City of Santa Fe v. Travelers Casualty & Surety Co.

2010 NMSC 010, 228 P.3d 483, 147 N.M. 699
CourtNew Mexico Supreme Court
DecidedFebruary 16, 2010
Docket31,549
StatusPublished
Cited by12 cases

This text of 2010 NMSC 010 (City of Santa Fe v. Travelers Casualty & Surety Co.) is published on Counsel Stack Legal Research, covering New Mexico Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Santa Fe v. Travelers Casualty & Surety Co., 2010 NMSC 010, 228 P.3d 483, 147 N.M. 699 (N.M. 2010).

Opinion

OPINION

CHÁVEZ, Chief Justice.

{1} The City of Santa Fe contracted with Lone Mountain Contracting, Inc., to repair a water tank. The contract did not contain a time-to-sue provision, and therefore the six-year statute of limitations applied to the contract. See NMSA 1978, § 37-1-3 (1880, as amended through 1975). To comply with Section 13-4-18(A)(l) of the Little Miller Act, NMSA 1978, §§ 13^-18 to -20 (1923, as amended through 1987), Lone Mountain obtained a performance bond from Travelers Casualty and Surety Company. The bond contained a two-year time-to-sue provision. Santa Fe declared Lone Mountain in default and demanded performance by Travelers on September 29, 2004. Santa Fe ultimately sued Travelers on May 14, 2007. The district court granted summary judgment to Travelers, holding that the two-year time-to-sue provision in the bond applied and barred the lawsuit for being untimely. The Court of Appeals agreed, relying on State ex rel. Udall v. Colonial Penn Insurance Co., 112 N.M. 123, 812 P.2d 777 (1991). City of Santa Fe v. Travelers Cas. & Sur. Co., No. 28,944, slip op. at 3 (N.M.Ct.App. Jan. 14, 2008). We reverse and hold that unless the governmental entity directly contracts for a shorter time-to-sue provision with either the contractor or the surety, a shorter time-to-sue provision contained in a performance bond is unenforceable. To hold otherwise would be to permit the contractor and the surety to unilaterally negotiate terms that would frustrate the purpose of the Little Miller Act, which is to ensure that governmental entities are afforded the fullest protection for the completion of contracts.

BACKGROUND

{2} Santa Fe contracted with Lone Mountain in 2003 to repaii' a water tank. To comply with Section 13^4-18(A)(1), Lone Mountain obtained a performance bond from Travelers. Although the contract between Santa Fe and Lone Mountain did not contain a time-to-sue provision, the bond issued by Travelers contained the following provision:

Any proceeding, legal or equitable, under this Bond ... shall be instituted within two years after Contractor Default or within two years after the Contractor ceased working or within two years after the Surety refuses or fails to perform its obligations under this Bond, whichever occurs first. If the provisions of this Paragraph are void or prohibited by law, the minimum period of limitation available to sureties as a defense in the jurisdiction of the suit shall be applicable.

{3} On September 29, 2004, Santa Fe declared Lone Mountain in default and demanded performance from Travelers. Travelers denied the claim on October 28, 2005. After negotiations failed and Travelers invoked the two-year time-to-sue provision, Santa Fe filed a complaint for declaratory judgment in district court on May 14, 2007, seeking application of the six-year statute of limitations under Section 37-l-3(A). The district court granted summary judgment to Travelers and the Court of Appeals affirmed.

{4} Santa Fe advances two arguments for reversing the Court of Appeals. First, if a contractor and its surety are permitted to negotiate a shorter time-to-sue provision between themselves, the public policy underlying the Little Miller Act would be frustrated. Second, reliance by the Court of Appeals on Udall is misplaced, because unlike the parties in Udall, where the governmental entity contracted directly with the surety for a shorter time-to-sue provision, Santa Fe and Travelers did not contract directly for a shorter time-to-sue provision. Travelers counters by arguing that freedom to contract principles control under Udall because Santa Fe was required by the Little Miller Act to accept the bond as satisfactory, making Santa Fe a party to the bond. We agree with Santa Fe.

PUBLIC POLICY FORBIDS A SURETY FROM SHORTENING TIME-TO-SUE PROVISIONS IN A PERFORMANCE BOND UNLESS IT DIRECTLY CONTRACTS WITH THE GOVERNMENTAL ENTITY TO DO SO

{5} Section 13-A-18(A)(1) of the Little Miller Act provides, in relevant part: Award of the contract shall be made pursuant to the Procurement Code [13-1-28 NMSA1978] in the following manner:

(1) a performance bond satisfactory to the state agency or local public body, executed by a surety company authorized to do business in this state and said surety to be approved in federal circular 570 as published by the United States treasury department or the state board of finance or the local governing authority, in an amount equal to one hundred percent of the price specified in the contract^]

Whether the public policy underlying the Little Miller Act allows sureties to contractually limit the time the governmental entity has to sue is a question of law that we review de novo. State v. Lucero, 2007-NMSC-041, ¶ 8, 142 N.M. 102, 163 P.3d 489 (“We review issues of statutory and constitutional interpretation de novo.”); K.R. Swerdfeger Constr., Inc. v. Bd. of Regents, Univ. of N.M., 2006-NMCA-117, ¶ 23, 140 N.M. 374, 142 P.3d 962 (“Whether a contract is against public policy is a question of law for the court to determine from all the circumstances of each case.” (internal quotation marks and citation omitted)).

{6} New Mexico appellate courts have stated that performance bonds are required by the Little Miller Act for the protection of the public and to assure performance of governmental contracts. See N.M. State Highway & Transp. Dep’t v. Gulf Ins. Co., 2000-NMCA-007, ¶ 16, 128 N.M. 634, 996 P.2d 424 (“The performance bond protects the State by ensuring completion of the contract!.]”); Employment Sec. Comm’n v. C.R. Davis Contracting Co., 81 N.M. 23, 25, 462 P.2d 608, 610 (1969) (“Statutory bonds are required for the benefit and protection of the public.”). In Silver v. Fidelity & Deposit Co. of Maryland, 40 N.M. 33, 40, 53 P.2d 459, 463-64 (1935), we articulated the legislative purpose for enacting the performance bond requirement of the Little Miller Act: to protect the public through the security afforded by the bond by assuring that claims will be paid.

{7} Section 13-4-18 reinforces this purpose by requiring that the performance of the contractor be bonded up to one hundred percent of the contract price by either a full performance bond or a combination performance bond and self-insurance by the governmental entity. See § 13-4-18(A), (B). It is clear that the surety cannot unilaterally limit its exposure to the governmental entity. It must assume the same obligations to the governmental entity as did the contractor. See Gulf Ins. Co., 2000-NMCA-007, ¶ 17, 128 N.M. 634, 996 P.2d 424 (“[B]y bonding the project, the surety steps into the shoes of not only the contractor, but also of the laborers and materialmen paid by it, and of the government.”); see also Gloucester City Bd. of Educ. v. Am. Arbitration Ass’n, 333 N.J.Super. 511, 755 A.2d 1256, 1265 (2000) (discussing a New Jersey statute for bonding on public works projects: “[i]n our view, the intent of N.J.S.A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Smith v. AAA
New Mexico Supreme Court, 2024
State ex rel. Off. of St. Eng'r v. Romero
New Mexico Supreme Court, 2022
State v. Montoya
2015 NMSC 010 (New Mexico Court of Appeals, 2015)
State v. Montoya
New Mexico Supreme Court, 2015
State v. Vasquez
2014 NMSC 10 (New Mexico Supreme Court, 2014)
State ex rel. Office of State Eng'r v. Elephant Butte Irrigation Dist.
2012 NMCA 90 (New Mexico Court of Appeals, 2012)
State v. Burton
New Mexico Court of Appeals, 2012
Arnold v. Farmers Ins. Co. of Arizona
827 F. Supp. 2d 1289 (D. New Mexico, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
2010 NMSC 010, 228 P.3d 483, 147 N.M. 699, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-santa-fe-v-travelers-casualty-surety-co-nm-2010.