City of Topeka v. Watertower Place Development Group

959 P.2d 894, 265 Kan. 148, 1998 Kan. LEXIS 344
CourtSupreme Court of Kansas
DecidedMay 29, 1998
Docket78,862
StatusPublished
Cited by40 cases

This text of 959 P.2d 894 (City of Topeka v. Watertower Place Development Group) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Topeka v. Watertower Place Development Group, 959 P.2d 894, 265 Kan. 148, 1998 Kan. LEXIS 344 (kan 1998).

Opinion

The opinion of the court was delivered by

Lockett, J.:

The City of Topeka (City) and the Watertower Place Development Group (Watertower) entered into a contract giving Watertower exclusive rights to develop an area in the City. The City filed a declaratory action, claiming Watertower had breached the contract and, therefore, the City was no longer bound by the contract. Watertower filed a counterclaim for specific performance and monetary damages. The district court entered sum *149 mary judgment for the City, finding the contract to be unambiguous and that the City had properly terminated the contract due to Watertower’s breach. Watertower appealed, claiming (1) an alleged breach of contract is an issue of fact to be determined by a jury; (2) the district court’s determination that the City had properly terminated the contract was not supported by substantial competent evidence; (3) the district court incorrectly based its grant of summary judgment upon the testimony of an expert; (4) the district court had previously ruled the City had committed an anticipatory breach of the contract; and (5) the district court failed to address all of Watertower’s arguments.

BACKGROUND

In an attempt to stimulate growth in blighted business districts within cities, the Kansas Legislature passed the Redevelopment of Central Business District Areas Act, K.S.A. 12-1770 et secj. Under the Act, the legislature authorized cities to acquire property and issue special obligation bonds. K.S.A. 12-1770. Pursuant to the Act, the Topeka City Council established the Watertower redevelopment district. As a result, the City was authorized to acquire the property and issue special obligation bonds to pay for the acquisition. The bonds were to be financed by an increase in ad valorem taxes that the City anticipated would result from the redevelopment. K.S.A. 12-1771(h).

The parties decided to take advantage of the Act. On January 16,1990, the City entered into a contract granting Watertower the exclusive rights for 15 years to develop the Watertower redevelopment district in Topeka. Although the contract comprises 34 pages, the parties’ disagreements arise from “Section 11. Commitment to be provided by the Developer,” which provides in part:

“Within one hundred eighty (180) days of the City’s adoption of any Redevelopment Project Plan . . ., the Developer . . . shall provide to the City either: (i) the commitment of a purchaser of Tax Increment Financing Special Obligation Bonds (the ‘Bonds’) to be authorized and issued by the City for the Project’s financing in accordance with the authority granted the City under the Act . . . .”

Under Section 11, the monies generated by the bonds were to be used to acquire the property in the development area and to prepare the area for construction of the development.

*150 Section 11 also provided the methodology for Watertower’s compliance with the commitment of a bond purchaser, providing:

“The Commitment shall not be deemed sufficient until approved and accepted in writing by the City, which approval shall not be unreasonably withheld, provided however, if the Commitment is not approved by the City within 21 days after receipt thereof by the City, the City shall specify with particularity the portion of the Commitment and with particularity the reason why such portion does not meet with its approval. The Developer shall have one additional ninety (90) day period thereafter to provide a Commitment acceptable to the City. In the event Developer fails to obtain the Commitment for a particular Project for which a Redevelopment Project Plan has been approved, Developer shall have no liability whatsoever as a result thereof relative to that particular Project, however, in such case the City may, subject to the provisions of Section 6 herein, (i) terminate this Agreement thereby extinguishing the Developers exclusive right to develop the Projects contemplated by the Plan; or (ii) terminate the Redevelopment Preyed Plan for that particular Preyed under consideration and obtain a different developer for that Preyed; or (in) act as is otherwise agreed to in writing by the City and the Developer.” (Emphasis added.)

The parties dispute whether Watertower or the City failed to comply with Section 11.

As noted above, Section 11 required Watertower to provide a purchaser of bonds by a specific date. Toward that end, Water-tower provided a letter authored by B.C. Christopher, which promised to “pursue, on a best efforts basis, the financing for the required land acquisition, relocation, improvement, and demolition costs through the sale of tax increment bonds.” B.C. Christopher’s commitment to use best efforts to market the bonds was subject to nine conditions. It is undisputed that Watertower intended the B.C. Christopher letter to satisfy the requirements under Section 11. It is also undisputed that the City did not accept the letter as fulfilling the commitment and considered Watertower to have breached the contract. Due to the breach, the City sent a contract termination letter to Watertower.

It was later discovered that the City Council did not follow the Kansas Open Meetings Act requirement when voting to terminate the contract. Instead, the city attorney, in executive session, explained to the council that he intended to terminate the contract with Watertower unless the council members talked to him after *151 the meeting and objected to the termination of the contract. No council member objected, and the letter of termination was sent to Watertower on May 19, 1993.

Subsequent negotiations attempting to breathe new life into the project, through modification of the old contract or the creation of a new contract, continued into 1994.

The City ultimately determined that further negotiations were fruitless and on July 27, 1994, the City brought a declaratory judgment action in the district court, seeking judicial declaration that the contract was terminated and Watertower was no longer the exclusive developer of the project. Watertower counterclaimed, seeking specific performance of the contract and damages from the breach of contract by the City. First, the district court granted summary judgment to the City on Watertower’s claim it was entitled to specific performance of the contract. That judgment was appealed and upheld by the Court of Appeals. That ruling is not before this court.

Subsequently, the City filed for summary judgment, claiming that it had not breached the contract, but rather it had terminated the contract on May 19, 1993, pursuant to Section 11 of the contract. The district court found there were no material factual disputes. Therefore, the parties’ disagreement was one of contract interpretation, which is a question of law to be decided by the court.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

South Mulberry Properties v. GT Management
Court of Appeals of Kansas, 2022
Unified School District No. 446 v. Sandoval
286 P.3d 542 (Supreme Court of Kansas, 2012)
Daggett v. Board of Public Utilities
263 P.3d 847 (Court of Appeals of Kansas, 2011)
Wittig v. Westar Energy, Inc.
235 P.3d 535 (Court of Appeals of Kansas, 2010)
Pollock v. Crestview Country Club Ass'n
205 P.3d 1283 (Court of Appeals of Kansas, 2009)
Hammer v. Thompson
129 P.3d 609 (Court of Appeals of Kansas, 2006)
Colgan Air, Inc. v. Raytheon Aircraft Co.
404 F. Supp. 2d 893 (E.D. Virginia, 2005)
Stafford v. Crane
382 F.3d 1175 (Tenth Circuit, 2004)
Allen, Gibbs & Houlik, L.C. v. Ristow
94 P.3d 724 (Court of Appeals of Kansas, 2004)
TR, Inc. of Ashland v. Brandon
87 P.3d 331 (Court of Appeals of Kansas, 2004)
Krider v. Board of Trustees of Coffeyville Community College
83 P.3d 177 (Supreme Court of Kansas, 2004)
State Ex Rel. Graeber v. Marion County Landfill, Inc.
76 P.3d 1000 (Supreme Court of Kansas, 2003)
State, Department of Social & Rehabilitation Services v. Lasater
54 P.3d 511 (Court of Appeals of Kansas, 2002)
Berkshire Aircraft, Inc. v. AEC Leasing Co.
84 P.3d 608 (Court of Appeals of Kansas, 2002)
Howarth v. Olivier
52 P.3d 911 (Court of Appeals of Kansas, 2002)
Cannon v. Farmers Insurance
50 P.3d 48 (Supreme Court of Kansas, 2002)
Liggatt v. Employers Mutual Casualty Co.
46 P.3d 1120 (Supreme Court of Kansas, 2002)
Blair Construction, Inc. v. McBeth
44 P.3d 1244 (Supreme Court of Kansas, 2002)
Brenner v. Oppenheimer & Co.
44 P.3d 364 (Supreme Court of Kansas, 2002)
Butler National Corp. v. Gerald T. Kelly & Co.
43 P.3d 824 (Court of Appeals of Kansas, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
959 P.2d 894, 265 Kan. 148, 1998 Kan. LEXIS 344, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-topeka-v-watertower-place-development-group-kan-1998.