent, ignored these conditions in the interest of remaining employed. The contractor employer made it clear "if you do not want to do the work —go home.”, said the witness David McAnulty, sworn by the claimant.

The alleged negligence of the State is couched in the following terms in both the claim and the bill of particulars. "On information and belief, the state of new york was careless and negligent in that its inspectors, officers, agents and employees were aware of the continuous, dangerous and hazardous methods used and the various violations of the Labor Law in the construction of said sewer line, yet they permitted the operation and construction to continue. They failed to properly and adequately stop the construction of said sewer line; failed to properly post signs and warning devices alerting [287]*287people on the said project as to the dangerous conditions; failed to properly and adequately inspect said job and was otherwise careless and negligent.”

At the date of the accident section 241 of article 10 of the Labor Law specifically dealt with excavation work, and provided: "All areas, buildings or structures in which construction, excavation or demolition work is being performed shall be so constructed, shored, equipped, guarded, arranged, operated and conducted by the owners, contractors, and subcontractors as to provide reasonable and adequate protection and safety to the persons employed therein or lawfully frequenting such places. The board may make rules to carry into effect the provisions of this section.”

The board referred to in the statute is the Board of Standards and Appeals of the State of New York, Industrial Code Rule No. 23 (12 NYCRR Part 23), Protection of Persons Employed in Construction and Demolition Work, was adopted by the Board of Standards and Appeals. The pertinent parts of the rule are found in section 23.8: "Excavation, (a) Stability of structures. Where there is any question of stability of structures adjoining or over areas to be excavated, such structures shall be supported where necessary by underpinning, sheet piling, shoring, bracing or other means to prevent injury to any employee, (b) General requirements. (1) No employee shall be permitted to enter any excavated area unless sheet piling, shoring or other safeguard that may be necessary for his protection is provided. (2) Where any employee in an excavation is exposed to the hazard of falling or sliding material from any bank or side more than five feet high above his footing, adequate piling and bracing shall be provided against the bank or side to eliminate such hazard. The excavation shall be checked after every rain storm or other hazard-increasing occurrence and the protection against slides and cave-ins increased if necessary.”

By section 21 of the Labor Law, the Industrial Commissioner is charged with the enforcement of the provisions of the Labor Law and of the Industrial Code, and subdivision 2 of that section provides: "[the Industrial Commissioner] 2. Shall cause proper inspections to be made of all matters prescribed by this chapter or by the industrial code”.

Section 200 of the Labor Law empowers the commissioner, if he finds any place violating these requirements to be in a dangerous condition, to post a notice in the area warning [288]*288persons of the danger. This notice shall prohibit further work in the area until the dangerous condition is corrected and the notice removed.

It is not clear in this record how, or when, the inspection process is initiated in a project such as we have in this situation. In any event, the construction safety inspector for the area, employed by the Department of Labor, learned of it and first visited the site on March 27, 1967. This inspector, Joseph F. Peacock (now retired), entered the employ of the State in 1957. He brought with him a background as a construction foreman in general construction for a period of 11 years, this preceded by other employment and military service. We consider him to be qualified for his duties.

The project had not been started on March 27, 1967; he made further inspections on April 3, April 7, and April 20, 1967, to find nothing had been started. His next inspection was May 26, 1967, at which time he found that work was in progress. His examination revealed an 8-foot deep excavation which was in violation of the code rule. He did not recall, and we do not know, why he made this particular visit to the job site; his best explanation was that it was his routine when he was in the area concerning several other jobs he was carrying, generally 50 in number.

Observing the violation on the morning of May 26, he "tagged the job — shut the job down — nobody works.” On the site, he was in conversation with a member of the Secord family, whom he knew and recognized from other projects of the Secord Bros., and explained the problem. There were no workmen in the trench in the morning. Peacock returned the same afternoon to find no workmen present, that nothing had been done to correct the violation, so he left the tag where it had been placed, and informed Secord he would return on Monday, May 29, warning that no work was to continue until the tag was removed.

Returning on the morning of May 29, he engaged in further conversation with Mr. Secord who asked him what he wanted him to do. Peacock testified he advised the excavation and/or trench had to be protected from a cave-in and outlined the various alternatives set forth in the code rule, that is either by shoring or sloping. Mr. Secord personally operated the equipment that was present and achieved what Mr. Peacock termed a "one on one slope” which he considered to be adequate and safe, and approved.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kalofonos v. State
115 Misc. 2d 692 (New York State Court of Claims, 1982)
Walker v. State
104 Misc. 2d 221 (New York State Court of Claims, 1980)
Dunbar v. United Steelworkers of America
602 P.2d 21 (Idaho Supreme Court, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
94 Misc. 2d 284, 404 N.Y.S.2d 772, 1976 N.Y. Misc. LEXIS 2891, Counsel Stack Legal Research, https://law.counselstack.com/opinion/claim-of-the-estate-of-klee-v-state-nyclaimsct-1976.