City of Richmond, Kentucky v. Integrated Engineering, Pllc

Court of Appeals of Kentucky·Decided February 1, 2024·No. 2023 CA 000522·Unknown

Opinion

RENDRED: FEBRUARY 2, 2024; 10:00 A.M.

NOT TO BE PUBLISHED

Commonwealth of Kentucky

Court of Appeals

NO. 2023-CA-0522-MR

CITY OF RICHMOND, KENTUCKY APPELLANT

APPEAL FROM MADISON CIRCUIT COURT v. HONORABLE DAVID M. WARD, JUDGE ACTION NO. 19-CI-00422

INTEGRATED ENGINEERING, PLLC; HARSHA WIJESIRI; AND SMITH CONTRACTORS, INC. APPELLEES

OPINION

AFFIRMING

** ** ** ** **

BEFORE: THOMPSON, CHIEF JUDGE; KAREM AND MCNEILL, JUDGES. THOMPSON, CHIEF JUDGE: City of Richmond, Kentucky appeals from a March 28, 2023 order of the Madison Circuit Court granting summary judgment in favor of Integrated Engineering, PLLC, Harsha Wijesiri, and Smith Contractors, Inc. Appellant argues that the circuit court erred in its application of the statute of limitations in favor of Appellees. It also argues that the question of when the action accrued should have been submitted to a jury, and that the court erred in

holding that Integrated Engineering was not equitably estopped from asserting a statute of limitations defense. Appellant requests an opinion reversing the order of summary judgment. After careful review, we find no error and affirm the order on appeal.

FACTS AND PROCEDURAL HISTORY In 2009, City of Richmond engaged Integrated Engineering and one of its principals, Harsha Wijesiri, to provide engineering services to the city. Richmond and Integrated Engineering began a flood mitigation project that centered on Water Street in downtown Richmond. Integrated Engineering subsequently began oversight of the design, installation, and repair of streets, street pavers, and storm sewers to address surface and sub-surface water issues in the area.

“Phase 1” of the project began in 2013 or 2014, with the installation of permeable pavers on Water Street. Granular fill material was used between the pavers to allow surface water to drain into the ground. This phase was completed in late 2015 or early 2016.1 Soon thereafter, and no later than March 3, 3016, Richmond’s Construction Site Inspector, Daniel Winkler, documented problems with the paver

1 Though Richmond engaged Integrated Engineering in 2009, the relationship was not formalized until September 21, 2015.

installation. Specifically, Winkler noted that the pavers were buckling, separating, and moving. In addition, he noted that some of the pavers were missing. He also observed that some of the fill material between the pavers was missing. Winkler emailed Integrated and Wijesiri about the problem and included photographs, and copied the email to Richmond’s Planning and Zoning Director, Jason Hart.

The following month, representatives from all interested parties met on-site to examine the pavers. Thereafter, repairs to the pavers and fill material were undertaken. For the following three years, Richmond continued to have ongoing problems with the pavers as the base settled and the pavers and fill material continued to shift or migrate. During this period, Integrated worked with Richmond to address the problem, but was largely unsuccessful.

On May 2, 2018, a City Commissioner emailed the Mayor, City Manager, and the full Commission with a photograph of the displaced pavers, and inquired whether the construction team could be held accountable. A series of communications followed, culminating in Richmond terminating its relationship with Integrated in October 2018.

In early 2019, Richmond contacted Bell Engineering to investigate the ongoing problem with the pavers and related drainage system. Bell Engineering dug test pits where the pavers were installed, and opined in April 2019, that

Integrated’s design of the paver system and use of below-grade materials were the cause of the ongoing problems with the pavers on Water Street.

On June 11, 2019, Richmond, Integrated, and Wijesiri entered into a tolling agreement regarding the work of the contractor and Integrated Engineering’s work on the project. One month later, on July 11, 2019, Richmond terminated the tolling agreement. It then filed the instant action in Madison Circuit Court asserting claims of professional negligence, breach of contract, and breach of fiduciary duty.

Shortly thereafter, Integrated filed a motion for summary judgment, arguing that Richmond’s claims were untimely per the one-year period of limitation set out in Kentucky Revised Statutes (“KRS”) 413.245. Richmond raised various arguments in opposition to the motion, including its contention that the period of limitation should not commence until Integrated stopped representing Richmond. The Madison Circuit Court initially denied the motion, noting that the parties should engage in discovery to ascertain when the cause of action accrued and whether any tolling of the statutory period occurred.

After discovery was conducted, Integrated filed another motion for summary judgment based on the statute of limitations. The circuit court entered an order granting Integrated’s motion on March 28, 2023. In support of the order, the circuit court determined that Richmond’s cause of action accrued no later than

May 2, 2018, when multiple individuals within Richmond city government were aware of the problem and questioned whether it was possible to hold anyone accountable. The court also determined that the one-year period of limitation set out in KRS 413.245 applied; that Richmond’s engagement of Bell Engineering did not toll the running of the statute; and, that Integrated’s continuous representation did not allow Richmond to avoid the obligation to investigate and determine the cause of the harm it was experiencing. It also found that Integrated was not estopped from asserting a limitation defense. This appeal followed.

STANDARD OF REVIEW

Summary judgment “shall be rendered forthwith if the pleadings, depositions, answers to interrogatories, stipulations, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” Kentucky Rules of Civil Procedure (“CR”) 56.03. “The record must be viewed in a light most favorable to the party opposing the motion for summary judgment and all doubts are to be resolved in his favor.” Steelvest, Inc. v. Scansteel Service Center, Inc., 807 S.W.2d 476, 480 (Ky. 1991). Summary judgment should be granted only if it appears impossible that the nonmoving party will be able to produce evidence at trial warranting a judgment in his favor. Id. “Even though a trial court may believe the party opposing the motion may not

succeed at trial, it should not render a summary judgment if there is any issue of material fact.” Id. Finally, “[t]he standard of review on appeal of a summary judgment is whether the trial court correctly found that there were no genuine issues as to any material fact and that the moving party was entitled to judgment as a matter of law.” Scifres v. Kraft, 916 S.W.2d 779, 781 (Ky. App. 1996).

ARGUMENTS AND ANALYSIS

Free access — add to your briefcase to read the full text and ask questions with AI

City of Richmond, Kentucky v. Integrated Engineering, Pllc, (Ky. Ct. App. 2024).

City of Richmond, Kentucky v. Integrated Engineering, Pllc (City of Richmond, Kentucky v. Integrated Engineering, Pllc) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Harrison v. Valentini
184 S.W.3d 521 (Kentucky Supreme Court, 2006)
Gill v. Warren
751 S.W.2d 33 (Court of Appeals of Kentucky, 1988)
Steelvest, Inc. v. Scansteel Service Center, Inc.
807 S.W.2d 476 (Kentucky Supreme Court, 1991)
Stephens v. Denison
64 S.W.3d 297 (Court of Appeals of Kentucky, 2001)
Weiand v. Board of Trustees of Kentucky Retirement Systems
25 S.W.3d 88 (Kentucky Supreme Court, 2000)
Scifres v. Kraft
916 S.W.2d 779 (Court of Appeals of Kentucky, 1996)
Alagia, Day, Trautwein & Smith v. Broadbent
882 S.W.2d 121 (Kentucky Supreme Court, 1994)