CJ Project Management, Inc. d/b/a CJ Group v. BSPV-Plano, LLC

CourtUnited States Bankruptcy Court, E.D. Texas
DecidedMarch 31, 2025
Docket22-04055
StatusUnknown

This text of CJ Project Management, Inc. d/b/a CJ Group v. BSPV-Plano, LLC (CJ Project Management, Inc. d/b/a CJ Group v. BSPV-Plano, LLC) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, E.D. Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CJ Project Management, Inc. d/b/a CJ Group v. BSPV-Plano, LLC, (Tex. 2025).

Opinion

IN THE UNITED STATES BANKRUPTCY COURT FOR THE EASTERN DISTRICT OF TEXAS SHERMAN DIVISION

IN RE: § § BSPV-PLANO, LLC, § Case No. 22-40276 § (Chapter 11) Debtor. § ____________________________________§ § CJ PROJECT MANAGEMENT, INC., § § Plaintiff, § § v. § Adv. Proc. No. 22-4055 § BSPV-PLANO, LLC, RICHARD SHAW, § and NORTH/SOUTH BUILDING, LLC, § § Defendants. §

MEMORANDUM OPINION AND ORDER

This adversary proceeding arises out of a subcontract between CJ Project Management, Inc. (“CJ”) and North/South Building, LLC (“North/South”) to frame buildings on property owned by BSPV-Plano, LLC (“BSPV” and, together with North/South, the “Defendants’”). CJ initiated this proceeding to resolve the validity and priority of its mechanic’s lien against BSPV’s property, among other things. North/South filed counterclaims against CJ for breach of contract as well as a claim for damages arising from a fraudulent or invalid lien. BSPV and North/South also asserted counterclaims against CJ for damages arising from a fraudulent or invalid lien. The Court, having considered the evidence and arguments presented at a bench trial on October 29- 31, 2024, as well as the record of this proceeding and applicable law, makes the following findings of fact and conclusions of law. I JURISDICTION The Court has jurisdiction over this matter pursuant to 28 U.S.C. §§ 1334(a) and 157(a). This Court has authority to enter final orders in this proceeding because it statutorily constitutes a core proceeding as contemplated by 28 U.S.C. § 157(b)(2)(B) and (K) and meets all constitutional standards for the proper exercise of full judicial power by this Court. All parties

agree to the entry of a final order by this Court. II. RELEVANT PROCEDURAL HISTORY In its complaint, CJ asserted claims for (1) “misapplication of trust funds,” against Richard Shaw, North/South, and BSPV, (2) “statutory retainage and trapped funds” against BSPV and (3) a declaratory judgment that CJ properly perfected mechanic’s liens on BSPV’s property. The Defendants moved for summary judgment on all of CJ’s claims. In its response to the Defendants’ motion for summary judgment, CJ expressly abandoned its claim against Richard Shaw for the misapplication of trust funds. In addition, CJ waived its claim against BSPV for “statutory retainage and trapped funds” by failing to address that claim in response to

the Defendants’ motion for summary judgment. See Keenan v. Tejeda, 290 F.3d 252, 262 (5th Cir. 2002) (noting that “an issue raised in the complaint but ignored at summary judgment may be deemed waived”). On October 29, 2024, the Court entered an order granting the Defendants’ motion for summary judgment, in part. The Court also entered a motion by the Defendants to sanction CJ for the spoilation of evidence on the same date. As a result of the spoilation, the Court presumes that CJ had in its possession, before providing any bid proposals to North/South, sufficient drawing plans and records to show that CJ was bidding to frame 390,000 gross square feet of buildings. The parties entered into a Joint Pretrial Order but most of the facts surrounding CJ’s mechanic’s lien remained disputed. The Court proceeded to trial on (1) CJ’s request for a declaratory judgment that CJ’s claim should be treated as a secured claim in BSPV’s bankruptcy case; (2) North/South’s counterclaim against CJ for breach of contract; and (3) the counterclaims asserted by BSPV and North/South against CJ for filing a fraudulent or invalid mechanic’s lien.

The parties submitted written closing arguments. After receiving the closing arguments, the Court took the matter under advisement in order to prepare this detailed written ruling. III. FINDINGS OF FACT A. The Bridgemoor Project 1. BSPV was formed in May 2018 to acquire, own, develop, and operate a 31.5 acre, “55+” Independent Senior Luxury Apartment Community with 318 units of apartment inventory, that is known and branded as “The Bridgemoor at Plano,” and located at 1109 Park Vista Road in Plano, Texas (the “Project”). 2. The majority of costs for development and construction of the Project were to be financed

through the issuance of private bonds. The Huntington National Bank (“Huntington”) served as the trustee for the bond holders. 3. North/South was the prime contractor to BSPV, performing work under a written prime contract with BSPV. Richard Shaw owns North/South, and Roger Zais was the project manager for the Project. 4. The normal course of funding construction expenses involved North/South compiling receipts, invoices, and applications for payment from subcontractors and submitting these to BSPV for payment. BSPV would then submit the documents to Huntington for review. Upon approval, Huntington would fund BSPV, and BSPV would transfer funds to North/South. North/South, in turn, would pay construction costs. B. The Framing Subcontract 5. Ike Chukwura is the principal, owner, and sole employee of CJ. Mr. Chukwura has a master’s degree in architecture from a Texas university, and he testified that he has

managed and designed construction projects for 20 years. 6. Mr. Chukwura heard from a friend who was a painting subcontractor on the Project that there was an opportunity to apply to subcontract for the framing work. Although Mr. Chukwura had no experience with framing, and no employees, tools or equipment to perform framing work, he met with Mr. Shaw and Mr. Zais to discuss submitting a bid for the framing for the Project. 7. North/South had been in the construction business for many years. North/South generally worked with the same subcontractors on its projects. 8. Mr. Chukwura intended to sub-subcontract the framing work to ReyTex Framing Corp.

(“ReyTex”). Mr. Shaw was aware of ReyTex but had never hired ReyTex for a project. 9. CJ had access to all the architectural drawings before submission of its bid to North/South. The architectural drawings contained the square footage and the total number of buildings from which CJ could observe that the scope of framing involved 417,000 square feet of buildings. The framing would involve several different types of apartment buildings, balconies on the apartment buildings, garages, and a club house, among other things. 10. Page A-2 of the architectural drawings showed the air-conditioned square footage of the apartment buildings, which was 330,073 square feet. Although the air-conditioned square footage was not relevant for framing, it was relevant for other construction purposes. 11. The framing square footage for the Project was not changed, nor were there any material changes in the drawings, plans, or designs which impacted the square footage to be

framed. 12. CJ provided portions of the architectural drawings to ReyTex. ReyTex used those drawings to formulate a bid for the framing work. ReyTex reviewed the documents it received from CJ and concluded the framing would involve 390,000 square feet. ReyTex underestimated the square footage to be framed for the Project because it inadvertently omitted two buildings from its calculation. 13. ReyTex submitted a framing bid to CJ dated October 26, 2018. ReyTex proposed that it would frame the Project for CJ for $1,462,500. 14. On the same day CJ received ReyTex’s bid, CJ submitted a framing bid to North/South.

CJ proposed that it would frame the project for $1,551,353. CJ’s bid was expressly calculated using 330,073 square feet at $4.70 per square foot.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Keenan v. Tejeda
290 F.3d 252 (Fifth Circuit, 2002)
In The Matter Of Fidelity Holding Company, Ltd.
837 F.2d 696 (Fifth Circuit, 1988)
Centurion Planning Corp. v. Seabrook Venture II
176 S.W.3d 498 (Court of Appeals of Texas, 2005)
Williams v. Glash
789 S.W.2d 261 (Texas Supreme Court, 1990)
City of Beaumont v. Excavators & Constructors, Inc.
870 S.W.2d 123 (Court of Appeals of Texas, 1994)
In Re DePugh
409 B.R. 125 (S.D. Texas, 2009)
In Re DePugh
409 B.R. 84 (S.D. Texas, 2009)
Walker & Associates Surveying, Inc. v. Roberts
306 S.W.3d 839 (Court of Appeals of Texas, 2010)
Aland v. Martin
271 S.W.3d 424 (Court of Appeals of Texas, 2008)
Spoljaric v. Percival Tours, Inc.
708 S.W.2d 432 (Texas Supreme Court, 1986)
Wallerstein v. Spirt
8 S.W.3d 774 (Court of Appeals of Texas, 1999)
In Re Ira Haupt & Co.
253 F. Supp. 97 (S.D. New York, 1966)
CVN Group, Inc. v. Delgado
95 S.W.3d 234 (Texas Supreme Court, 2002)
Green International, Inc. v. Solis
951 S.W.2d 384 (Texas Supreme Court, 1997)
De Monet v. Pera
877 S.W.2d 352 (Court of Appeals of Texas, 1994)
Cigna Insurance Co. of Texas v. Rubalcada
960 S.W.2d 408 (Court of Appeals of Texas, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
CJ Project Management, Inc. d/b/a CJ Group v. BSPV-Plano, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cj-project-management-inc-dba-cj-group-v-bspv-plano-llc-txeb-2025.