City of Savage v. Formanek

459 N.W.2d 173, 1990 Minn. App. LEXIS 837, 1990 WL 119444
CourtCourt of Appeals of Minnesota
DecidedAugust 21, 1990
DocketC3-90-110
StatusPublished
Cited by18 cases

This text of 459 N.W.2d 173 (City of Savage v. Formanek) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Savage v. Formanek, 459 N.W.2d 173, 1990 Minn. App. LEXIS 837, 1990 WL 119444 (Mich. Ct. App. 1990).

Opinion

OPINION

NORTON, Judge.

Appellant, City of Savage, appeals from a judgment voiding its contract with respondents, Formaneks, and excusing respondents from further performance because the agreement was unenforceable.

FACTS

Respondents, the Formaneks, have owned land in the City of Savage since 1959. In 1980, the City of Savage (City) started planning an industrial development project (Project) that included twenty acres of land owned by the Formaneks. The Project area, along with much of the land along the Minnesota River in Savage, is under the authority of the Army Corps of Engineers. This means that any fill or development requires a permit from the *174 Corps. The Corps has two methods of issuing permits. One is through “discretionary authority,” which means that any fill in an area must be approved by the Corps and a permit issued on a case-by-case basis. The second is through a nationwide permit system. This is a default method where the Corps has issued a blanket permit covering all areas that are not covered by discretionary authority. The Forma-neks were aware of the Corps requirements because they owned land not in the Project area that was subject to the Corps’ discretionary authority.

In late 1983, as part of the Project, an Environmental Assessment Worksheet (EAW) was sent to the Corps. The purpose of the EAW was to give notice to interested government agencies of the planned development of the Project and to indicate what environmental effect it would have. In January 1984, the City received notice from the Corps that the Project was authorized by the nationwide permit system. The City interpreted the Corps’ January 1984 response as granting a permit for the total project; both Phase I, the installation of sewer and road improvements, and Phase II, the actual industrial development. The Corps indicated later that only Phase I was permitted.

The Formaneks were aware of the potential negative effect of Corps discretionary authority on the ability of landowners to develop their property. They made several contacts with the City engineer and representatives of the Corps to assure themselves that all permits for the Project were complete. Also, during the planning of the Project, the Corps was expanding its authority in another area of Savage, the Savage Fen, about a half-mile from the Project. This Fen area included the other Formanek property which was already under Corps’ discretionary authority. The Fen area had been determined a unique wetland plant community that was in need of special environmental protection. Both the Formaneks and the City believed that the Formaneks Project property was not a wetland and therefore not in need of any protection that would require Corps’ discretionary authority. The Formaneks and other City officials were assured by the City engineer in charge of the project that the expansion of discretionary authority concerning the Fen area did not affect the Project and that permitting for the Project was complete.

In order to pay for the Project, the City planned a combination of special assessments to the current landowners and tax increment financing. The tax increment financing was necessary because the cost of the improvements, approximately $3.4 million, would have made assessments prohibitive. The tax increment financing was dependent on successful development that would result in an increased tax base and thereby provide the funds for paying the debt.

To assure that the special assessments would be paid, the City and the landowners entered into assessment agreements. The agreements gave the City a lien in all assessed property. The Formaneks signed their agreement on April 24, 1984. The improvements in the Project area were started in the summer of 1984 and completed in early 1985.

On March 4, 1985, the City received notice that the Corps was taking discretionary authority of the Project. The designation of the Project within the Corps’ discretionary authority has effectively halted any development. The mayor admitted that the designation has left much of the land in an unusable condition. Five private landowners in the Project area have sought permits and been rejected. The only permit that has been approved was on land owned by the state that was being purchased by the City. The City has encouraged the private landowners to stop asking for permits on an individual basis and work with the City to come up with some agreement with the Corps for development. The Formaneks have not found anyone interested in purchasing their property or developing it because of the permit requirement. The Formaneks have not sought a permit for their property because they have no development proposal to support it. The Formaneks made their first assessment *175 payment in 1985 of $31,362.57 but have made no further payments.

The City brought an action claiming breach of the assessment agreement-and sought to foreclose on the Formaneks’ property. The Formaneks counterclaimed saying that the agreement was unenforceable and that their payment of the assessment should be refunded to them with interest. The only issue litigated at trial was the enforceability of the assessment agreement. The trial court found the agreement void because both parties were mistaken as to a material fact concerning the agreement. The court also found that the For-maneks would have been excused from performance because of frustration of purpose. Because only the enforceability of the agreement was litigated, the trial court left open the possibility that the City could bring a claim for any benefit that the improvements placed on the landowners’ property.

ISSUES

1. Did the trial court err in voiding the assessment agreement based on mutual mistake?

2. Did the trial court err in excusing the Formaneks’ duties under the assessment agreement?

3. Did the trial court err in denying the Formaneks’ request for attorney fees?

ANALYSIS

On appeal from a judgment, an appellate court reviews whether the evidence sustains the findings and whether the findings sustain the conclusions of law and judgment. Minnesota Power & Light Co. v. Carlton County, 275 Minn. 101, 102 n. 1, 145 N.W.2d 68, 70 n. 1 (1966).

Mutual Mistake

“If there is a mutual mistake concerning a material fact, parties to a contract may avoid the contract.” Winter v. Skoglund, 404 N.W.2d 786, 793 (Minn.1987) (footnote omitted).

Where a mistake of both parties at the time a contract was made as to a basic assumption on which the contract was made has a material effect on the agreed exchange of performances, the contract is voidable by the adversely affected party unless he bears the risk of the mistake * * *.

Id. (quoting Restatement (Second) of Contracts § 152(1) (1981)).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fitness International, LLC v. City Center Ventures, LLC
9 N.W.3d 526 (Supreme Court of Minnesota, 2024)
Doug Hoskin v. Josh Krsnak
Court of Appeals of Minnesota, 2024
August Ventures, LLC v. Gedney Foods Company
Court of Appeals of Minnesota, 2024
State of Minnesota v. Melissa Rae Guillette
Court of Appeals of Minnesota, 2016
Swenson v. Bender
764 N.W.2d 596 (Court of Appeals of Minnesota, 2009)
Hopfenspirger v. West
949 So. 2d 1050 (District Court of Appeal of Florida, 2006)
Bolander v. Bolander
703 N.W.2d 529 (Court of Appeals of Minnesota, 2005)
Pieper, Inc. v. Land O'Lakes
Eighth Circuit, 2004
Chalmers v. Kanawyer
544 N.W.2d 795 (Court of Appeals of Minnesota, 1996)
Felt v. McCarthy
898 P.2d 315 (Court of Appeals of Washington, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
459 N.W.2d 173, 1990 Minn. App. LEXIS 837, 1990 WL 119444, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-savage-v-formanek-minnctapp-1990.