CKC Systems, Inc.

CourtArmed Services Board of Contract Appeals
DecidedJune 20, 2019
DocketASBCA No. 61025
StatusPublished

This text of CKC Systems, Inc. (CKC Systems, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CKC Systems, Inc., (asbca 2019).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) CKC Systems, Inc. ) ASBCA No. 61025 ) Under Contract No. SPRPA1-12-C-W008 )

APPEARANCE FOR THE APPELLANT: Ms. Jenny Cheng President

APPEARANCES FOR THE GOVERNMENT: Daniel K. Poling, Esq. DLA Chief Trial Attorney Edward R. Murray, Esq. Trial Attorney DLA Aviation Richmond, VA

SharifT. Dawson, Esq. Trial Attorney Defense Supply Center Philadelphia, PA

OPINION BY ADMINISTRATIVE JUDGE OSTERHOUT

This appeal arises from a contracting officer's termination for default of Contract No. SPRPA1-12-C-W008 (the contract) for containers between CKC Systems, Inc. (appellant or CKC) and the Defense Logistics Agency (the government or DLA). CKC alleges that it should be allowed to continue the contract because it completed the first article test and can complete the contract. The government argues that CKC failed to deliver the containers on time and does not have an excusable delay. The parties have elected to waive a hearing and submit the case upon the record pursuant to Board Rule 11. We deny the appeal.

FINDINGS OF FACT

1. On April 4, 2012, DLA awarded the contract to CKC. The contract required CKC to produce 26 containers, National Stock Number (NSN) 6KH 8145-01-274-3467, at a unit price of$12,614.38 each for a total of $327,973.88 as contra<;:t line item number (CLIN) OOOlAA. (R4, tab 1 at 1-2)

2. The contract required a not separately priced first article test as CLIN OOOlAB (R4, tab 1 at 2). 3. Delivery of the first article was due within 180 days of contract award. Early delivery was authorized. (R4, tab 1 at 2)

4. The contract incorporated Solicitation No. SRPA1-l l-R-W223, CKC's proposal, and the contract award (R4, tab 1 at 1, block 18).

5. The contract included drawing no. 600E001 (R4, tab 1 at 3). The solicitation also included drawing no. 600E001 (R4, tab 6 at 7).

6. Four shock mounts were required as part of the container and listed as part 21 on drawing no. 600EOO 1. The drawings annotated that the shock mounts were part number C635-1A and the manufacturer was Dow Elco. (R4, tab 22 at 3)

7. The drawings instructed:

Each shock mount shall be marked with its manufacturing cure date£l1 (month and year) permanently molded in the top of the mount material so as to be plainly visible when the mount is installed. If mount configuration makes this impossible, the cure date shall be stamped on the top surface of the flexing element using white waterproof ink conforming to A-A-208. Shock mounts shall be no older than one (]) year old when installed in the container.

(R4, tab 22 at 3 n.12) (emphasis added)

8. The drawings directed where CKC was to place the shock mounts by indicating the placement of part 21 (R4, tab 22 at 7).

9. The contract incorporated by reference Federal Acquisition Regulation (FAR) 52.249-8, DEFAULT (FIXED-PRICE SUPPLY AND SERVICE) (APR 1984), which states:

(a)(l) The Government may, subject to paragraphs (c) and (d) below, by written notice of default to the

1 Cure Date - Curing is the heat-induced process whereby the long chains of the rubber molecules become cross-linked by a vulcanizing agent to form three dimensional elastic structures. The Cure Date is the date that the rubber is fully molded in this process. (https://www.colonialseal.com/downloads /press-releases/TAEiastomerCureDates. pdf) 2

I Contractor, terminate this contract in whole or in part if the Contractor fails to:

(i) Deliver the supplies or to perform the services within the time specified in this contract or any extension;

(ii) Make progress, so as to endanger performance of this contract (but see subparagraph (a)(2) below); or

(iii) Perform any of the other provisions of this contract (but see subparagraph (a)(2) below).

(2) The Government's right to terminate this contract under subdivisions (l)(ii) and (l)(iii) above, may be exercised if the Contractor does not cure such failure within 10 days (or more if authorized in writing by the Contracting Officer) after receipt of the notice from the Contracting Officer specifying the failure.

(R4, tab 1 at 14)

10. From February 21, 2013, through February 25, 2013, the government conducted testing on the containers (R4, tab 10 at 2).

11. On September 25, 2013, the government performed additional form and fit tests (R4, tab 10 at 2).

12. In December 2013, the government issued the first article test report, concluding, "Based on the test results, the container has met all the requirements with the exception of Item Inspection and some issues found during the Fit Check" (R4, tab 10 at 2). The issues included the restraint block being "rather tight" and that an installation tool "was not painted a lusterless red" as the contract required (R4, tab 10 at 16). Neither of these inspection results impacted the shock mounts.

13. On January 13, 2014, the contracting officer (CO) issued unilateral Modification No. POOOO 1 (R4, tab 2 at 1). This modification directed changes for CLINs 0001 and OOOlAA. For CLIN OOOlAA, the modification changed the delivery date from December 19, 2013, to May 14, 2015. (R4, tab 2 at 3)

14. On June 10, 2015, the CO issued unilateral Modification No. P00002, referencing a CKC email, dated June 5, 2015. This modification extended the delivery date for CLIN OOOlAA until December 15, 2015, in exchange for a reduction in price of $499.98. (R4, tab 3 at 1-4) The administrative record does not contain the email

3 but because of the reduction in price included in the modification, we find that this delivery date was at CKC's request.

15. On December 3, 2015, the CO issued a cure notice to CKC. The CO outlined the contract and modifications that had taken place to that point. The CO also stated that progress payments in the amount of $100,151.00 had been disbursed under the contract. The CO notified CKC as follows:

[T]he government considers the firm's repeated requests to extend the delivery due date of this contract, in addition to the fact that it is now delinquent on several other contracts, a condition which is endangering the performance of this contract. Therefore, unless this condition is cured within IO days after receipt of this notice, the Government may terminate for default under the terms and conditions of the Federal Acquisition Regulation 52,249-8, entitled "Default", clause of this contract.

(R4, tab 11) The CO required a response by December 14, 2015.

16. On December 14, 2015, CKC responded. CKC stated that the "(g]overnment took an extended approximately 12 months to approve the [first article] due to various reasons." CKC requested an extension until September 29, 2016, and explained that it was delayed due to "[ c]ontingencies that were out of our control" and the fact that the container was the "biggest in size" CKC had contracted to build which made it the "most challenging unit" that it had to build. CKC stated that the contract could be completed, assuming no other unforeseen contingency occurred, "around June 29, 2016 (optimum schedule)." (R4, tab 12)

17. On December 21, 2015, the CO sent a response to CKC concerning various show cause and cure notices. Regarding the contract at issue in this appeal, the CO wrote:

In your response to the CURE Notice dated December 3, 2015, CKC requested a final extended revised delivery date of 29 September 2016 for the 26 units on this contract. Per the teleconference on December 16, 2015 between DLA, DCMA, and CKC, as well as CKC's response to the teleconference in the email dated December 18, 2015, it has been determined that the Government will accept your final revised delivery date of 29 September 2016 for your consideration of I% of the contract value ($3,302.00).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lisbon Contractors, Inc. v. The United States
828 F.2d 759 (Federal Circuit, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
CKC Systems, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/ckc-systems-inc-asbca-2019.