City of Syracuse v. Dale Engineering Co.

233 A.D. 417, 253 N.Y.S. 444, 1931 N.Y. App. Div. LEXIS 11314

This text of 233 A.D. 417 (City of Syracuse v. Dale Engineering Co.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Syracuse v. Dale Engineering Co., 233 A.D. 417, 253 N.Y.S. 444, 1931 N.Y. App. Div. LEXIS 11314 (N.Y. Ct. App. 1931).

Opinion

Crosby, J.

Defendant Dale Engineering Company was the successful bidder for a contract for resurfacing, with asphalt over brick, a portion of Genesee street in Syracuse. It gave the city a bond to secure its faithful performance of the contract. At the completion of the work this defendant gave the city a so-called maintenance bond as security that the pavement would remain in good repair for a period of five years. The latter bond was given to enable this defendant to draw the last fifteen per cent of the contract price which, otherwise, pursuant to the contract, would have been retained by the city for the five-year period. The city paid the full contract price, including pay for the extra work done by defendant pursuant to the order of the city’s engineer, and it is undisputed that the pavement went to pieces rather badly within a few months.

The defendant National Surety Company is the surety on both the faithful performance bond and the maintenance bond given by the Dale Engineering Company and recovery has been had by the city against both defendants on both bonds.

We have two actions here, for the reason that the contract was let for resurfacing a stretch of street along part of which were the tracks of a street car company, and some practical reason suggested the advisability of letting the job in two separate contracts. The same questions are involved in both actions.

Appellants raise the question whether, in any case, the plaintiff could recover on both bonds, and contend that plaintiff, having accepted the pavement and having paid for it, is confined to such damages as it may recover on the bond given and accepted for the purpose of securing maintenance. This question need not now be decided. At any future trial, the verdict, if any, obtained by plaintiff, and the judgment entered thereon, can be in such form as to enable any court to which the matter may come to determine easily the assessment of damages relating to each bond.

The important question in the case relates to the defense which was pleaded but which defendants were refused permission to prove at the trial. That defense was, in substance, that under the terms of the contract, plaintiff retained entire control over the building of the pavement, both as to work and materials, and that plaintiff, over the protest of defendant contractor, compelled defendant contractor to use materials destructive of the asphalt, after being given warning of what the result would be.

The contract is not printed in the record, but, from the portions quoted in the respective briefs, we learn that the resurfacing material was to be of asphalt. When the work was completed the surface was found to be so slippery as to be dangerous to traffic. [419]*419Plaintiff made the claim, that defendant contractor had not properly applied a surface coat of grit and said defendant made the claim that it was compelled by plaintiff, under the terms of the contract, to apply the surface coat in cold, rainy weather under conditions which made it impossible for defendant to make the grit adhere to the asphalt. The controversy was culminated by the plaintiff’s engineer giving to defendant a so-called extra-work order to apply a coat of Tarvia to the surface of asphalt. For the performance of this extra-work order plaintiff paid defendant the contract price of cost plus fifteen per cent. Defendant alleged and attempted to prove that it knew that, because of some chemical reaction, Tarvia would destroy the asphalt, that it so informed plaintiff, and that it finally applied the Tarvia under protest and under compulsion of the extra-work order.

Let us turn now to some of the stipulations of the contract.

Paragraph B provides that “ it is further agreed * * * that the City Engineer shall * * * decide upon the amount, quality * * * and fitness of the several kinds of work and materials * * * and upon all questions which may arise relative to the fulfillment of the contract, * * * and his * * * decisions shall be final and conclusive,” etc.

Paragraph F provides that “it is further agreed that the said Engineer may make alterations in [various things] or material of the work * * * or any part thereof, either before or after the commencement of construction.” This paragraph further provides, in effect, that if, by reason of such changes, the work, ■under the contract, is lessened, the contractor shall have no pay for work thus dispensed with, but, if increased, he shall be paid actual reasonable cost plus fifteen per cent.

Paragraph M provides that “ The contractor agrees that he will perform such extra work as the Engineer may order in writing, but will not perform any extra work unless so ordered.”

With these provisions in the contract, and binding on defendant, the question is whether or not it should have been permitted to make the defense pleaded. That counsel for plaintiff anticipated such defense and claimed to be ready to meet it is shown by this remark in his opening to the jury: “ I know that there is going to be the question raised wdth reference to the effect of the Tarvia that was put on this pavement. Now, if that becomes an issue in this case, we will be prepared to show you that Tarvia — the Tarvia coat didn’t in any way harm this paving. * * * In any event, even if it had, the Dale Engineering Company put it on. The Dale Engineering Company guaranteed it * * * after they had put it on.” The last remark of counsel suggested [420]*420the theory on which the case was tried and submitted to the jury, namely, that, although every specification of the contract, as to work and materials, was under the absolute control of plaintiff, although it could change every specification at will at any time and if a dispute arose plaintiff’s engineer could decide every question, without the contractor having a right to say a word about it, although the engineer could change the specifications and compel the contractor to build the pavement of mud or ashes, yet, no matter how disastrous the result, the plaintiff could exact the last ounce of flesh under the bond. The city claimed the right to supervise everything, to reject everything, to decide everything, then to approve the work and pay for it in full, then exact bonds to secure it against the results of its own mistakes of judgment, and then recover on the bonds. The plaintiff’s engineer, at one time, must have doubted the justice of this theory, for when testifying to a conversation he had.with defendant’s president, when the plan of applying Tarvia was first suggested by him, he said: “ I suggested the application of a tar seal coat * * * and I emphasized * * * that we could, in no way, apply anything to that street or do anything to it whatsoever without his absolute approval. * * * I said to Mr. Collins [defendant’s president] that he would have the obligation to maintain this street for five years from the date of the final acceptance and that we could not recommend or that we would not recommend, nor do anything to the street which might, in any way, interfere with that maintenance requirement.”

Even the court, at first, doubted the correctness of the harsh theory which it later adopted, for when the issue as to responsibility for the application of Tarvia first arose at the trial, the court said: “ Isn’t the real question in the case whether or not the City directed these parties to put it [Tarvia] on or whether the defendant and the City agreed

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Patterson v. . Meyerhofer
97 N.E. 472 (New York Court of Appeals, 1912)
Cameron-Hawn Realty Co. v. . City of Albany
101 N.E. 162 (New York Court of Appeals, 1913)

Cite This Page — Counsel Stack

Bluebook (online)
233 A.D. 417, 253 N.Y.S. 444, 1931 N.Y. App. Div. LEXIS 11314, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-syracuse-v-dale-engineering-co-nyappdiv-1931.