City of South Bend v. Surface Transportation Board

566 F.3d 1166, 386 U.S. App. D.C. 120, 2009 U.S. App. LEXIS 11503, 2009 WL 1492555
CourtCourt of Appeals for the D.C. Circuit
DecidedMay 29, 2009
Docket08-1150, 08-1301
StatusPublished
Cited by13 cases

This text of 566 F.3d 1166 (City of South Bend v. Surface Transportation Board) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of South Bend v. Surface Transportation Board, 566 F.3d 1166, 386 U.S. App. D.C. 120, 2009 U.S. App. LEXIS 11503, 2009 WL 1492555 (D.C. Cir. 2009).

Opinion

GINSBURG, Circuit Judge:

The City of South Bend and the Brothers of the Holy Cross petition for review of orders of the Surface Transportation Board (1) denying their application for adverse abandonment of two railroad lines in South Bend, Indiana, and (2) refusing to reopen the proceeding. The petitioners *1168 argue the Board’s orders were arbitrary and capricious under the Administrative Procedure Act. We deny the petitions for review because in both instances the Board acted reasonably.

I. Background

The Congress has delegated to the Board exclusive jurisdiction to regulate “transportation by rail carriers” and “the construction, acquisition, operation, abandonment, or discontinuance” of rail facilities, see 49 U.S.C. § 10501(b), with the instruction that the agency “ensure the development and continuation of a sound rail transportation system,” id. § 10101(4). A rail carrier may abandon a line upon its own petition or that of a third party with a “proper interest,” Modern Handcraft, Inc., 363 I.C.C. 969, 971 (1981) (adjacent landowner and transportation authority have standing), “only if the Board finds that the present or future public convenience and necessity require or permit the abandonment,” 49 U.S.C. § 10903(d). Abandonment frees subservient landowners to exercise reversionary rights in, and local governments to condemn, the railroad’s right-of-way. See Hayfield N. R.R. Co. v. Chicago & N.W. Transp. Co., 467 U.S. 622, 633-34, 104 S.Ct. 2610, 81 L.Ed.2d 527 (1984). Because reassembling a right-of-way may be difficult if not impractical, the Board must, before authorizing an abandonment, give weight to its “statutory duty to preserve and promote continued rail service.” N.Y. Cross Harbor R.R. v. STB, 374 F.3d 1177, 1187 (D.C.Cir.2004).

In 2006 the petitioners applied for adverse abandonment of two interconnected short branch rail lines that together run for 3.7 miles through South Bend. The current owner, Norfolk Southern Railway Company (NS), has neither maintained nor used either line. One line serves a coal-fired power plant on the campus of the University of Notre Dame, but the University stopped receiving coal by rail in the mid-1990s. Notre Dame now receives 3,500 truck loads of coal per year from a transloading facility six miles from campus. According to the petitioners, there is no evidence Notre Dame or anyone else is or will be interested in renewed rail service. Thus, they argued before the Board, the public interest favors abandonment so the City can construct a sewer system and a recreational trail through the right-of-way and the Brothers and the Sisters of the Holy Cross can exercise their reversionary interests in order to expand their campuses.

The Chicago, Lake Shore and South Bend Railway Company (CLS), a start-up short branch railroad, opposed the application. CLS hopes to buy the lines from NS and persuade Notre Dame to resume accepting coal by rail. NS took no position on the application but explained that, if the lines are not abandoned, rehabilitating them would be feasible.

The Board denied the petitioners’ application on the ground that there is “a reasonable potential for future” use of the lines. Norfolk S. Ry. Co., No. AB-290 (Sub-No. 286), 2008 WL 391303, slip op. at 3-4, 6-7 (Feb. 13, 2008) (NS I). The Board acknowledged that, according to an article in the South Bend Tribune put into the record by the petitioners, the Executive Vice-President of Notre Dame, John Affleek-Graves, said that opposition from the city government and neighborhood residents stood in the way of the University’s “considering] using rail service again for coal deliveries.” Id. at 5 n. 14. The Board, however, explained that the practice of transloading coal for daily shipments by truck would not make economic sense if CLS were to rehabilitate the lines to restore rail service to the plant. Id. at 4. The Board deemed the City’s development projects, which could go forward without the lines being abandoned, and the Broth *1169 ers’ concern about the construction cost of rerouting a road in order to expand the campus, insufficient to outweigh the public interest in preserving the lines. Id. at 6-7. In sum, because (a) Notre Dame might in the future, “under appropriate circumstances,” accept coal by rail, and (b) there was no substantial countervailing interest in immediate abandonment, the Board declined to “short-circuit” CLS’s plan to restore rail service. Id. at 7. At the same time, the Board invited the petitioners to renew their challenge if, after a “reasonable period of time,” CLS was unable to restore operations. Id. *

Some weeks later the petitioners asked the Board to reopen the proceeding in light of a letter the Board had received from Affleck-Graves. The Board, with one member in dissent, denied the petition, concluding the letter presented no new information and the petitioners could have solicited a similar letter earlier. See Norfolk S. Ry. Co., No. AB-290 (Sub-No. 286), 2008 WL 3971092, slip op. at 2-4 (Aug. 26, 2008) (NS II).

II. Analysis

We review the Board’s denial of the petitioners’ application under the highly deferential arbitrary-and-capricious standard of the APA. See 5 U.S.C. § 706(2)(A); Cross Harbor, 374 F.3d at 1181; Burlington N. R.R. Co. v. STB, 114 F.3d 206, 210 (D.C.Cir.1997); see also Chicago & N.W. Transp. Co. v. Kalo Brick & Tile Co., 450 U.S. 311, 321, 101 S.Ct. 1124, 67 L.Ed.2d 258 (1981) (Board’s assessment of public convenience and necessity “entitled to considerable deference”). Here the Board correctly allocated the burden to the petitioners, see Cross Harbor, 374 F.3d at 1186, duly balanced the relevant interests, see id. at 1183, and reasonably determined that preserving the right-of-way for a time in order to serve potential future demand outweighed the petitioners’ interest in immediate abandonment, see Seminole Gulf Ry., No. AB-400 (Sub-No. 4), 2004 WL 2618630, at *4 (S.T.B. Nov. 17, 2004); Salt Lake City Corp., No. AB-33 (Sub-No. 183), 2002 WL 368014, at *6 (S.T.B. Mar. 6, 2002). **

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
566 F.3d 1166, 386 U.S. App. D.C. 120, 2009 U.S. App. LEXIS 11503, 2009 WL 1492555, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-south-bend-v-surface-transportation-board-cadc-2009.