City of Royston v. Littrell Engineering Co.

75 S.E.2d 678, 87 Ga. App. 903, 1953 Ga. App. LEXIS 878
CourtCourt of Appeals of Georgia
DecidedApril 1, 1953
Docket34412
StatusPublished
Cited by4 cases

This text of 75 S.E.2d 678 (City of Royston v. Littrell Engineering Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Royston v. Littrell Engineering Co., 75 S.E.2d 678, 87 Ga. App. 903, 1953 Ga. App. LEXIS 878 (Ga. Ct. App. 1953).

Opinion

Gardner, P. J.

1. The present case is to recover a general judgment against the City of Royston for damages alleged to have been caused by the breach by the city of a contract made with Littrell Engineering Company to install a natural-gas system for said City of Royston. The trial judge overruled the general demurrer, and the case is here upon exception to that ruling.

It appears from the allegations of the petition, attached to which are the two agreements referred to, that the defendant city was desirous of having installed therein a natural-gas system and service for its citizens; and, in order to determine whether it would be practical and feasible to do so, that is, whether such system could be installed and feasibly operated to make its use by the city beneficial to the city and to those consuming the gas, the city engaged the services of Littrell to go into the matter and make the proper surveys, plans, and investigations, and furnish the city the result of his work; and, if the operation of the system appeared feasible to the mayor and council of the city, a natural-gas system would be installed therein, and the services of this engineer would be engaged to supervise and superintend such installation, the engineer to receive for his services ten percent of the money provided for the. installation of said system ($330,000), which amounted to $33,000. Littrell transferred and assigned this agreement over to the present plaintiff,' Littrell Engineering Company, and said survey and plans were made, presented to the mayor and council, and accepted on October 19, 1950, at which time the city made a contract with the plaintiff company to supervise the installation of such gas system. However, before engaging a contractor to do the installing, the city discharged the plaintiff and engaged another engineer to supervise the installation of such natural-gas system.

The plaintiff sued to recover the $33,000 which it would have made had it been permitted to complete the contract and super[906]*906vise said installation, less the expense it would have incurred of $5100. It is set out that the action of the city made it impossible for the plaintiff to complete said contract, and such failure was not its fault. The petition made a case to recover damages for breach of contract, such damages being those which naturally and directly flowed from and resulted from the defendant's wrongful failure and refusal to carry out said agreement.

Where the non-performance of a contract is caused by the act or fault of the opposite party thereto, the failure of the other party is excused. Code, § 20-1104. “Where a party bound by an executory contract repudiates his obligation before the time for performance, the other party has the option to treat the contract as ended so far as future performance is concerned, and to maintain an action at once for the damages occasioned by the breach. Crosby v. Georgia Realty Co., 138 Ga. 746 (76 S. E. 38). This is true whether the contract is wholly executory or has been partially executed.” Shell Petroleum Corp. v. Jackson, 47 Ga. App. 667, 670 (171 S. E. 171). The plaintiff alleged that it performed the contract insofar as it was able to do, the same amounting to about 80 percent of the work to be done. It made all the preliminary plans and specifications. All that was left was for the city to engage the contractor and begin the installation, and for the plaintiff to supervise the same. The plaintiff could not do more. It was discharged and another engineer hired. The two contracts, the preliminary agreement transferred by Littrell and the agreement of October 19, 1950, are to be considered together as one agreement, and are sued on as such. In a proper case the plaintiff is not limited to a quantum meruit recovery, but may rely on the contract and recover the value thereof. Parker v. King, 68 Ga. App. 672 (23 S. E. 2d, 575).

2. It appears from the petition that the engineering company is seeking to recover of the defendant municipality a general judgment for damages sustained as a result of the alleged breach by the city of a contract whereby the plaintiff was to install a natural-gas system in the City of Royston. The petition alleged that it was to receive 10 percent of the cost of installing the system, which was $330,000, and that it was damaged in the [907]*907sum of $33,000, less certain expenses which were to be paid by it for the printing of bonds, legal fees, and the like, and that it was therefore entitled to recover $27,900 of the city. No special judgment or judgment against any special fund is sought. The prayer is to recover of the city $27,900 as damages occasioned by the defendants’ breach of contract. The petition set out a cause of action showing a breach of this contract, but not to recover a general judgment against the city. The plaintiff would be entitled to recover only from the fund raised by the sale of the revenue-anticipation certificates or bonds issued by the city, pursuant to election duly held authorizing the same, and sold, as alleged. Whatever sums were realized therefrom could be subjected to any judgment or valid claim for expenses incurred, or liabilities arising out of the installation of this system of natural gas, or the contracting therefor, such as for a refusal to perform or breach on the part of the city.

The State Constitution, art. VII, sec. VII, par. I, limits the power of municipalities to create debts. Par. II thereof provides for the levy of taxes to pay bonds issued for improvements under the Constitution; par. Ill provides that upon a special election such indebtedness may be increased as therein set out. See Code (Ann.), §§ 2-6001, 2-6002, 2-6003.

“Revenue anticipation obligations may be issued by any . . municipal corporation , . to provide funds for the purchase or construction . . of any revenue producing facility . . which such . . municipal corporation . . is authorized by the Act . . approved March 31, 1937 . . as amended by the Act approved March 14, 1939, to construct and operate, or to provide funds to extend, repair or improve any such existing facility, and to buy, construct, extend, operate and maintain gas or electric generating and distribution systems.” The section provides that such certificates or bonds “shall be payable . . only from revenue produced by such revenue-producing facilities . . and shall not be deemed debts of, or to create debts against,” the municipality. The Constitution then provides that “no such political subdivision of the State shall exercise the power of taxation for the purpose of paying the principal or interest of any such revenue-anticipation obligations or any part thereof.” Constitution, art. VII, sec. VII, par. V; Code (Ann.), § 2-6005.

[908]*908The act referred to provides that a city may install and construct revenue-producing systems, plants, works, and instrumentalities, operate the same within and without the territorial limits, collect the revenue, and issue revenue-anticipation certificates to finance in whole or in part the cost of the acquisition and -construction thereof. The'city is given the power to- make all contracts necessary to carry this power into effect and have said system installed. See Code (Ann. Supp.), § 87-801 et seq.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Trimier v. Atlanta University, Inc.
234 S.E.2d 342 (Court of Appeals of Georgia, 1977)
Albright v. Benefield
213 S.E.2d 45 (Court of Appeals of Georgia, 1975)
Irwin v. Young
87 S.E.2d 322 (Court of Appeals of Georgia, 1955)

Cite This Page — Counsel Stack

Bluebook (online)
75 S.E.2d 678, 87 Ga. App. 903, 1953 Ga. App. LEXIS 878, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-royston-v-littrell-engineering-co-gactapp-1953.