NUMBER 13-23-00342-CV
COURT OF APPEALS
THIRTEENTH DISTRICT OF TEXAS
CORPUS CHRISTI – EDINBURG
CITY OF SAN ANTONIO, ACTING BY AND THROUGH CITY PUBLIC SERVICE BOARD, Appellant,
v.
SPECTRUM GULF COAST, LLC, Appellee.
ON APPEAL FROM THE 408TH DISTRICT COURT OF BEXAR COUNTY, TEXAS
MEMORANDUM OPINION
Before Justices Benavides, Tijerina, and Silva Memorandum Opinion by Justice Silva
Appellant City of San Antonio, acting by and through City Public Service Board
(CPS Energy), appeals the trial court’s order granting partial summary judgment in favor of appellee Spectrum Gulf Coast, LLC (Spectrum). 1 By five issues, CPS Energy argues
that the trial court erred by entering a partial summary judgment finding that it breached
its 1984 contract with Spectrum because (1) the contract provision requiring compliance
with all applicable laws did not contemplate or incorporate a 2005 statute; (2) even if the
contract incorporated future laws, it did not incorporate the 2005 statute; (3) the 2005
statute only applied to contracts entered into after September 1, 1995; (4) Spectrum’s
breach of contract action is improperly predicated on violation of a statute that provides
no private right of action; and (5) the 2005 statute’s prohibition on price discrimination
was not violated. We reverse and remand.
I. BACKGROUND 2
According to Spectrum’s live pleading, it entered into a contract with CPS Energy
in 1984 that allowed Spectrum to use CPS Energy’s utility poles to provide
communications services, such as broadband internet service. 3 Part of the contract
required the parties to “observe and comply with . . . all laws, ordinances, and regulations
1 This appeal is governed by the September 1, 2005 amendment to Texas Civil Practice and
Remedies Code § 51.014(d), which allows a trial court to issue a written order permitting an interlocutory appeal if: “(1) the parties agree that the order involves a controlling question of law as to which there is a substantial ground for difference of opinion; (2) an immediate appeal from the order may materially advance the ultimate termination of the litigation; and (3) the parties agree to the order.” Act of June 18, 2005, 79th Leg., ch. 1051, § 2005 Tex. Gen. Laws 3512, 3512–13 §§ 1, 2, eff. June 18, 2005 (amended 2011) (current version at TEX. CIV. PRAC. & REM. CODE ANN. § 51.014(d)). 2 This case is before this Court on transfer from the Fourth Court of Appeals in San Antonio pursuant to a docket-equalization order issued by the Supreme Court of Texas. See TEX. GOV’T CODE ANN. §§ 22.220(a) (delineating the jurisdiction of appellate courts), 73.001 (granting the supreme court the authority to transfer cases from one court of appeals to another at any time that there is “good cause” for the transfer). Because this is a transfer case, we apply the precedent of the San Antonio Court of Appeals to the extent it differs from our own. See TEX. R. APP. P. 41.3. 3 The contract was originally between Rogers Cablesystems of Texas and CPS Energy; however,
Spectrum is Rogers’ successor in interest. For simplicity’s sake, we discuss the contract as being entered into between Spectrum and CPS Energy.
2 which in any manner affect the rights and obligations of the parties hereto under the
[a]greement, so long as such laws, ordinances[,] or regulations remain in effect.”
In 2005, the Legislature amended § 54.204 of the Texas Utilities Code, which
prohibits “discriminat[ion] in favor of or against a certified telecommunications provider
regarding municipal utility pole attachment.” TEX. UTIL. CODE ANN. § 54.204(b)(1).
Moreover, § 54.204(c) states:
[a] municipality or a municipally owned utility may not charge any entity, regardless of the nature of the services provided by that entity, a pole attachment rate or underground conduit rate that exceeds the fee the municipality or municipally owned utility would be permitted to charge under rules adopted by the Federal Communications Commission [(FCC)] under 47 U.S.C. [§] 224(e) if the municipality’s or municipally owned utility’s rates were regulated under federal law and the rules of the [FCC]. In addition, not later than September 1, 2006, a municipality or municipally owned utility shall charge a single, uniform pole attachment or underground conduit rate to all entities that are not affiliated with the municipality or municipally owned utility regardless of the services carried over the networks attached to the poles or underground conduit.
Id. § 54.204(c).
Spectrum’s live pleading further alleged that CPS Energy violated the law by
effectively charging it and AT&T substantially different pole attachment rates, to AT&T’s
advantage. Spectrum discovered the discrepancy and paid its invoices under protest.
Eventually, the Texas Public Utility Commission (PUC) concluded that CPS Energy’s
conduct violated § 54.204(b), a holding that was affirmed by the Supreme Court of Texas
in 2019. See Time Warner Cable Tex. LLC v. CPS Energy, 593 S.W.3d 291, 296 (Tex.
2019). Spectrum also claimed that the PUC found that CPS Energy violated § 54.204(c)
by charging it in excess of the maximum allowable rates in 2008, 2009, and 2010, though,
the Supreme Court of Texas declined to review that finding. Spectrum brought six causes
3 of action against CPS Energy: (1–2) violations of § 54.204(b), (c); (3) breach of contract;
(4) breach of fiduciary duty; (5) unjust enrichment; and (6) negligence. See TEX. UTIL.
CODE ANN. § 54.204(b), (c).
CPS Energy filed a counterclaim, alleging in its live petition that Spectrum
breached their contract by failing to pay the contracted-for rates. CPS Energy’s causes
of actions included (1) breach of contract, (2) violation of the Texas Theft Liability Act,
and (3) violations of the Texas Penal Code. CPS Energy also sought declaratory relief.
Each party filed a competing motion for partial summary judgment on their breach
of competing contract claims, specifically seeking partial summary judgment as to the
element of breach. The trial court ultimately granted Spectrum’s motion for partial
summary judgment, finding that CPS Energy breached the parties’ contract. The trial
court also granted CPS Energy’s request for permissive appeal, posing the controlling
question of law as: “Whether CPS Energy breached the parties’ agreement by unlawfully
imposing discriminatory rates on Spectrum[?]” See Act of June 18, 2005, 79th Leg., R.S.,
ch. 1051, § 2, 2005 Tex. Gen. Laws. 3512, 3512–13 (amended 2011) (current version at
TEX. CIV. PRAC. & REM. CODE ANN. § 51.014(d)) (allowing permissive appeals only when
the appealed order “involves a controlling question of law” and “an immediate appeal from
the order may materially advance the ultimate termination of the litigation”); Indus.
Specialists, LLC v. Blanchard Refin. Co., 652 S.W.3d 11, 16 (Tex. 2022) (discussing
these requirements and explaining that “courts have no discretion to permit or accept an
appeal if the two requirements are not satisfied”).
4 II. STANDARD OF REVIEW AND APPLICABLE LAW
“The elements of a breach of contract claim are ‘(1) a valid contract; (2) the plaintiff
performed or tendered performance; (3) the defendant breached the contract; and (4) the
plaintiff was damaged as a result of the breach.’” Brooks v. Excellence Mortg., Ltd., 486
S.W.3d 29, 36 (Tex. App.—San Antonio 2015, pet. denied) (quoting McLaughlin, Inc. v.
Free access — add to your briefcase to read the full text and ask questions with AI
NUMBER 13-23-00342-CV
COURT OF APPEALS
THIRTEENTH DISTRICT OF TEXAS
CORPUS CHRISTI – EDINBURG
CITY OF SAN ANTONIO, ACTING BY AND THROUGH CITY PUBLIC SERVICE BOARD, Appellant,
v.
SPECTRUM GULF COAST, LLC, Appellee.
ON APPEAL FROM THE 408TH DISTRICT COURT OF BEXAR COUNTY, TEXAS
MEMORANDUM OPINION
Before Justices Benavides, Tijerina, and Silva Memorandum Opinion by Justice Silva
Appellant City of San Antonio, acting by and through City Public Service Board
(CPS Energy), appeals the trial court’s order granting partial summary judgment in favor of appellee Spectrum Gulf Coast, LLC (Spectrum). 1 By five issues, CPS Energy argues
that the trial court erred by entering a partial summary judgment finding that it breached
its 1984 contract with Spectrum because (1) the contract provision requiring compliance
with all applicable laws did not contemplate or incorporate a 2005 statute; (2) even if the
contract incorporated future laws, it did not incorporate the 2005 statute; (3) the 2005
statute only applied to contracts entered into after September 1, 1995; (4) Spectrum’s
breach of contract action is improperly predicated on violation of a statute that provides
no private right of action; and (5) the 2005 statute’s prohibition on price discrimination
was not violated. We reverse and remand.
I. BACKGROUND 2
According to Spectrum’s live pleading, it entered into a contract with CPS Energy
in 1984 that allowed Spectrum to use CPS Energy’s utility poles to provide
communications services, such as broadband internet service. 3 Part of the contract
required the parties to “observe and comply with . . . all laws, ordinances, and regulations
1 This appeal is governed by the September 1, 2005 amendment to Texas Civil Practice and
Remedies Code § 51.014(d), which allows a trial court to issue a written order permitting an interlocutory appeal if: “(1) the parties agree that the order involves a controlling question of law as to which there is a substantial ground for difference of opinion; (2) an immediate appeal from the order may materially advance the ultimate termination of the litigation; and (3) the parties agree to the order.” Act of June 18, 2005, 79th Leg., ch. 1051, § 2005 Tex. Gen. Laws 3512, 3512–13 §§ 1, 2, eff. June 18, 2005 (amended 2011) (current version at TEX. CIV. PRAC. & REM. CODE ANN. § 51.014(d)). 2 This case is before this Court on transfer from the Fourth Court of Appeals in San Antonio pursuant to a docket-equalization order issued by the Supreme Court of Texas. See TEX. GOV’T CODE ANN. §§ 22.220(a) (delineating the jurisdiction of appellate courts), 73.001 (granting the supreme court the authority to transfer cases from one court of appeals to another at any time that there is “good cause” for the transfer). Because this is a transfer case, we apply the precedent of the San Antonio Court of Appeals to the extent it differs from our own. See TEX. R. APP. P. 41.3. 3 The contract was originally between Rogers Cablesystems of Texas and CPS Energy; however,
Spectrum is Rogers’ successor in interest. For simplicity’s sake, we discuss the contract as being entered into between Spectrum and CPS Energy.
2 which in any manner affect the rights and obligations of the parties hereto under the
[a]greement, so long as such laws, ordinances[,] or regulations remain in effect.”
In 2005, the Legislature amended § 54.204 of the Texas Utilities Code, which
prohibits “discriminat[ion] in favor of or against a certified telecommunications provider
regarding municipal utility pole attachment.” TEX. UTIL. CODE ANN. § 54.204(b)(1).
Moreover, § 54.204(c) states:
[a] municipality or a municipally owned utility may not charge any entity, regardless of the nature of the services provided by that entity, a pole attachment rate or underground conduit rate that exceeds the fee the municipality or municipally owned utility would be permitted to charge under rules adopted by the Federal Communications Commission [(FCC)] under 47 U.S.C. [§] 224(e) if the municipality’s or municipally owned utility’s rates were regulated under federal law and the rules of the [FCC]. In addition, not later than September 1, 2006, a municipality or municipally owned utility shall charge a single, uniform pole attachment or underground conduit rate to all entities that are not affiliated with the municipality or municipally owned utility regardless of the services carried over the networks attached to the poles or underground conduit.
Id. § 54.204(c).
Spectrum’s live pleading further alleged that CPS Energy violated the law by
effectively charging it and AT&T substantially different pole attachment rates, to AT&T’s
advantage. Spectrum discovered the discrepancy and paid its invoices under protest.
Eventually, the Texas Public Utility Commission (PUC) concluded that CPS Energy’s
conduct violated § 54.204(b), a holding that was affirmed by the Supreme Court of Texas
in 2019. See Time Warner Cable Tex. LLC v. CPS Energy, 593 S.W.3d 291, 296 (Tex.
2019). Spectrum also claimed that the PUC found that CPS Energy violated § 54.204(c)
by charging it in excess of the maximum allowable rates in 2008, 2009, and 2010, though,
the Supreme Court of Texas declined to review that finding. Spectrum brought six causes
3 of action against CPS Energy: (1–2) violations of § 54.204(b), (c); (3) breach of contract;
(4) breach of fiduciary duty; (5) unjust enrichment; and (6) negligence. See TEX. UTIL.
CODE ANN. § 54.204(b), (c).
CPS Energy filed a counterclaim, alleging in its live petition that Spectrum
breached their contract by failing to pay the contracted-for rates. CPS Energy’s causes
of actions included (1) breach of contract, (2) violation of the Texas Theft Liability Act,
and (3) violations of the Texas Penal Code. CPS Energy also sought declaratory relief.
Each party filed a competing motion for partial summary judgment on their breach
of competing contract claims, specifically seeking partial summary judgment as to the
element of breach. The trial court ultimately granted Spectrum’s motion for partial
summary judgment, finding that CPS Energy breached the parties’ contract. The trial
court also granted CPS Energy’s request for permissive appeal, posing the controlling
question of law as: “Whether CPS Energy breached the parties’ agreement by unlawfully
imposing discriminatory rates on Spectrum[?]” See Act of June 18, 2005, 79th Leg., R.S.,
ch. 1051, § 2, 2005 Tex. Gen. Laws. 3512, 3512–13 (amended 2011) (current version at
TEX. CIV. PRAC. & REM. CODE ANN. § 51.014(d)) (allowing permissive appeals only when
the appealed order “involves a controlling question of law” and “an immediate appeal from
the order may materially advance the ultimate termination of the litigation”); Indus.
Specialists, LLC v. Blanchard Refin. Co., 652 S.W.3d 11, 16 (Tex. 2022) (discussing
these requirements and explaining that “courts have no discretion to permit or accept an
appeal if the two requirements are not satisfied”).
4 II. STANDARD OF REVIEW AND APPLICABLE LAW
“The elements of a breach of contract claim are ‘(1) a valid contract; (2) the plaintiff
performed or tendered performance; (3) the defendant breached the contract; and (4) the
plaintiff was damaged as a result of the breach.’” Brooks v. Excellence Mortg., Ltd., 486
S.W.3d 29, 36 (Tex. App.—San Antonio 2015, pet. denied) (quoting McLaughlin, Inc. v.
Northstar Drilling Techs., Inc., 138 S.W.3d 24, 27 (Tex. App.—San Antonio 2004, no
pet.)). “A breach of contract occurs when a party fails to perform an act that it has
expressly or impliedly promised to perform.” Tabe v. Tex. Inpatient Consultants, LLLP,
555 S.W.3d 382, 385 (Tex. App.—Houston [1st Dist.] 2018, pet. denied) (quoting Case
Corp. v. Hi–Class Bus. Sys. of Am., Inc., 184 S.W.3d 760, 769–70 (Tex. App.—Dallas
2005, pet. denied)). “[I]t is the objective intent of the parties as expressed in the text of
the mutually agreed-upon contract, and not [a party]’s subjective intent at the time of
signing, that controls the breach of contract analysis.” In re Gaudet, 625 S.W.3d 887, 894
(Tex. App.—El Paso 2021, no pet.) (orig. proceeding).
Construction of a contract is a question of law that we review de novo. Rieder v.
Woods, 603 S.W.3d 86, 94 (Tex. 2020). Our primary objective is to ascertain the parties’
true intentions as expressed in the language they chose, construing the contract in a
manner that gives effect to the parties’ intent while considering the facts and
circumstances surrounding the contract’s execution. Id. If a written instrument is so
worded that it can be given a definite or certain legal meaning, then it is not ambiguous.
Kachina Pipeline Co. v. Lillis, 471 S.W.3d 445, 450 (Tex. 2015).
“The general rule is that the laws which are in existence at the time of the making
5 of the contract are impliedly incorporated into the contract.” Progressive Cnty. Mut. Ins.
Co. v. Caltzonsing, 658 S.W.3d 384, 393 (Tex. App.—Corpus Christi–Edinburg 2022, no
pet.); Est. of Griffin v. Sumner, 604 S.W.2d 221, 230 (Tex. App.—San Antonio 1980, writ
ref’d n.r.e.). A contractual right acquired pursuant to the laws existing at the time the
contract was entered into cannot be taken away by a subsequent statute. Wessely Energy
Corp. v. Jennings, 736 S.W.2d 624, 626 (Tex. 1987) (“The laws existing at the time a
contract is made becomes a part of the contract and governs the transaction.”); see Est.
of Griffin, 604 S.W.2d at 230 (“A substantive right conferred by the existing law . . . may
not be defeated by a subsequent amendment of the law.”). Therefore, a contractual
obligation, which includes the relevant law in force at the time the contract is made, cannot
be impaired by a subsequent change in the law that applies retroactively. Cardenas v.
State, 683 S.W.2d 128, 131 (Tex. App.—San Antonio 1984, no writ). The bar against laws
impairing the obligation of contracts is enshrined in the Texas Constitution’s Bill of Rights.
TEX. CONST. art. I, § 16.
III. ANALYSIS
The permissive appeal question presented before us is: “Whether CPS Energy
breached the parties’ contract by unlawfully imposing discriminatory rates on
Spectrum[?]” See TEX. CIV. PRAC. & REM. CODE ANN. § 51.014(d); see also Northside
Indep. Sch. Dist. v. Dubose, No. 04-06-00517-CV, 2007 WL 1481661 (Tex. App.—San
Antonio May 23, 2007, no pet.) (mem. op.) (answering the question of law as posed by
the trial court under § 51.014(d)). CPS Energy poses five arguments as to why it did not
breach the contract: (1) the contract provision requiring compliance with all applicable
6 laws did not contemplate or incorporate a 2005 statute; (2) even if the contract
incorporated future laws, it did not incorporate the 2005 statute; (3) the 2005 statute only
applied to contracts entered into after September 1, 1995; (4) Spectrum’s breach of
contract action is improperly predicated on violation of a statute that provides no private
right of action; and (5) the 2005 statute’s prohibition on price discrimination was not
violated.
A. Continued or Renewed?
Embedded in CPS Energy’s arguments is a question as to the duration and term
of the contract. Accordingly, we begin by addressing the relevant provision, which states:
This [a]greement shall become effective upon the date first written above. In the event Licensee for any reason does not furnish service to all the Licensor’s service area within thirty-six (36) months from the date hereof, Licensor may terminate this [a]greement to any portion of the service area not then being served by Licensee by giving thirty (30) days written notice thereof to Licensor. If attachment rights are not terminated in accordance with the provisions of other sections of this [a]greement, this [a]greement shall remain in effect for a term of one (1) year from the effective date of this [a]greement and thereafter continue in effect from year to year, subject to the right of either party hereto to terminate this [a]greement at any time after giving to the other party at least six (6) months prior written notice thereof.
(Emphasis added). Spectrum argues that “continuing in effect from year to year” indicates
that the contract “renews” each year and thus adopts the laws in effect at the time of
renewal. CPS Energy counters that the clause means the terms of the contract as entered
into in 1984 continue in effect until it is canceled or expressly modified, and therefore the
parties are bound by the laws in effect at the time the contract was originally entered.
Neither party provided citation to any controlling authority directly discussing the
distinction between renewing and continuing or the language at issue here. Spectrum
7 provided several cases that it argues support its position, but upon closer inspection, they
do not. For example, citing National Safe Deposit Co. v. Stead, Spectrum argues the
Supreme Court decided the issue in a way that favors its position. See 232 U.S. 58, 71
(1914) (“As it now appears that all of the rentals were from year to year, and that all had
expired before final hearing, and were renewed after the passage of the law, it can also
be said that all such contracts of joint rental are made in the light of the provisions of this
particular statute.”). However, the language used in that contract is not detailed by the
Supreme Court, so we are unable to compare it with the language of the contract here.
See id. Moreover, it is not clear whether the contracts in that case expired and were
“renewed” automatically or whether the parties entered into new contract. See id.
Spectrum also cites Northshore Cycles, Inc. v. Yamaha Motor Corp., U.S.A. from
the Fifth Circuit Court of Appeals for the same proposition. See 919 F.2d 1041, 1043 (5th
Cir. 1990) (per curiam) (“[A] contract for a specified term such as one year or three years,
which provides for automatic renewal from year to year or month to month unless one
party notifies the other declining renewal, would likely not be constitutionally exempt from
the Statute’s inventory repurchase provisions if following the effective date of the Statute
the then current term of the contract had expired and been automatically renewed.”).
However, the language relied upon is dicta, and the Fifth Circuit actually held that the
parties chosen language—“shall continue until terminated as provided herein”—
exempted the application of the later-enacted statute, leading the court to dismiss the suit
for failure to state a claim upon which relief may be granted. Id. at 1042, 1044.
Spectrum next relies on Great American Indemnity Co. v. State, where the Austin
8 Court of Appeals held:
It is the general rule that a renewal of a policy constitutes a separate and distinct contract for the period of time covered by the renewal, except where the provisions of the extension certificate show that the purpose and intention of the parties was not to make a new contract but was to continue the original contract in force. And “such limitation must be found in clear and unambiguous terms within the four corners of the certificate.”
229 S.W.2d 850, 853 (Tex. App.—Austin, 1950 writ ref’d) (quoting Krey Packing Co. v.
Employers’ Liab. Assur. Corp., Ltd., of London, England, 127 S.W.2d 780, 783 (Mo. App.
1939)). But Great American actually supports CPS Energy’s position that the parties
specifically contracted for the original contract’s terms to remain in force. See id. (noting
that parties can expressly “continue the original contract in force”). Here, the clause in
question includes the phrase “continue in effect” from year to year. See id.; compare
Continue, Merriam-Webster Online Dictionary, https://www.merriam-
webster.com/dictionary/continue (last visited June 5, 2024) (defining “continue” as “to
maintain without interruption a condition, course, or action”), with Renew, Merriam-
Webster Online Dictionary, https://www.merriam-webster.com/dictionary/renew (last
visited June 5, 2024) (defining “renew” as “to become new or as new” or “to begin again”).
Lastly, Spectrum cites McDonald v. Roemer for the proposition that a year-to-year
lease where either party has the right to terminate at the end of the term is not subject to
the statute of frauds’ requirement to be in writing because it was for less than one year.
See 505 S.W.2d 698, 699 (Tex. App.—San Antonio, 1974 no writ). But, in McDonald, the
court again recognized a distinction between continuing a contract and renewing it:
“However, a distinction is made between a provision in a lease for a renewal with
permission of lessor, and a provision for the extension of the term at the option of the
9 lessee; and only the latter is treated as a demise for the full term.” Id. (citing Bailey v.
Willeke, 185 S.W.2d 456 (Tex. App.—Austin 1945), modified and aff’d, 189 S.W.2d 477,
481 (Tex. 1945)). Thus, McDonald is inapposite to the issue at hand. 4
Here, because the parties specifically agreed for the contract to “continue in effect,”
we conclude that they contracted for the original terms to remain in effect until the contract
was properly cancelled by either party, as opposed to “renewing” each year and thus
adopting the new statutes. See Rieder, 603 S.W.3d at 94. We next consider whether the
contract was written to adopt subsequently passed statutes.
B. Did the Contract Adopt § 54.204?
Generally, a contract incorporates the law as written at the time it is entered, even
if the parties do not expressly state that it does so. See Caltzonsing, 658 S.W.3d at 393;
Est. of Griffin, 604 S.W.2d at 230. Moreover, the law in effect at the time a contract is
entered should govern the fulfillment of the contract. See Jennings, 736 S.W.2d at 626.
“This doctrine is based on the presumption that the parties to a contract knew and took
into consideration the law in effect at the time of contract.” Fix v. Flagstar Bank, FSB, 242
S.W.3d 147, 155 (Tex. App.—Fort Worth 2007, pet. denied). Here, the parties expressly
adopted the applicable law as part of the contract without mention of subsequent
amendments or statutes. In contrast, in the same paragraph, the contract states that
Spectrum shall comply with the provisions of Texas Revised Civil Statutes Article 1436c
“and any amendments thereto.” Thus, not only does well-established law direct us to the
4 Spectrum also cites a series of Federal Communication Commission administrative opinions but
none of those cases involve an alleged breach of contract nor the language at hand. Accordingly, those cases are also inapposite.
10 conclusion that the contract did not adopt § 54.204, which was enacted twenty years after
the contract was entered, but so, too, does the parties’ chosen language in the contract.
See Rieder, 603 S.W.3d at 94; Jennings, 736 S.W.2d at 626.
Because Spectrum’s breach of contract claim was predicated on the contract’s
adoption of § 54.204, we answer the question of law posed by the trial court—“Whether
CPS Energy breached the parties’ agreement by unlawfully imposing discriminatory rates
on Spectrum[?]”—in the negative. We sustain CPS Energy’s first issue. 5
IV. CONCLUSION
We reverse the trial court’s judgment and remand the case for further proceedings
consistent with this opinion.
CLARISSA SILVA Justice
Delivered and filed on the 27th day of June, 2024.
5 Because CPS Energy’s first issue is dispositive, we need not reach its remaining issues. See
TEX. R. APP. P. 47.4 (directing appellate courts to write memorandum opinions “no longer than necessary to advise the parties of the court’s decision and the basic reasons for it”).