City of Unionville v. Martin

68 S.W. 605, 95 Mo. App. 28, 1902 Mo. App. LEXIS 6
CourtMissouri Court of Appeals
DecidedApril 7, 1902
StatusPublished
Cited by9 cases

This text of 68 S.W. 605 (City of Unionville v. Martin) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Unionville v. Martin, 68 S.W. 605, 95 Mo. App. 28, 1902 Mo. App. LEXIS 6 (Mo. Ct. App. 1902).

Opinion

SMITH, P. J.

The plaintiff, a city of the fourth class, entered into a written contract with defendant Martin whereby the latter undertook to bore a well for the former. The latter, with his co-defendants as sureties, further entered into a bond to such former in the sum of three thousand dollars, conditioned for the faithful performance of said contract and to refund all [33]*33moneys advanced to the latter by snch former in case of a refusal, failure or neglect to complete the work specified in said contract.

This is an action on said bond to recover the penalty thereof. The petition alleges that defendant Martin begun the work under said contract, and after drilling a hole about seven hundred feet, abandoned the said contract and left the work in an incomplete and unfinished.condition. It further alleges that during the progress of the work the plaintiff from time to time advanced to defendant Martin on said contract, various amounts of money aggregating $1,172.75, which he has refused to refund although requested so to do. It was still further therein alleged that by the terms of said contract, defendant Martin bound himself to complete the work therein specified within one hundred and eighty days from May 15, 1896, and to pay the plaintiff the sum of two dollars a day as a forfeit for each day that should occur between the expiration of said period and the completion of the work, and that the number of days that said work had remained incomplete after the expiration of said period were far more than sufficient to make the amount of the forfeiture exceed three thousand dollars. There was also a still further allegation to the effect that under the contract the defendants were liable to pay an attorneys ’ fee for the prosecution of the action which was reasonably worth three hundred dollars. Judgment was demanded for three thousand dollars, the penalty on the bond, etc.

Separate answers were filed by defendant Martin and the other defendants, the sureties. The answer of the former admitted the execution of the contract and bond, but pleaded that the contract was illegal and void. There was pleaded also the further defense that during the progress of the work the plaintiff, against the objections of defendant Martin and contrary to the [34]*34provisions of said contract, caused about one hundred feet of the steel casing, which was used to form the lining of the well, to be perforated by drilling holes therein in such a way as left the interior of said casing with rough edges and beards protruding therein so that the ropes used in drilling the well were thereby cut, and the drill, which was of enormous weight, dropped to the bottom of the well — a distance of over seven hundred feet;.and that by reason of such perforations, water, sand and gravel flowed through the same and settled upon the said drill and apparatus, rendering it impossible to extricate the same or to further prosecute the work; and that in consequence of such unwarranted interference by plaintiff, defendant Martin was prevented from fully complying with the said contract, etc. A counterclaim was also pleaded.

The separate answer of the surety defendants admitted the execution 'of the contract and bond, and alleged that the plaintiff had no authority in law to make the former or to accept the latter of these instruments, and that therefore the same were void. It was therein further pleaded that defendant Martin by reason of the interference of the plaintiff with the execution of the contract by said Martin, was prevented from completing the work thereunder; and that such interference was without their knowledge or consent; and that by reason thereof they were discharged, etc. The replication was a general denial. There was a trial resulting in judgment for defendants and plaintiff appealed.

It was disclosed by the evidence adduced at the trial that a proposition authorizing plaintiff to borrow a certain sum of money with which to erect a combined system of electric light and waterworks had been submitted to the qualified voters of plaintiff city and carried by a two-thirds majority. It was further disclosed that an ordinance had been passed providing for the issue of bonds and to authorize the reception of bids therefor. It further appeared from the journal [35]*35kept by the board of aldermen of plaintiff city, that it had been ordered by that body that the bond (here sued on) “be approved.” No ordinance authorizing the contract for doing the work was introduced in evidence. It is in effect conceded that no such ordinance was passed by the board of aldermen and approved by the mayor. The case thus presented is that when the contract was entered into between the mayor and defendant Martin there was not as much as a semblance of an ordinance authorizing the same; and the question which confronts us at the outset is whether or not the contract thus entered into is valid. It is true that the petition does not plead the existence of an ordinance authorizing the contract, but this is implied: Werth v. Springfield, 78 Mo. 107.

The plaintiff as a city of the fourth class had power, under several acts of the Legislature, to erect, maintain and operate waterworks. Sess. Acts, 1891, p. 67; Sess. Acts 1893, p. 60; Sess. Acts 1895, p. 81. And to establish and make public wells. Sess. Acts 1895, p. 65.

By section 106 of the last-cited act, it was provided that for any of the purposes mentioned in the preceding sections, the board of aldermen (of cities of the fourth class) should have power.to enact all necessary ordinances, etc., and should have power to enact all such ordinances as might be expedient for maintaining the peace, good government and welfare of the city, etc. And by another section of the act (28) the duties and powers of the officers of every character connected with the city government were required to be prescribed by ordinance. From these and other sections of the act it is clear that the jurisdiction over the matter of contracting for the boring of a public well was in the mayor and board of aldermen, and that the manner of exercising such jurisdiction was to be by ordinance cmd not othenvise; and, therefore, the act of the mayor in entering into the contract in question was not [36]*36the act of the plaintiff. The rule is, that the charter of a city is in the nature of a power of attorney, and the authority conferred by it must be carried out in the manner prescribed by it. Where it requires the passage of an ordinance — a legislative act — by the mayor and aldermen to accomplish the object, that power can not be delegated to others. Ruggles v. Collier, 43 Mo. 353; Thomson v. Boonville, 61 Mo. 282; Stewart v. Clinton, 79 Mo. 603; Rowland v. Gallatin, 75 Mo. 134; Nevada v. Eddy, 123 Mo. 546; Moore v. Cape Girardeau, 103 Mo. 470; Wheeler v. Poplar Bluff, 149 Mo. 36; Rumsey Mfg. Co. v. Schell City, 21 Mo. App. 175; Beatty v. St. Joseph, 57 Mo. App. 251; Gehling v. St. Joseph, 49 Mo. App. 430; Poplar Bluff v. Hoag, 62 Mo. App. 672; Maudlin v. Trenton, 67 Mo. App. 452; McQuiddy v. Brannock, 70 Mo. App. 535; Kolkmeyer v. City of Jefferson, 75 Mo. App. 678, loc. cit. 683. In the last-cited case it was said by us: “When special powers are conferred, or where a special method is prescribed for the exercise and execution of a power, this brings the exercise of such power within the provision of the maxim expressio unius, etc., and by necessary implication forbids and renders nugatory the doing of the thing specified, except in the particular way pointed out.” Heidelberg v. St. Francois Co., 100 Mo. 69; McKissick v. Mt. Pleasant Twp., 48 Mo. App. 416.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Reynolds v. City of Independence
693 S.W.2d 129 (Missouri Court of Appeals, 1985)
West Virginia Coal Co. v. City of St. Louis
25 S.W.2d 466 (Supreme Court of Missouri, 1930)
City of Fort Worth v. First Baptist Church of Fort Worth
268 S.W. 1016 (Court of Appeals of Texas, 1924)
Hollinghausen v. Ade
233 S.W. 39 (Supreme Court of Missouri, 1921)
Koch v. City of Weston
220 S.W. 1007 (Missouri Court of Appeals, 1920)
O'Dell v. Scranton
103 S.W. 570 (Missouri Court of Appeals, 1907)
Chenowith v. State
96 S.W. 19 (Court of Criminal Appeals of Texas, 1906)
Kansas City ex rel. Diamond Brick & Tile Co. v. Schroeder
93 S.W. 405 (Supreme Court of Missouri, 1906)
Calvert v. City of St. Joseph
95 S.W. 308 (Missouri Court of Appeals, 1906)

Cite This Page — Counsel Stack

Bluebook (online)
68 S.W. 605, 95 Mo. App. 28, 1902 Mo. App. LEXIS 6, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-unionville-v-martin-moctapp-1902.