City of Reno v. Matley

378 P.2d 256, 79 Nev. 49, 1963 Nev. LEXIS 80
CourtNevada Supreme Court
DecidedFebruary 4, 1963
Docket4541
StatusPublished
Cited by6 cases

This text of 378 P.2d 256 (City of Reno v. Matley) is published on Counsel Stack Legal Research, covering Nevada Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Reno v. Matley, 378 P.2d 256, 79 Nev. 49, 1963 Nev. LEXIS 80 (Neb. 1963).

Opinion

*50 OPINION

By the Court,

Badt, C. J.:

Some thirteen members of the Matley family and CWF Corporation, Shoshone Coca Cola Bottling Co., and Joseph J. Morrey, as successors in interest to three respective parcels of property conveyed to them by the Matleys and abutting the easement in issue herein, sought declaratory relief and an injunction to restrain the City of Reno from constructing a road upon the easement granted to the City other than as required by an agreement entered into between the Matleys and the City. The court granted the relief asked for, and the City has appealed. Appellant’s opening brief assigns the following errors:

1. That the court erred in holding that the City’s covenant to construct and maintain a street on the easement granted by the Matleys was a covenant running with the land.

2. That, such being the case, it was error to hold that the successors in interest of the Matleys are real parties in interest.

3. Error in holding “that the covenant of the appellant to construct and maintain a street section eighty feet wide along the easements described in said agreement of April 24, 1956, means the construction and maintaining of a street surface 80 feet in width.”

4. Error in holding “that it is the duty of the appellant under the provisions of said agreement of April 24, 1956 to remove or eliminate any barrier or hazard which would prevent the use of any portion of said eighty foot easement as a street.”

*51 5. Error in holding “that the roadbed heretofore constructed by the appellant does not discharge appellant’s obligation to construct and maintain a street section 80 feet wide.”

6. Error in holding “that appellant is required to eliminate the barrier created by the drainage ditches located on the eighty foot easement and to construct a level street surface to the property line on each side of the street easement.”

7. Error in holding “that the appellant had not as of the date of the submission of the action to the trial court surfaced any portion of said street section eighty feet in width, and that the trial court could not determine whether the portion of said street section 80 feet in width which the defendant is required to surface is of sufficient width to accommodate the traffic using said street.”

8. That it was error to grant a summary judgment where there were genuine issues of fact to be tried.

9. That it was error for the court to issue a mandatory injunction.

A pretrial conference was held and an order made pursuant to stipulation, which we have condensed as follows:

On April 24, 1956, the Matleys entered into a written contract with the City whereunder they agreed to convey to the City some 212 acres of land and “an easement for the purpose of constructing a street 80 feet in width extending to Vassar Street from Matley Lane to the terminal area of the Reno Municipal Airport, containing 1.58 acres, subject to the conditions of paragraph 2(h) of the agreement; also an easement for the purpose of constructing an access street 80 feet in width from the terminal area of the Reno Municipal Airport to Mill Street,” containing 4.176 acres; also “an easement for the purpose of constructing an access street 60 feet in width from Matley Lane” to the lands described, containing 1.256 acres; also “a permanent underground easement for the purpose of constructing and maintaining a sewer line or lines” as described.

In consideration of the premises the City agreed to pay the Matleys something over $400,000, constituting *52 severance damages to the remaining adjacent lands of the Matleys, to construct certain fences along the easements granted, to construct and maintain a street section 100 feet wide as described (the “Plumb Lane Extension”), and further, of primary contention in this case (we borrow the phrase from appellant’s brief) : “to construct and maintain at its own cost and expense a street section 80 feet wide, surfaced to sufficient width in accordance with good engineering practice to accommodate traffic using said street, on the easement hereinabove described in Paragraph 1 (c) hereof * * with an identical covenant with reference to the easement described in paragraph 1(d) of the agreement.

The City further agreed that if it failed to construct the streets thus referred to or ceased thereafter to maintain the easements for public purposes, the easements would terminate and the land revert to the Matleys and their successors in interest. The City further agreed to construct and maintain a sewer line on the underground easement granted, with certain provisions for pumping if required. Sundry other covenants were agreed upon, which, however, are not pertinent to the issues herein.

Subsequently to the execution of said agreement in 1956, plaintiffs CWF Corporation, Shoshone Coca Cola Bottling Co., and (through mesne conveyance) plaintiff Morrey acquired by purchase from the Matleys their respective parcels of land fronting on the conveyance to the City. The city engineer of Reno submitted plans and specifications for the construction of the streets, which were approved by the City, and thereafter the City entered into a contract for the construction of said streets with Isbell Construction Company, which entered upon such construction, graded the streets according to the plans and specifications, built up and compacted a roadbed for streets 40 feet in width, hauled in, dumped and leveled gravel on top of said roadbed, and has, for the purpose of draining aforesaid roadbed and in accordance with the plans and specifications, dug on each side of the roadbed on both streets a drainage ditch which has been graded and at all points dug to a depth sufficient to drain percolating and other waters away from *53 said roadbed. The high level of percolating and other waters make drainage of the roadbed necessary and to do so efficiently the City planned and the construction company dug the ditch along and within the limits of the 80-foot right of way. There is on each side of the roadbed a 20-foot strip from the edge of the road to the line of the right of way, the ditch being next to the right of way line with its center side sloping toward the shoulder and edge of the roadbed. The topography of plaintiff’s abutting lands is uneven, though generally sloping from east to west on the north portion and from west to east on the south portion; the drainage ditch is in some instances a barrier and at almost every other point a hazard to access of the abutting lands of the plaintiffs. (At the oral argument it was conceded that in some places the ditch was six feet deep.) At almost every point along the drainage ditches ordinary access to the plaintiffs’ abutting lands would require that a conduit, capable of receiving as well as carrying waters, be laid and the ditch filled. This problem will be aggravated when the road is hard-surfaced, since that will at certain points raise the level of the road as much as a foot in some areas. In some parts thereof the drainage ditch carries percolating and surface waters only.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shoen v. Maddi's Fresian Ranch, LLC
Nevada Supreme Court, 2018
ECM, Inc. v. Placer Dome U.S., Inc.
24 F. App'x 821 (Ninth Circuit, 2001)
Leonard v. Stoebling
728 P.2d 1358 (Nevada Supreme Court, 1986)
Moseley v. Bishop
470 N.E.2d 773 (Indiana Court of Appeals, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
378 P.2d 256, 79 Nev. 49, 1963 Nev. LEXIS 80, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-reno-v-matley-nev-1963.