City San Antonio v. Uvalde Rock Asphalt

11 S.W.2d 829
CourtCourt of Appeals of Texas
DecidedNovember 21, 1928
DocketNo. 8068. [fn*]
StatusPublished
Cited by2 cases

This text of 11 S.W.2d 829 (City San Antonio v. Uvalde Rock Asphalt) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City San Antonio v. Uvalde Rock Asphalt, 11 S.W.2d 829 (Tex. Ct. App. 1928).

Opinion

SMITH, J.

On June 14, 1920, the city of San Antonio and Uvalde Rock Asphalt Company entered into a contract whereby the asphalt company agreed and undertook to pave a portion of Nolan’ street in said city, in consideration of the sum of approximately $30,-000, of which amount $8,500 was to be paid in cash by the city and the balance to be evidenced by assignable certificates to be issued by the city and to be paid by property owners whose property abutted on said street. The work of paving, which included necessary “curbing and headers” coextant with the paving, was completed by the paving company and accepted by the city, which paid over its proportion of the agreed price and issued certificates for the balance. There appears to be no question about the regularity or validity of the proceedings by which the improvement was ordered or the contract made by the city. The Uvalde Company succeeded to the rights and liabilities of the Uvalde Rock *830 Asphalt Company, which was thereby eliminated from the transaction and subsequent litigation.

On January 13, 1922, the city brought this action against the paving company to recover the amount it had paid that company under the contract, and to cancel the certificates issued against the abutting property. It was alleged by the city, and conceded by the paving company, that under the contract the latter was obligated to improve the designated portion of Nolan street by placing thereon “a prepared, gravel base of eight inches in thickness after compression and a two-inch Uvalde rock asphalt topping, and to construct the necessary curbing and headers, all at the unit prices shown in said contract.” It was alleged by the city that the paving company had not completed said improvements in accordance with the contract, and, quoting from appellant’s brief, that by reason thereof “the said portion of Nolan street, after said improvements had been completed, was not fit for the purpose for which it had been built, and that almost immediately after completion it cracked, buckled, crawled and disintegrated so' as not to present a smooth-wearing surface for ordinary traffic, and particularly alleged that said company had not placed a two-inch Uvalde rock asphalt topping on said street but had placed a topping of materially less thickness, and further alleged that said topping had not been placed upon a prepared gravel base eight inches in thickness after compression, as required by said contract, and that said gravel base had not been permitted to dry out properly before the topping was laid, and that the gravel used was not clean and free from foreign substance but contained a large portion of clay and dirt, and contained so large a proportion of clay and dirt as to prevent same from being a suitable and sufficient foundation for said paving, all of which was in violation of and contrary to said contract; and said first amended ■ original petition contained a prayer for the recovery of said sum of $8,500.00 theretofore paid by said city as its proportionate share of the cost of said improvements, and further prayed that the contract between the parties and the certificates theretofore issued thereunder be cancelled and annulled.”

The paving company claimed that it had done the work in accordance with the specifications in the contract, under the immediate and constant supervision and instructions of the inspectors and representatives, and to the satisfaction of the city, whose engineer had inspected and approved the work, and whose commissioners had approved and accepted the same by resolution duly passed, and had paid the company therefor and issued and delivered to the company the paving certificates thereon; “that said contract provided that in order to prevent dispute and litigation the (City) engineer should in all cases determine the quantity and quality of the kinds of work and the materials which were to be accepted and paid for; and said pleading further set forth in detail the provisions of said contract making the said City Engineer the representative of the city and final arbiter in passing upon the kind and sufficiency of the work and material done under said contract; and further alleged that under said contract the city was given thirty days after the said improvements were completed to raise any objections to the action of the engineer, and that thereafter it was strictly relegated to the remedies provided for in the maintenance bond attached to and made a part of said contract. Said answer then alleged the giving of the maintenance bond in the sum of $6,800.00, and the terms thereof, and the provisions of the contract relative to the remedy on said bond, and again alleged that under said contract and bond the City of San Antonio became relegated to the provisions of the maintenance bond thirty days after the acceptance of the work, and further alleged that said city had actually ratified and confirmed such maintenance bond, not only by its acceptance thereof but by actually calling on the contractor to make repairs on said street on several dates alleged in said pleading, and further alleged that by calling on the said defendant to make such repairs the city had effected an election to rely on the provisions of said contract and bond. Said answer further alleged that by reason of the said city having called on said defendant to make such repairs, and by reason of the fact that such defendant had made such repairs, the city was estopped to seek to recover the consideration paid under said contract or to cancel on behalf of the property owners the assessment certificates issued by virtue thereof. Said answer then specially pleaded Article XI, Section B, of the said contract dated June 14, 1920, and alleged in detail the acceptance by the city of said improvements on the 14th day of April, 1921, and the certificate of the City Engineer certifying to the completion of said improvements in accordance with said contract, which certificate was dated June 14, 1920, and alleged that said city was bound by the action of the City Engineer" in making such certificate and by the action of the city in accepting said improvements in accordance with said certificate.”

In this connection the paving company specially pleaded the following provisions of the paving contract:

Article X, subd. A: “To prevent all disputes and litigations, the Engineer shall in all cases determine the quantity and quality of the several kinds of work and materials which are to be accepted or paid forjznder this contract, and he shall determine all questions in relation to the work and materials and the construction or constituents thereof; and he shall also decide every question which *831 may arise in connection with the work required or executed under this contract; and all other matters as herein provided; and the estimate or decision of such Engineer shall be final and conclusive in any such event.”

Article XI, subd.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gerardo Tapia-Lopez v. State
Court of Appeals of Texas, 2015
Painter Bus Lines, Inc. v. Carpenter
146 S.W.2d 278 (Court of Appeals of Texas, 1940)

Cite This Page — Counsel Stack

Bluebook (online)
11 S.W.2d 829, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-san-antonio-v-uvalde-rock-asphalt-texapp-1928.