City of the Dalles Ex Rel. Taylor Electric Supply Inc. v. D'Lectric Co.

803 P.2d 771, 105 Or. App. 46, 1990 Ore. App. LEXIS 1761
CourtCourt of Appeals of Oregon
DecidedDecember 26, 1990
DocketCC88-24; CA A62764
StatusPublished
Cited by1 cases

This text of 803 P.2d 771 (City of the Dalles Ex Rel. Taylor Electric Supply Inc. v. D'Lectric Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of the Dalles Ex Rel. Taylor Electric Supply Inc. v. D'Lectric Co., 803 P.2d 771, 105 Or. App. 46, 1990 Ore. App. LEXIS 1761 (Or. Ct. App. 1990).

Opinion

*48 DEITS, J.

Plaintiff Taylor Electric Supply, Inc., furnished materials to defendant D’Lectric Company, the electrical subcontractor for the City of The Dalles’ Mid-Columbia Senior Center construction project. D’Lectric did not pay plaintiff in full, and plaintiff brought this action, pursuant to ORS 279.526 et seq, on the prime contractor’s bond issued by defendant Fairmont Insurance. The case was tried to the court, which held that plaintiff was not entitled to recover. It appeals, and we reverse.

We quote the relevant facts from the trial court’s opinion letter:

“The City of The Dalles employed Trimble Commercial Contractors as the prime contractor in the construction of the Mid-Columbia Senior Center. Fairmont Insurance, as Trimble’s surety, issued a Performance, and Labor and Material Bond to secure performance and payment of all subcontractors.
“Trimble subcontracted to D’Lectric Company to perform all the necessary electrical work on the project. Consequently, D’Lectric opened an account with Taylor Electric for electrical equipment and supplies to be incorporated into the project.
“John Russell, an electrician employed by D’Lectric on the Senior Center project, testified that sometime in early December, 1986, ten or eleven light fixtures were delivered to the job site. The trim were packaged separately from the light fixtures. Three of the trim were slightly damaged with bent rims. Mr. Russell hammered out the dents and installed the repaired trim. At that time, Mr. Russell asked another electrician to reorder three new trim to replace the installed, but imperfect trim. The three replacement trim, however, never arrived. No evidence was presented showing whether or not the trim were actually reordered * * * at that time.
“On December 13,1986 a Certificate of Substantial Completion was issued establishing December 15,1986 as the date of substantial completion. A Certificate of Temporary Occupancy was issued on December 16, 1986. The final electrical inspection was made on December 23,1986.
“On February 2,1987, D’Lectric ordered three Halo trim, at a cost of $208.22, presumably to replace the damaged, installed trim. The trim were delivered the following day. The *49 replacement trim, however, were never installed. Consequently, the damaged trim were never replaced and are still in place in the Senior Center. This litigation centers on the characterization of these three trim.
“D’Lectric has since become insolvent and has been discharged in bankruptcy. The balance owing to Taylor Electric is $15,920.57. Pursuant to ORS 279.526, plaintiff filed suit to recover payment from the performance bond.
“On April 27, 1987 plaintiff sent notice of its claim to Trimble. However, due to insufficient postage and according to company policy, the letter was not accepted by Trimble. A second notice was mailed to Trimble and the City of The Dalles on June 3,1987, and to Fairmont on June 4,1987.”

The issue is whether either of plaintiffs notices to Trimble satisfies and was timely under ORS 279.528(1):

“The notice of claim required by ORS 279.526 shall be sent by registered or certified mail or hand delivered no later than 120 days after the day the person last provided labor or furnished materials. The notice may be sent or delivered to the contractor at any place the contractor maintains an office, conducts business or at the residence of the contractor.”

Under ORS 279.526, service of a notice that complies with ORS 279.528 is a condition precedent to bringing an action.

The trial court concluded that neither notice sufficed. It reasoned that the April 27 notice did not meet the statutory requirements, because adequate postage to assure delivery and receipt is implicitly required. The court then concluded that the June 3 notice also did not satisfy the statute. Although that notice was served within 120 days after plaintiffs furnishing of the replacement trim, the court noted that all other materials had been furnished more than 120 days before the notice; the court then concluded, inter alia, that the trim was “corrective in nature and [was] not furnished as part of the original contract” and, therefore, that the “delivery of the three halo trim to replace the previously installed trim does not constitute the furnishing of materials within the context of ORS 279.528(1), and fails to extend the notification period.” Plaintiff assigns error to the court’s conclusions concerning both notices. Because we agree with plaintiff that the June notice complies with ORS 279.528, we do not reach the questions relating to the earlier notice.

*50 ORS 279.528 was amended by Or Laws 1985, ch 526, § 2, to make it similar to the notice and limitations provisions of the federal Miller Act. 1 Because no Oregon cases have dealt with the issue since the 1985 amendment was adopted, the trial court and the parties relied on federal cases applying the Miller Act provisions. Those cases have taken three general views.

The first is exemplified by United States v. Western Electric Co., 337 F2d 568, 572 (9th Cir 1964), where the court said that the

“test to be applied is whether the work was performed and the material supplied as a ‘part of the original contract’ or for the ‘purpose of correcting defects, or making repairs following inspection of the project.’ ”

Under that view, the periods for notice and for bringing an action cannot be extended by mere corrective performance or deliveries.

The view at the other extreme is reflected by Trinity Universal Insurance Company v. Girdner, 379 F2d 317, 318 (5th Cir 1967). The court said, in construing 40 USC § 270b(b):

“We have studied the language of the statute, the legislative history of its 1959 amendment, and the cases. Particularly in view of the liberal construction which must be given the Miller Act, we are convinced that the ‘last labor or materials’ language is broad enough to include work performed upon the demand of the government to correct defects in the work as originally completed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Smith & Smith Excavation, Inc.
386 P.3d 112 (Court of Appeals of Oregon, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
803 P.2d 771, 105 Or. App. 46, 1990 Ore. App. LEXIS 1761, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-the-dalles-ex-rel-taylor-electric-supply-inc-v-dlectric-co-orctapp-1990.