City of Southlake v. Federal Aviation Administration

679 F. Supp. 618, 1986 U.S. Dist. LEXIS 17062, 1986 WL 20453
CourtDistrict Court, N.D. Texas
DecidedDecember 2, 1986
DocketCA 3-86-2908-R
StatusPublished

This text of 679 F. Supp. 618 (City of Southlake v. Federal Aviation Administration) is published on Counsel Stack Legal Research, covering District Court, N.D. Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Southlake v. Federal Aviation Administration, 679 F. Supp. 618, 1986 U.S. Dist. LEXIS 17062, 1986 WL 20453 (N.D. Tex. 1986).

Opinion

MEMORANDUM OPINION

BUCHMEYER, District Judge.

This suit involves a controversy concerning runway 13R—the new $50 million western northwest/southeast diagonal “crosswind” runway—at the Dallas-Fort Worth International Airport (“DFW”).

Before construction started in late 1983, the Federal Aviation Administration (“FAA”) specifically found that runway 13R was consistent “with existing national environmental policies and objectives as set forth” in the National Environmental Policies Act, 42 U.S.C. § 4331 (“NEPA”). However, some three days before the runway was to be put into operation, 1 the City of Southlake—a community of approximately 5500 people, located directly to the northwest of runway 13R—sought to enjoin any use of this new runway “until such time as defendants have completed [a supplemental] Environmental Impact Statement ... to assess the impact of, and consider alternatives to, unrestricted use” of runway 13R.

Under § 1006 of the Federal Aviation Act, 49 U.S.C. § 1486(a), 2 the exclusive jurisdiction of this controversy—which requires judicial review of the FAA decision that no further environmental clearance was necessary prior to the construction and use of runway 13R—lies with the court of appeals. City of Alexandria v. Helms, 728 F.2d 643, 645 (4th Cir.1984). Therefore, for the reasons discussed below, this case will be dismissed for want of jurisdiction.

I. The Factual Background

In May of 1974, the FAA approved the Final Environmental Impact Statement (“FEIS”) for the development of the DFW Airport. This FEIS covered the environmental impact of “Phase I” of the airport’s master plan: two parallel north/south runways and a northwest/southeast diagonal “crosswind” runway (designated as runway 13L ). 3 It also specifically addressed the runways planned for future construction at DFW: two additional north/south runways and a western northwest/south *620 east diagonal “crosswind” runway (designated runway 13R). 4

Because of economic reasons — some of which are discussed in this Court’s opinion in City of Irving v. Federal Aviation Administration, 539 F.Supp. 17, 20-21 (N.D.Tex.1981) — the construction of runway 13R was delayed. However, the need for additional runways to relieve the increasing congestion and delay at DFW became acute (539 F.Supp. at 21). Therefore, in the fall of 1983, DFW gave notice to the cities surrounding the airport — including the plaintiff Southlake — of the proposed construction and intended use of runway 13R.

DFW then prepared a “Technical Assessment of Final Environmental Impact Statement for Proposed Construction of Runway 13R” (the “Technical Assessment”), and, as required, presented it to the FAA for approval. On October 13, 1983, the FAA issued a “Written Reevaluation of Final Environmental Impact Statement, Dallas/Fort Worth Regional Airport — Proposed Construction of Runway 13R.” This “Reevaluation” approved the DFW Technical Assessment and the construction of runway 13R by stating:

“The proposed construction of Runway 13R/13L is consistent with the Airport Master Plan, which has not been altered. The proposed runway involves property previously acquired for this specific use, does not include any off-airport property, and will not divide any established communities or planned development. The noise analyses showed the impact would not be greater than those projected in the FEIS.... Therefore, the conclusions resulting from the FEIS and confirmed by a thorough review of the Technical Assessment Report, remain applicable, accurate, and valid. After careful and thorough consideration of the facts contained herein, the undersigned finds the proposed Federal Action consistent with existing national environmental policies and objectives as set forth in Section 101(A) of the National Environmental Policies Act of 1969 (NEPA).” (Emphasis added.)

After the FAA advised DFW that the construction of runway 13R was consistent with the FEIS approved in 1974, and that no additional environmental studies were necessary, work was begun on runway 13R in late 1983. Its construction cost almost $50 million — some 2lh times the cost of the first “crosswind” runway completed in 1970 during “Phase I” of the airport’s plans. (See 539 F.Supp. at 19.)

Almost three years after the FAA’s action of October 13, 1983 — and just days before the opening of runway 13R — the City of Southlake filed suit to enjoin the use of this new runway. Southlake alleges, in essence, that in May of 1986 the defendants first announced their intent to use runway 13R in an “unrestricted” manner; that this “unrestricted” use will result in a 100% increase in air traffic on runway 13R, and significantly higher noise levels, than were contemplated in the original FEIS or in the 1983 Technical Assessment; and that, therefore, an “adequate” or “supplemental” environmental impact statement must be prepared by DFW and approved by the FAA before runway 13R can be placed in use.

The FAA and the other defendants 5 all deny that the intended usage of runway 13R differs in any significant way from that contemplated in the FEIS and the 1983 Technical Assessment. They also contend that Southlake had known of the intended use of runway 13R for years before construction was begun; that Southlake, over the objections of DFW, actually rezoned property to permit residential development near the end of runway 13R (see 539 F.Supp. at 33); and that the noise levels from the “actual” intended use of runway *621 13R will be even less than those approved by the FAA in the May 1974 FEIS.

The temporary restraining order sought by Southlake was denied by this Court — in part because each defendant, by motions to dismiss, raised serious questions concerning the jurisdiction of this Court in view of 49 U.S.C. § 1486(a).

II. The Law

49 U.S.C. § 1486(a) explicitly provides that orders of the FAA are subject to review only “by the courts of appeals ... or the United States Court of Appeals for the District of Columbia.” Because of § 1486(a), this Court has no jurisdiction to review an order of the FAA — even where the basic complaint is that the FAA has failed to require the preparation of an environmental impact statement under NEPA. City of Alexandria v. Helms, 728 F.2d 643 (4th Cir.1984).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
679 F. Supp. 618, 1986 U.S. Dist. LEXIS 17062, 1986 WL 20453, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-southlake-v-federal-aviation-administration-txnd-1986.