City of Richmond, Kentucky v. Integrated Engineering, Pllc

CourtCourt of Appeals of Kentucky
DecidedFebruary 1, 2024
Docket2023 CA 000522
StatusUnknown

This text of City of Richmond, Kentucky v. Integrated Engineering, Pllc (City of Richmond, Kentucky v. Integrated Engineering, Pllc) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Richmond, Kentucky v. Integrated Engineering, Pllc, (Ky. Ct. App. 2024).

Opinion

RENDRED: FEBRUARY 2, 2024; 10:00 A.M. NOT TO BE PUBLISHED

Commonwealth of Kentucky Court of Appeals NO. 2023-CA-0522-MR

CITY OF RICHMOND, KENTUCKY APPELLANT

APPEAL FROM MADISON CIRCUIT COURT v. HONORABLE DAVID M. WARD, JUDGE ACTION NO. 19-CI-00422

INTEGRATED ENGINEERING, PLLC; HARSHA WIJESIRI; AND SMITH CONTRACTORS, INC. APPELLEES

OPINION AFFIRMING

** ** ** ** **

BEFORE: THOMPSON, CHIEF JUDGE; KAREM AND MCNEILL, JUDGES.

THOMPSON, CHIEF JUDGE: City of Richmond, Kentucky appeals from a

March 28, 2023 order of the Madison Circuit Court granting summary judgment in

favor of Integrated Engineering, PLLC, Harsha Wijesiri, and Smith Contractors,

Inc. Appellant argues that the circuit court erred in its application of the statute of

limitations in favor of Appellees. It also argues that the question of when the

action accrued should have been submitted to a jury, and that the court erred in holding that Integrated Engineering was not equitably estopped from asserting a

statute of limitations defense. Appellant requests an opinion reversing the order of

summary judgment. After careful review, we find no error and affirm the order on

appeal.

FACTS AND PROCEDURAL HISTORY

In 2009, City of Richmond engaged Integrated Engineering and one

of its principals, Harsha Wijesiri, to provide engineering services to the city.

Richmond and Integrated Engineering began a flood mitigation project that

centered on Water Street in downtown Richmond. Integrated Engineering

subsequently began oversight of the design, installation, and repair of streets, street

pavers, and storm sewers to address surface and sub-surface water issues in the

area.

“Phase 1” of the project began in 2013 or 2014, with the installation

of permeable pavers on Water Street. Granular fill material was used between the

pavers to allow surface water to drain into the ground. This phase was completed

in late 2015 or early 2016.1

Soon thereafter, and no later than March 3, 3016, Richmond’s

Construction Site Inspector, Daniel Winkler, documented problems with the paver

1 Though Richmond engaged Integrated Engineering in 2009, the relationship was not formalized until September 21, 2015.

-2- installation. Specifically, Winkler noted that the pavers were buckling, separating,

and moving. In addition, he noted that some of the pavers were missing. He also

observed that some of the fill material between the pavers was missing. Winkler

emailed Integrated and Wijesiri about the problem and included photographs, and

copied the email to Richmond’s Planning and Zoning Director, Jason Hart.

The following month, representatives from all interested parties met

on-site to examine the pavers. Thereafter, repairs to the pavers and fill material

were undertaken. For the following three years, Richmond continued to have

ongoing problems with the pavers as the base settled and the pavers and fill

material continued to shift or migrate. During this period, Integrated worked with

Richmond to address the problem, but was largely unsuccessful.

On May 2, 2018, a City Commissioner emailed the Mayor, City

Manager, and the full Commission with a photograph of the displaced pavers, and

inquired whether the construction team could be held accountable. A series of

communications followed, culminating in Richmond terminating its relationship

with Integrated in October 2018.

In early 2019, Richmond contacted Bell Engineering to investigate the

ongoing problem with the pavers and related drainage system. Bell Engineering

dug test pits where the pavers were installed, and opined in April 2019, that

-3- Integrated’s design of the paver system and use of below-grade materials were the

cause of the ongoing problems with the pavers on Water Street.

On June 11, 2019, Richmond, Integrated, and Wijesiri entered into a

tolling agreement regarding the work of the contractor and Integrated

Engineering’s work on the project. One month later, on July 11, 2019, Richmond

terminated the tolling agreement. It then filed the instant action in Madison Circuit

Court asserting claims of professional negligence, breach of contract, and breach of

fiduciary duty.

Shortly thereafter, Integrated filed a motion for summary judgment,

arguing that Richmond’s claims were untimely per the one-year period of

limitation set out in Kentucky Revised Statutes (“KRS”) 413.245. Richmond

raised various arguments in opposition to the motion, including its contention that

the period of limitation should not commence until Integrated stopped representing

Richmond. The Madison Circuit Court initially denied the motion, noting that the

parties should engage in discovery to ascertain when the cause of action accrued

and whether any tolling of the statutory period occurred.

After discovery was conducted, Integrated filed another motion for

summary judgment based on the statute of limitations. The circuit court entered an

order granting Integrated’s motion on March 28, 2023. In support of the order, the

circuit court determined that Richmond’s cause of action accrued no later than

-4- May 2, 2018, when multiple individuals within Richmond city government were

aware of the problem and questioned whether it was possible to hold anyone

accountable. The court also determined that the one-year period of limitation set

out in KRS 413.245 applied; that Richmond’s engagement of Bell Engineering did

not toll the running of the statute; and, that Integrated’s continuous representation

did not allow Richmond to avoid the obligation to investigate and determine the

cause of the harm it was experiencing. It also found that Integrated was not

estopped from asserting a limitation defense. This appeal followed.

STANDARD OF REVIEW

Summary judgment “shall be rendered forthwith if the pleadings,

depositions, answers to interrogatories, stipulations, and admissions on file,

together with the affidavits, if any, show that there is no genuine issue as to any

material fact and that the moving party is entitled to a judgment as a matter of

law.” Kentucky Rules of Civil Procedure (“CR”) 56.03. “The record must be

viewed in a light most favorable to the party opposing the motion for summary

judgment and all doubts are to be resolved in his favor.” Steelvest, Inc. v.

Scansteel Service Center, Inc., 807 S.W.2d 476, 480 (Ky. 1991). Summary

judgment should be granted only if it appears impossible that the nonmoving party

will be able to produce evidence at trial warranting a judgment in his favor. Id.

“Even though a trial court may believe the party opposing the motion may not

-5- succeed at trial, it should not render a summary judgment if there is any issue of

material fact.” Id. Finally, “[t]he standard of review on appeal of a summary

judgment is whether the trial court correctly found that there were no genuine

issues as to any material fact and that the moving party was entitled to judgment as

a matter of law.” Scifres v. Kraft, 916 S.W.2d 779, 781 (Ky. App. 1996).

ARGUMENTS AND ANALYSIS

Richmond argues that the Madison Circuit Court erred in granting

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Harrison v. Valentini
184 S.W.3d 521 (Kentucky Supreme Court, 2006)
Gill v. Warren
751 S.W.2d 33 (Court of Appeals of Kentucky, 1988)
Steelvest, Inc. v. Scansteel Service Center, Inc.
807 S.W.2d 476 (Kentucky Supreme Court, 1991)
Stephens v. Denison
64 S.W.3d 297 (Court of Appeals of Kentucky, 2001)
Weiand v. Board of Trustees of Kentucky Retirement Systems
25 S.W.3d 88 (Kentucky Supreme Court, 2000)
Scifres v. Kraft
916 S.W.2d 779 (Court of Appeals of Kentucky, 1996)
Alagia, Day, Trautwein & Smith v. Broadbent
882 S.W.2d 121 (Kentucky Supreme Court, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
City of Richmond, Kentucky v. Integrated Engineering, Pllc, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-richmond-kentucky-v-integrated-engineering-pllc-kyctapp-2024.