This text of City of Reno v. Bd. of Admin. (City of Reno v. Bd. of Admin.) is published on Counsel Stack Legal Research, covering Nevada Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Reno v. Bd. of Admin., (Neb. 2014).

Opinion

controlling statutory language and relevant caselaw, we conclude that the Board abused its discretion in determining the timeliness of Reno's notice when the Board failed to apply the correct legal standard that governs the inquiry for what is the date of injury for an occupational disease under a statute that concerns a disability by injury. See NRS 233B.135(3) (providing that a reviewing court determines whether an agency decision violated statutory provisions or was arbitrary or capricious); Vredenburg ex rel. Vredenburg v. Sedgwick CMS, 124 Nev. 553, 557, 188 P.3d 1084, 1087 (2008) (stating that an agency's conclusions of law that are closely related to its view of the facts will not be set aside if supported by substantial evidence); In re Halverson, 123 Nev. 493, 510, 169 P.3d 1161, 1173 (2007) (stating that it is an abuse of discretion to apply the wrong legal standard); Washoe Med. Ctr. v. Second Judicial Dist. Court, 122 Nev. 1298, 1302, 148 P.3d 790, 792 (2006) (indicating that de novo review applies to statutory interpretation issues); United Exposition Serv. Co. v. State Indus. Ins. Sys., 109 Nev. 421, 423, 851 P.2d 423, 424 (1993) (stating that "Mills court's role in reviewing an administrative decision is identical to that of the district court"). At the relevant time, NRS 616B.557(1) permitted a self- insured employer to make an SIA claim when its employee has a permanent physical impairment from any cause or origin and incurs a subsequent disability by injury arising out of and in the course of his employment which entitles him to compensation for disability that is substantially greater by reason of the combined effects of the preexisting impairment and the subsequent injury than that which would have resulted from the subsequent injury alone. . . .

SUPREME COURT OF NEVADA 2 (0) 1947A csetto NRS 616B.557(1) (2005) (emphases added). The employer's ability to recover on an SIA claim was conditioned on the employer effectuating a notice "of any possible [SIA] claim . . . as soon as practicable, but not later than 100 weeks after the injury." NRS 616B.557(5) (2005) (emphasis added). The plain meaning of the 100-week language set forth the ultimate time limitation for the notice. See Cromer v. Wilson, 126 Nev. 106, 109, 225 P.3d 788, 790 (2010) (providing that unambiguous statutes are interpreted based on their plain meaning); see also Idaho Watersheds Project v. Hahn, 187 F.3d 1035, 1036-37 (9th Cir. 1999) (treating the time limitation that follows an "as-soon-as-practicable-but-not-later-than phrase" as the decisive time limitation); Arel v. T & L Enters., Inc., 189 P.3d 1149, 1152-53 (Idaho 2008) (same); Luckenbill v. Indus. Comm'n, 507 N.E.2d 1185, 1190 (Ill. App. Ct. 1987) (same). Here, the Board determined that the degenerative joint disease of Reno's employee was the subsequent occupational injury upon which NRS 616B.557(1) conditions an SIA claim. Accordingly, the Board endeavored to establish the disease's injury date in order to resolve whether Reno accomplished its notice within "100 weeks after the injury." NRS 616B.557(5) (2005) (emphasis added). But in so doing, the Board erroneously focused on "the date of [the disease's] onset" for the injury date and, as a result, concluded that July 1, 2002, was the date of injury because the disease "was manifest" and "evident" by that time. The district court's focus on the onset and discovery of the disease was misplaced in this matter that concerns the injury date for an occupational disease as it relates to a statute that concerned a "subsequent disability by injury." NRS 616B.557(1) (2005). Under similar circumstances, the court in Mirage Casino-Hotel v. Nevada Department of

SUPREME COURT OF NEVADA 3 (0) 1947A e Administration ascertained the injury date for an occupational disease with respect to a statute and regulation that concerned the injury date for disability benefits. 110 Nev. 257, 259-60, 871 P.2d 317, 318-19 (1994). The Mirage court recognized that disablement for the purposes of an occupational disease is statutorily defined as 'the event of becoming physically incapacitated by reason of an occupational disease arising out of and in the course of employment. . . ." Id. at 260, 871 P.2d at 319 (quoting NRS 617.060). It held that the injury date for calculating disability benefits for an occupational disease was not when an employee merely "suffered" from the disease, but it was when an employee was "no longer able to work" because the disease disabled the employee. Id. Accordingly, it concluded that the injury date for an occupational disease was when the disease caused the employee to be "disabled; i.e., unable to continue working." Id. Similar to Mirage, this matter concerns a statute that affords relief based on a disability by an occupational injury. See NRS 616B.557(1) (2005). When the Board applied NRS 616B.557 to the degenerative joint disease, it erroneously focused on the onset of the disease and when it became manifest or evident. Pursuant to Mirage, the Board needed to focus on when the disease caused the employee to be "disabled; i.e., unable to continue working." Mirage, 110 Nev. at 260, 871 P.2d at 319. As to Reno's contention that a new injury date was generated when its employee continued his employment and continuously aggravated his knee condition as a result, its argument is insufficiently developed. Reno premises this contention on the fact that• the Board considered this theory to be viable and on the assertion that NRS

SUPREME COURT OF NEVADA 4 (0) 1947A 616B.557(5) must be construed in its favor because it is ambiguous. We, however, do not find the statute to be ambiguous. And because Reno fails to offer this court pertinent legal authority or analysis to support its theory that continuous employment generated a new injury date under NRS 616B.557

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Luckenbill v. Industrial Commission
507 N.E.2d 1185 (Appellate Court of Illinois, 1987)
Cromer v. Wilson
225 P.3d 788 (Nevada Supreme Court, 2010)
Vredenburg Ex Rel. Vredenburg v. Sedgwick CMS
188 P.3d 1084 (Nevada Supreme Court, 2008)
Edwards v. Emperor's Garden Restaurant
130 P.3d 1280 (Nevada Supreme Court, 2006)
Arel v. T & L ENTERPRISES, INC.
189 P.3d 1149 (Idaho Supreme Court, 2008)
Idaho Watersheds Project v. Hahn
187 F.3d 1035 (Ninth Circuit, 1999)
In re Halverson
169 P.3d 1161 (Nevada Supreme Court, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
City of Reno v. Bd. of Admin., Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-reno-v-bd-of-admin-nev-2014.