City-Wide Asphalt Co. v. E. E. Scott Construction Co.

610 S.W.2d 330, 1980 Mo. App. LEXIS 2813
Missouri Court of Appeals·Decided December 2, 1980·No. No. WD 30886·Published·Cited by 4 cases

Opinion

MANFORD, Judge.

This is a direct appeal from a judgment awarding recovery of monies upon a contractor’s performance and maintenance bonds. Two separate actions were originally filed, then consolidated for trial. Trial was had before the court upon written waiver of trial by jury. The judgment is affirmed and remanded with directions.

Review of this cause is made pursuant to Rule 73.01 as interpreted by Murphy [332]*332v. Carron, 536 S.W.2d 30 (Mo.banc 1976), and the judgment will not be set aside unless the judgment is unsupported by substantial evidence; unless the judgment is against the weight of the evidence; unless the judgment erroneously declares the law or unless the judgment erroneously applies the law.

Appellants present nine points of error and while each is addressed by this court, the points presented are, for purposes of disposition, summarized and considered as three because seven of the nine points attack specific findings of fact and conclusions of law entered by the trial court. These referenced seven will be addressed specifically herein, but for purposes of organization of this opinion, these seven points will be viewed as the third or final alleged error. Appellants charge the trial court erred in (1) adopting in total respondents’ proposed findings and conclusions because said findings and conclusions do not address the issue of delay on one of the road projects; because such adoption does not reveal the trial court’s reasoning or basis for its decision; and some of said findings and conclusions are not supported by the evidence; (2) admitting certain oral testimony in that said testimony contradicted the terms of a written assignment and thus violated the parol evidence rule and (3)(a) failing to allow interest at 6% on the amount granted to appellant as a setoff because the parties had stipulated the amount of the setoff and the court under a specific finding had found the amount was liquidated; (b) making its specific finding deducting from the setoff granted appellants the total amount of liquidated damages assessed against respondents in that the evidence supports a finding that appellants were not responsible for any more than half of the assessed liquidated damages involved; (c) in its specific finding denying appellants a setoff in the sum of $1,500 for a field laboratory; (d) in its specific finding which resulted in a deduction of $4,723.70, said amount representing contract backcharges, from the offset granted appellant E. E. Scott Construction Co., Inc., because the evidence did not support said amount of backcharges; (e) in its specific finding which granted judgment against appellant E. E. Scott Construction Co., Inc., in that the evidence showed the parties had reached an accord and satisfaction; (f) in its specific finding that consent and approval by the State Highway Commission of an assignment between the parties did not affect a modification of the contract between the parties and did not discharge the surety on the performance and maintenance bond and finally (g) in its specific finding of failing to grant appellant E. E. Scott Construction Co., Inc., a setoff for damages caused by respondents’ delays.

The parties stipulated to a large portion of the facts and in addition, upon the record, delineated the remaining factual issues in dispute. These disputed issues produced extensive oral testimony and a long list of exhibits.

Before summarizing the disputed issues or disposing of the alleged points of error, it is necessary to identify the parties and their respective roles in this controversy. All parties hereto are corporations authorized to do business in Missouri. Appellant, E. E. Scott Construction Co., Inc., (hereafter referred to as Scott Construction) is an excavating contractor sometimes referred to as a “dirt contractor”. Respondent, City-Wide Asphalt Co., Inc., (hereafter City-Wide) is a producer of asphalt products and an asphalt road paver. Respondent Curb Contractors, Inc. (hereafter Curb) is a specialty contractor which performs finish work such as curbings, drains, etc., along roadways. United States Fidelity and Guaranty Company (hereafter USF&G) is an insurance carrier who provided (as surety) the performance and maintenance bond for Scott Construction. The City of Kansas City, Missouri (hereafter City) was a principal party to one of the paving contracts referred to herein, along with the Missouri Highway Commission (hereafter Commission) who was a principal party to two other paving contracts referred to herein.

The three paving contracts involved three geographical locations and since they are referred to repeatedly herein, they will be [333]*333identified as the “Highway 10 job’ City job” and the “U.S. 40 job”. the

The contested issues are summarized as follows: (a) Was Scott Construction entitled to compensation for ditch liner repair on the Highway 10 job? (b) Was Scott Construction entitled to payment for certain billing on the Highway 10 job? (c) Did Scott Construction provide a field laboratory for which it was entitled to be compensated? (d) Did Scott Construction provide rework-regrading for seeding purposes on the Highway 10 job for which it was entitled to compensation? (e) Was Scott Construction entitled to compensation for labor and supervisor costs for pumping grout on the Highway 10 job? (f) Was City-Wide entitled to deduct any additional backcharg-es from the amount due Scott Construction on the Highway 10 job? (g) Was City-Wide entitled to deduct liquidated damages from the amount due Scott Construction on the Highway 10 job? (h) Was Scott Construction entitled to compensation for one-half of the cost of air-conditioning of the field office on the Highway 10 job? (i) Did City-Wide agree to an assignment from Scott Construction on Scott Construction’s contract with the Commission on the U.S. 40 job? (j) Did City-Wide cause any delays, thus damaging Scott Construction on the U.S. 40 job, and was City-Wide entitled to payment of $285.00 for reinforcing steel?

Scott Construction was a subcontractor and City-Wide was the general contractor on the Highway 10 job. On the City job and the U.S. 40 job, Scott Construction was the general contractor and respondents were subcontractors. This cause was initiated by two separate suits which were consolidated for trial. In their claims, respondents alleged that Scott Construction owed them monies for labor and material furnished on the city job and the U.S. 40 job. USF&G was joined as a party by virtue of its role as surety upon the bond for Scott Construction.

In response, Scott Construction filed its answer, denying that any monies were due and that USF&G had been discharged on the bond as a result of an assignment- of contracts between the parties (without notice to USF&G). In addition, Scott Construction filed a counterclaim for recovery of monies for certain items alleged to have been furnished on the job sites and for damages alleged to have resulted from respondents’ delay in performance.

For purposes of disposition, it is not necessary to recite the thorough and well prepared agreed-to stipulation of facts.

The evidence reveals no dispute regarding the city job, and it was agreed that Scott Construction owed respondent CityWide the sum of $42,322.49, and respondent Curb, $5,868.30. The evidence regarding the Highway 10 job reveals that the reasonable value for labor and material furnished by Scott Construction was $278,478.32.

Free access — add to your briefcase to read the full text and ask questions with AI

City-Wide Asphalt Co. v. E. E. Scott Construction Co., 610 S.W.2d 330, 1980 Mo. App. LEXIS 2813 (Mo. Ct. App. 1980).

610 S.W.2d 330 (City-Wide Asphalt Co. v. E. E. Scott Construction Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Computer Network, Ltd. v. Purcell Tire & Rubber Co.
747 S.W.2d 669 (Missouri Court of Appeals, 1988)
Brummet v. Pope
685 S.W.2d 238 (Missouri Court of Appeals, 1985)
Ahr v. Bradley
665 S.W.2d 626 (Missouri Court of Appeals, 1983)
Arie v. Intertherm, Inc.
648 S.W.2d 142 (Missouri Court of Appeals, 1983)