City of St. Louis ex rel. Esmar v. Tru-Bounce, Inc.

562 S.W.2d 158, 1978 Mo. App. LEXIS 1959
CourtMissouri Court of Appeals
DecidedJanuary 24, 1978
DocketNos. 37770, 37771
StatusPublished
Cited by2 cases

This text of 562 S.W.2d 158 (City of St. Louis ex rel. Esmar v. Tru-Bounce, Inc.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of St. Louis ex rel. Esmar v. Tru-Bounce, Inc., 562 S.W.2d 158, 1978 Mo. App. LEXIS 1959 (Mo. Ct. App. 1978).

Opinion

STEWART, Judge.

Action by the City of St. Louis at the Relation of Patrick M. Fiandaca III, Administrator C.T.M. D.B.N. of the Estate of William Esmar, deceased (plaintiff), against Tru-Bounce, Incorporated (Tru-Bounce), and Maryland Casualty Company (Maryland) as surety for Tru-Bounce, for monies due under a contract between Tru-Bounce as general contractor and William Esmar (Esmar) as subcontractor. A jury verdict was returned in favor of plaintiff and against both defendants. The verdict against Tru-Bounce was for $16,000, as the amount due under the contract and $1,600 as interest thereon. The verdict against Maryland was for $8,960 for vexatious delay and $6,450 for attorney’s fees.

[160]*160The trial court granted a new trial as to Maryland. It gave as its reasons, error in giving plaintiff’s verdict directing instruction against Maryland, and because the verdict against Maryland was excessive. Plaintiff appeals from the order of the trial court granting Maryland a new trial. Tru-Bounce appeals from the judgment entered against it.

Our disposition of this cause does not require an extensive statement of the facts.

Tru-Bounce entered into a unit price contract with the City of St. Louis to do certain work on a runway at Lambert-St. Louis-International Airport. As part of the contract, Tru-Bounce was to sandblast the runway. After the contract was awarded to Tru-Bounce, it accepted the bid of Esmar to do the sandblasting for a lump sum of $17,000 and entered into a contract in accordance with the bid. Esmar did the sandblasting on the runway at the airport and was paid the sum of $1,000 on account. Tru-Bounce refused to pay the $16,000 balance and Esmar brought this action. Es-mar died during the pendency of the litigation and plaintiff was substituted.

APPEAL OF DEFENDANT TRU-BOUNCE

At the outset we must consider plaintiff’s motion to dismiss the appeal of defendant Tru-Bounce for failure to comply with Rules 84.04(c) and 84.04(d).

Rule 84.04(c) requires a “. concise statement of the facts relevant to the questions presented for determination . ” which may be followed by a resume of the testimony relevant to those issues. The portion of defendant’s brief denominated Statement of Facts is primarily a summary of the testimony of each witness and of the court’s rulings regarding the evidence offered. As such, it is not a proper statement of facts and does not comply with the rule. Graff v. Montileone, 523 S.W.2d 131 (Mo.App.1975).

The point relied on by Tru-Bounce reads:

“The trial court erred in not directing a verdict for Tru-Bounce, Incorporated.
(a) Plaintiff failed to prove a connection between Mr. Skrainka and Tru-Bounce, Incorporated.
(b) The court erred in not allowing defendant Tru-Bounce, Incorporated to read certain portions of Defendant’s Exhibit A.
(c) The court erred in barring witness R. N. Skrainka’s testimony concerning an agreement between him and William Es-mar.” (citations of authority have been omitted)

The point and subpoints fail to state wherein and why any listed action on the part of the trial court is claimed to be erroneous. This point and its subpoints fail to comply with Rule 84.04(d). Donnell v. Vigus Quarries, Inc., 489 S.W.2d 223, 225[3] (Mo.App.1972). We also note that several paragraphs in this section of defendant’s brief lack specific page references to the transcript, in violation of 84.04(h).

Plaintiff’s motion to dismiss the appeal of Tru-Bounce is sustained and the judgment in favor of plaintiff against Tru-Bounce is affirmed.

APPEAL OF PLAINTIFF

The first issue raised by plaintiff is based on the trial court’s order granting Maryland a new trial. The order reads, in part:

“Defendant Maryland Casualty Company’s Motion for a New Trial granted on the grounds the first paragraph of instruction No. 4 was erroneous and the verdict against the defendant was excessive. Verdict and judgment of August 27, 1975 against that defendant set aside.”

Instruction 4 reads:

“Maryland Casualty Company executed and delivered its payment bond to the City of St. Louis to guarantee the payment of any and all amounts due subcontractors performing work on the contract in evidence therefore your verdict must be for the plaintiff William Esmar and against the defendant Maryland Casualty Company if you believe:
[161]*161First, Defendant Tru-Bounce, Incorporated owed plaintiff a balance of $16,000 on its contract with William Esmar, and Second, the defendant Maryland Casualty Company refused to pay plaintiff the sum due him, and
Third, that the refusal of payment by the defendant Maryland Casualty Company was without reasonable cause and was vexatious and that plaintiff was thereby damaged.”

The instruction does not require a finding that Maryland executed its payment bond to the City of St. Louis, but assumes the fact of execution of the bond. Plaintiff contends that such an assumption is not erroneous because the fact of execution of the bond was not controverted. We agree.

Plaintiff, by paragraph 7 of the petition, alleged that Maryland duly executed and gave a bond to the City of St. Louis. A certified copy of the bond was attached to the petition and made a part thereof by reference. Plaintiff also set out the amount and the condition of the bond in detail. Defendant’s answer, as material to our consideration of this issue, reads:

“5. Defendants admit the allegations of paragraph five of Plaintiff’s Second Amended Petition, and deny specifically each and every allegation contained in paragraphs 6, 7, 8, 9,10,11,12,13,14, and 15 of Plaintiff’s Second Amended Petition.
6. Defendants further specifically deny any and all allegations that have not been either admitted or denied in this Answer.”
Controlling is Rule 55.23 which reads: “55.23 Execution of Written Instrument
Deemed Confessed — When
When any claim or defense is founded upon a written instrument and the same shall be set up at length in the pleading or a copy attached thereto as an exhibit, the execution of such instrument shall be deemed confessed unless the party charged to have executed the same shall specifically deny the execution thereof. (Adopted Jan. 19, 1973, effective Sept. 1, 1973.)”

To put the execution of the bond in issue it was necessary for Maryland to make specific reference to that particular allegation. To “specifically deny each and every allegation” of certain numbered paragraphs is a general denial.1 In this case, Maryland’s general denial did not put in issue the execution of the bond. Universal Printing Co. v. Sayre & Fisher Co., 501 S.W.2d 180 (Mo.App.1973); United Farm Agency v. Howald, et al., 263 S.W.2d 889 (Mo.App.1954).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Interstate Petroleum Distributors, Ltd. v. F & B Investments, Inc.
816 S.W.2d 263 (Missouri Court of Appeals, 1991)
Howard Construction Co. v. Teddy Woods Construction Co.
817 S.W.2d 556 (Missouri Court of Appeals, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
562 S.W.2d 158, 1978 Mo. App. LEXIS 1959, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-st-louis-ex-rel-esmar-v-tru-bounce-inc-moctapp-1978.