City of Raton v. Vermejo Conservancy District

678 P.2d 1170, 101 N.M. 95
CourtNew Mexico Supreme Court
DecidedMarch 29, 1984
Docket14773
StatusPublished
Cited by27 cases

This text of 678 P.2d 1170 (City of Raton v. Vermejo Conservancy District) is published on Counsel Stack Legal Research, covering New Mexico Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Raton v. Vermejo Conservancy District, 678 P.2d 1170, 101 N.M. 95 (N.M. 1984).

Opinion

OPINION

WALTERS, Justice.

In 1935 the Colfax County District Court issued a decree adjudicating water rights in the Chico Rico, or Sugarite, stream system of Northern Colfax County. In 1980 the City of Raton (Raton) filed a declaratory judgment action against Vermejo Conservancy District (District) seeking a determination of the rights of those parties under the 1935 decree. The District counterclaimed, basing its claims on Raton’s alleged improper withholding of water in excess of its senior rights. Trial was held in two parts—on August 20, 1981, the court decided Raton’s claimed equitable defenses to the District’s call for release of water (Phase I), and on July 20, 1982, it determined the damages and injunction issues raised by the District’s counterclaim (Phase II). The trial court, in its final declaratory judgment entered December 9, 1982, ordered Raton to release water to the District upon demand in accordance with the senior rights of the District established in the 1935 decree, so long as the water could be put to beneficial use by the District. The trial court, as the measure of damage, also ordered Raton to make a one-time release to the District of 1,211 acre-feet of water wrongfully withheld in 1980.

Raton appealed the decision, asserting three contentions: (1) that the District lost its water rights when its method of storage was altered; (2) that the doctrine of laches precludes an assertion by the District of its senior rights and raises the issue of abandonment; and (3) that the trial court improperly interpreted the 1935 decree in determining the quantity of water available to Raton.

We summarize the uncontested facts found by the trial court: The final decree of water rights on the Chico Rico was entered on September 25, 1935. Among the parties to the adjudication were Raton and the District’s predecessor in interest, Maxwell Ditch and Reservoir Company (Maxwell). The district court found, among other things, that Maxwell had the right to divert and store up to 15,638 acre-feet of water per year at Hebron Reservoir, with a priority date of August 17, 1911. Under the court’s findings, Raton also had certain water rights with a priority date of January 1, 1891, and other water rights with a priority date of August 22, 1912.

Hebron Dam broke in 1942. As originally constructed, it had a reservoir capacity of 7800 acre-feet; when it broke, its storage capacity was reduced to 3,073 acre-feet because of siltation. Hebron Dam has not been rebuilt.

Following the break of Hebron Dam, the United States Bureau of Reclamation undertook an engineering study of the area. The Vermejo Project was ultimately authorized as a federal reclamation project and two million dollars were expended in rehabilitation of the irrigation dams, reservoirs and ditch system formerly operated by Maxwell. Part of the rehabilitation included the Eagle Tail Ditch by which water is carried from the Hebron Dam site to irrigated lands some 15V2 miles away, and the Eagle Tail Diversion canal was moved from its prior location at Hebron Dam to the north end of Hebron Reservoir. No significant amount of water has been stored in Hebron Reservoir since 1942.

The Vermejo Conservancy District, successor in interest to Maxwell, was organized in 1952 under the laws of the State of New Mexico. The District maintains and operates the Vermejo Project pursuant to a Í952 repayment contract with the Bureau of Reclamation. The Vermejo Project encompasses 7,380 acres of land which are irrigated in part by waters of the Chico Rico stream system.

Although, since 1938, neither the District nor its predecessor Maxwell had received all the water of the Chico Rico at the Hebron diversion to which they were entitled, at no time prior to 1980 had either made a priority call on Raton. On May 28, 1980, the District made such a priority call, demanding that all waters stored in Ra-ton’s reservoirs in excess of Raton’s storage rights under the 1935 decree be released from storage and allowed to flow downstream. It was this 1980 call that prompted Raton to file the declaratory judgment action.

1. District’s compliance with statutes

The trial court found that “[ejxcept for storage” the District’s method of collection, diversion, and distribution of the waters of the Chico Rico is “essentially unchanged” from the method used by Maxwell prior to the destruction of Hebron Dam in 1942. Raton argues here, citing NMSA 1978, § 72-5-24, that because there was a change in the method of storage following the rehabilitation undertaken by the Bureau of Reclamation, the District was required to apply to the State Engineer for approval of that change. Section 72-5-24 is a restriction of the rights of an appropriator to change the method of water storage. See Public Service Co. v. Reynolds, 68 N.M. 54, 358 P.2d 621 (1960). We agree with Raton that normally the District would have had to obtain the State Engineer’s approval for the change in storage. However, the trial court concluded that, under NMSA 1978, § 72-9-4, neither Maxwell nor the United States Bureau of Reclamation was required to obtain the State Engineer’s approval in order to implement the plan for rehabilitation for the Vermejo Project. Section 72-9-4 provides as follows:

Raton does not dispute that the Vermejo Project was a federal reclamation project pursuant to the Federal Reclamation Act. Raton argues that Section 72-9-4 does not provide an exemption from the requirements of Section 72-5-24.

Section 72-9-4 was enacted in 1941 N.M.Laws, ch. 126, § 27. Section 72-5-24 was enacted as Section 18 of that chapter. Chapter 126 was prefaced, “An act to conserve and regulate the use and distribution of the waters of New Mexico * * *.” All of Chapter 126 is clearly “the act” referred to in Section 72-9-4. Thus, the requirements of Section 72-5-24, enacted as Section 18 of that “act,” do not apply to federal reclamation projects. Even so, the evidence shows that the District applied to the State Engineer in 1978 for approval of the changes made by the Bureau of Reclamation in the District’s storage system, and the State Engineer’s office replied that the application was unnecessary in view of Section 72-9-4. Although not binding, the statutory interpretations of the body charged with administration of the statute are persuasive. Valley Country Club v. Mender, 64 N.M. 59, 323 P.2d 1099 (1958). The State Engineer’s interpretation here coincides with ours. The Vermejo Project was authorized as a federal reclamation project; consequently, the District was exempted from the requirements of Section 72-5-24 by the very terms of Section 72-9-4 with respect to changes in the system effected by the Bureau of Reclamation.

In its Reply Brief, Raton cites N.M. Const, art.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lujan v. Acequia Mesa Del Medio
436 P.3d 734 (New Mexico Court of Appeals, 2018)
State v. Martinez
2015 NMCA 051 (New Mexico Court of Appeals, 2015)
Peña Blanca Partnership v. San Jose De Hernandez Community Ditch
202 P.3d 814 (New Mexico Court of Appeals, 2008)
Collado v. City of Albuquerque
2002 NMCA 048 (New Mexico Court of Appeals, 2002)
Las Cruces Professional Fire Fighters v. City of Las Cruces
1997 NMCA 031 (New Mexico Court of Appeals, 1997)
Kirkpatrick v. Introspect Healthcare Corp.
845 P.2d 800 (New Mexico Supreme Court, 1992)
Regents of the University v. Hughes
838 P.2d 458 (New Mexico Supreme Court, 1992)
REGENTS OF UNIVERSITY OF NM v. Hughes
838 P.2d 458 (New Mexico Supreme Court, 1992)
J.R. Simplot Company, Inc. v. Idaho State Tax Commission
820 P.2d 1206 (Idaho Supreme Court, 1991)
Arch, Ltd. v. Yu
766 P.2d 911 (New Mexico Supreme Court, 1988)
Castillo v. Weatherly
753 P.2d 1323 (New Mexico Court of Appeals, 1988)
Padilla v. City of Santa Fe
753 P.2d 353 (New Mexico Court of Appeals, 1988)
Maestas v. Martinez
752 P.2d 1107 (New Mexico Court of Appeals, 1988)
Levenson v. Mobley
744 P.2d 174 (New Mexico Supreme Court, 1987)
New Mexico Pharmaceutical Ass'n v. State
738 P.2d 1318 (New Mexico Supreme Court, 1987)
New Mexico Hospital Ass'n v. A.T. & S.F. Memorial Hospitals, Inc.
734 P.2d 748 (New Mexico Supreme Court, 1987)
NM Hosp. Ass'n v. AT & SF MEM. HOSP.
734 P.2d 748 (New Mexico Supreme Court, 1987)
Patterson v. Environmental Improvement Division
731 P.2d 1364 (New Mexico Court of Appeals, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
678 P.2d 1170, 101 N.M. 95, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-raton-v-vermejo-conservancy-district-nm-1984.