City of St. Louis v. O'Neil Lumber Co.

21 S.W. 484, 114 Mo. 74, 1893 Mo. LEXIS 200
CourtSupreme Court of Missouri
DecidedFebruary 6, 1893
StatusPublished
Cited by11 cases

This text of 21 S.W. 484 (City of St. Louis v. O'Neil Lumber Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of St. Louis v. O'Neil Lumber Co., 21 S.W. 484, 114 Mo. 74, 1893 Mo. LEXIS 200 (Mo. 1893).

Opinion

Bkace, J.

This case is certified here from tbe St. Louis court of appeals under section 6 of tbe amendment of tbe constitution adopted in 1884.

Tbe statement of tbe case made by Judge Biggsof that court is as follows:

“On tbe seventeenth day of July, 1888, tbe municipal assembly of tbe city of St. Louis passed an ordinance authorizing tbe board of public improvements to contract for certain alterations and repairs at tbe House of Refuge. Section 2 of tbe ordinance is-as follows: ‘The cost of tbe above work shall be paid by tbe city of St. Louis, and the sum of $4,500 is-hereby appropriated out of funds set apart for improvements, alterations and repairs of the House of RefugpJ Tbe work was let to one James McLane under three-separate contracts. Contract number 2071 provided for the erection of two new privy buildings at a cost of $2,800. By contract, number 2083,’ McLane agreed to make certain alterations in the' basement and in the-dormitory of tbe old building for tbe sum of $850. Tbe third contract, number 2076, provided for furnishing lumber and laying tbe floor in tbe shoe shop of tbe House of Refuge. Tbe foregoing contracts were signed by McLane as principal and tbe interpleaders, Thomas-C. Higgins and John M. Sellers, as bis sureties. Among-other things tbe contracts provided that ‘in' case tbe contractor shall abandon tbe work * * * tbe commissioner of public buildings shall have power under tbe direction of tbe board of public improvements to place such and so many persons as be may deem advisable by contract [78]*78or otherwise to work and complete the work to be done, and to use such materials as he may find on the line of said work, or to procure other materials for the completion of the same and' to charge the expense of said labor and materials to the contractor; that this expense shall be deducted and paid out of such moneys as may then be due, or may at any time thereafter grow due to him under the contract; and, in case such expense is less than the amount still due under the contract, had it been completed by the contractor, he shall be entitled to receive the difference, and, in case such expense is greater, the party of the first part (which included the contractor and his sureties) shall pay the amount of said excess.’

“The contracts also contained the following provision: 'And said party of the first part (which includes the contractor and his sureties) hereby further agrees that he will furnish the said board of public improvements with satisfactosy evidence that all persons who have done or furnished materials wider this agreement and are entitled to a lien therefor, under any law of the state of Missouri, have been fully paid are no longer entitled to such lien; and in case such evidence be not furnished such amount as the board may consider necessary to meet the lawful claims of the persons aforesaid, provided said persons shall notify said board before the final estimates be returned, shall be retained from the moneys due the said party of the first part under this agreement until the liabilities aforesaid inay be fully discharged.’ Under-paragraph S. of the contract an estimate of the amount of the work done each month is to be made about the first of each succeeding month and a valuation according to the current market prices put thereon; from the amount of such estimate, ten per cent, is to be deducted and the balance certified as due. j

[79]*79“The obligation of Higgins & Sellers binds them ■with McLane to the city of St. Lonis arid for the faithful performance of the foregoing contracts in every particular. The foregoing quotations from the contracts are believed to be sufficient for an understanding of the legal propositions arising upon this record.

“McLane entered upon the work and continued it until the twentieth day of November, 1888, when he •absconded from the state, leaving the work in an unfinished condition. It is conceded that up to the first day of November the city had paid to McLane, for work done and materials furnished under contract number 2071, the sum of $1,003.50. This would leave the sum of $1,796.50 due from the city if- the work should be completed. The work under contract; number 2083 was also left in an unfinished condition. Monthly estimates of the work under this contract had also been made, and, up to the first day of November, McLane had been paid on account thereof $607.50, leaving a balance due from the city, if the work had been completed, of $242.50.

“The work under the third contract had been fully completed and paid for. It was also admitted that, in addition to the amounts earned by McLane under the two contracts, between the first and twentieth of November, the city owed him the sum of $37 for work done at the house of refuge not embraced in either •contract.

‘/When McLane abandoned the contracts, the city made an arrangement with Higgins & Sellers to complete the work. No new contract was entered into. The work was to be completed under the old contracts. Higgins & Sellers finished the work to the satisfaction of the city authorities. A few days after this arrangement with Higgins & Sellers, the O’Neil Lumber -Company, one of the interpleaders, filed a suit in equity [80]*80against McLane and the city, in which it claimed thatMcLane was indebted to it for lumber furnished on account of. said contracts, of the value of $750, and it asked that this amount be charged against the ‘remainder of the money due from the city under the contract. Then followed a like suit by John M. and Edward Doyle, the appellants herein, in which they claimed to have performed work and furnished materials to McLane, under contract number 2071, of the value of $1,304. They sought to make their claim a charge upon the balance due from the city under said contract number 2071. Other mechanics and material-men followed with like suits, but, under the view we have taken of the case, it will not be necessary to notice them. When Higgins & Sellers completed the work, they claimed that the work done and the materials furnished by them in the completion of contract number 2071 actually cost them the sum of $1059.89; that they did work in completing contract number 2083 of the value of $40; and that they did extra work under the last-mentioned contract amounting to $29.50 making-a total of $1,129.30. Their contention was and is now, that as they had earned this amount in the completion of the work, they were entitled to be first paid out of the balance of the funds due under the McLane contracts, in preference to the O’Neil Lumber Company and Doyle Brothers.

“When the city found itself beset with these conflicting claims, it brought into court the amoupt due from it under the McLane contracts, to-wit, $2,105.50. The foregoing facts were stated in its petition, and the court was asked to compel the claimants to interplead for the fund and that they be restrained from the further prosecution of the suits against the city. The necessary orders were made, and thereafter such proceedings were had in the case as to result in a trial between the [81]*81several interpleaders of their respective claims to priority. The court held that Higgins & Sellers must be paid first. This left a balance of $976.11 which the court found had been earned by McLane between the first and twentieth of November. As the O’Neil Lumber Company was' the first to institute suit and have the city served with process, the court gave its claim priority over those of the other interpleaders and ordered it to be paid in full.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Union Reddi-Mix Co. v. Specialty Concrete Contractor
476 S.W.2d 160 (Missouri Court of Appeals, 1972)
State Ex Rel. Auchincloss, Parker & Redpath, Inc. v. Harris
159 S.W.2d 799 (Supreme Court of Missouri, 1942)
Mayne v. St. Louis Union Trust Co.
64 F.2d 843 (Eighth Circuit, 1933)
Wm. B. Joyce & Co. v. Eifert
56 Ind. App. 190 (Indiana Court of Appeals, 1914)
Hutchinson v. Krueger
1912 OK 368 (Supreme Court of Oklahoma, 1912)
EAU Claire-St. Louis Lumber Co. v. Banks
117 S.W. 611 (Missouri Court of Appeals, 1909)
St. Peter's Catholic Church v. Vannote
56 A. 1037 (New Jersey Court of Chancery, 1904)
Keuthan v. St. Louis Trust Co.
73 S.W. 334 (Missouri Court of Appeals, 1903)
Judson v. Walker
55 S.W. 1083 (Supreme Court of Missouri, 1900)
Burnham, Munger & Co. v. Smith
82 Mo. App. 35 (Missouri Court of Appeals, 1899)
City of St. Louis ex rel. Glencoe Lime & Cement Co. v. Von Phul
34 S.W. 843 (Supreme Court of Missouri, 1896)

Cite This Page — Counsel Stack

Bluebook (online)
21 S.W. 484, 114 Mo. 74, 1893 Mo. LEXIS 200, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-st-louis-v-oneil-lumber-co-mo-1893.