City Stores Co. v. Gervais F. Favrot Co., Inc.
This text of 359 So. 2d 1031 (City Stores Co. v. Gervais F. Favrot Co., Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
CITY STORES COMPANY (MAISON BLANCHE DIVISION)
v.
GERVAIS F. FAVROT CO., INC.
Court of Appeal of Louisiana, Fourth Circuit.
*1032 Guste, Barnett & Shushan, William M. Barnett, New Orleans, for plaintiff-appellant.
Baldwin, Haspel, Molony, Rainold & Meyer, Robert R. Rainold, New Orleans, and Smith, Currie & Hancock, Bert R. Oastler and Frank E. Riggs, Jr., Atlanta, Ga., for defendant-appellee.
Before STOULIG, BOUTALL and SCHOTT, JJ.
BOUTALL, Judge.
This is an appeal from a judgment homologating, with minor amendment, an award of an arbitration panel determining amounts due on three building contracts to the contractor, Gervais F. Favrot Co., Inc., from the owner, City Stores Company.
The parties entered into three construction contracts involving a warehouse and retail store in the City of New Orleans. The first contract was executed on March 8, 1972 and covered construction of the building and an area up to 5 feet from its outside perimeter. On August 17, 1972, the parties executed a second contract for performance of site work on the facility, much of which had been completed on the date of execution. On June 1, 1973 the parties confected a third contract for work already completely performed on an additional site, called "Parcel Q" which had been acquired subsequent to the first agreement. The second and third contracts incorporated by reference the General Conditions and Specifications of the first contract. However, the first contract obviously did not refer to the other two, nor was it amended to incorporate their provisions by reference.
The contracts were based on a "cost plus" method of payment with a guaranteed maximum price, subject to cost increases occasioned by work changes initiated by the owner during construction. The construction employed the "fast track" method, used for speed of beginning and completion and, in theory, for economy. When this method is used, the owner supplies the contractor initially with uncompleted contract drawings and specifications, upon which the contractor is entitled to rely, and the obligation is placed on the owner to complete the drawings and specifications in a manner consistent with the initial documents, used by the contractor to begin construction.
The basic dispute between the parties arose around the claims of the contractor beyond the contract price and whether the project should be considered as one overall project or three separate projects.
The owner contended the contractor failed to keep its cost records separate on the three contracts and co-mingled its expenditures in spite of the owner's request for separate billings. The contractor allegedly submitted claims for cost overruns which fluctuated from $145,000 to $580,000 and failed to provide adequate supporting data to allow the project architect to issue a certificate of payment in accordance with *1033 the contract documents. Between 75 and 100 separate work items were involved in the contractor's claim.
The contractor contended the later drawings and specifications submitted by the owner contained numerous changes, additions, and deletions from the original documents furnished it, and that it was requested to forego formal change orders in favor of a determination of all amounts due for extra work at the conclusion of construction.
After numerous conferences between the owner's architect and representatives and the contractor's representatives, the parties were unable to resolve their dispute. The contractor then filed a formal demand for arbitration with the American Arbitration Association pursuant to a contractual arbitration clause. The demand requested arbitration under the first contract dated March 8, 1972, but the "Claim for an Equitable Adjustment" presented to the arbitrators October 15, 1974 contained all of the claims for the entire project. The owner answered these claims and presented some of its own, and timely objected to the arbitration procedure. The arbitrators eventually made an award based on work performed on the entire project under all three contracts.
Before the arbitration hearing started, the owner filed a declaratory judgment suit in the district court alleging the disputes between it and the contractor were not arbitrable in nature and requested injunctive relief. The district court denied a preliminary injunction, and this court affirmed because the preliminary injunction question became moot when the arbitration proceeding was completed prior to the hearing of the preliminary injunction question in this court.[1] This court stated there was sufficient evidence to support the trial court's finding the contract between the parties contained an arbitration clause, but made no decision on the question of arbitrability of the dispute. After deciding the narrow issue of the moot request for a preliminary injunction, the case was remanded for further proceedings. The issue of arbitrability remains undecided.
After the arbitration award in favor of the contractor was rendered, the owner then filed this suit in which this appeal has been taken to modify, correct or vacate the award of the arbitration panel. R.S. 9:4210 and 4211. This has created a procedural issue. This proceeding was allotted to another division of the trial court, and it was not consolidated with the first proceeding. A trial date was set, but the trial judge set it aside on his own motion. The matter was reset for hearing approximately 6 months later, still without benefit of a decision on the question of arbitrability. The trial court then proceeded to hear the matter, modified the arbitrator's award on the date from which the interest began to run, and homologated the award as thus amended. The owner has appealed from that judgment and the contractor has filed an answer to that appeal.
We first proceed to the determination of the procedural issue. The appellant contends that the trial court erred in failing to vacate, correct or modify the award of the arbitration panel because the award was made prior to a final determination of the arbitrability of the matters upon which the panel acted, and that the question of arbitrability is still pending trial in the first suit between these parties. It should be noted that the first suit was not brought under the provisions of R.S. 9:4203 where a party aggrieved by the refusal of another to perform under a written agreement for arbitration may petition the court for an order directing that the arbitration proceed, nor was it the type of proceeding encompassed in R.S. 9:4202. The first suit was a declaratory judgment suit brought by the owner seeking to declare what issues are subject to arbitration, and contained within it ancillary proceedings for a preliminary and permanent injunction to prevent arbitration. *1034 The owner was refused a preliminary injunction to enjoin arbitration, and on appeal to this court, the matter of a preliminary injunction was declared moot because arbitration had already concluded. As far as the record on this appeal shows, the merits of that case have never been determined, and we cannot see any sound basis for concluding that this untried case should stop all proceedings conducted within the provisions of the Louisiana Arbitration Law.
In effect, what appellant is urging is that although he has been refused a preliminary injunction to stop the arbitration proceedings from going forward, nevertheless because the merits of that case have not been tried, it acts as an automatic injunction which would prevent the arbitration award from becoming effective.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
359 So. 2d 1031, 1978 La. App. LEXIS 3238, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-stores-co-v-gervais-f-favrot-co-inc-lactapp-1978.