City of Philadelphia v. Pennsylvania Public Utility Commission

822 A.2d 94, 2003 Pa. Commw. LEXIS 176
CourtCommonwealth Court of Pennsylvania
DecidedMarch 31, 2003
StatusPublished

This text of 822 A.2d 94 (City of Philadelphia v. Pennsylvania Public Utility Commission) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Philadelphia v. Pennsylvania Public Utility Commission, 822 A.2d 94, 2003 Pa. Commw. LEXIS 176 (Pa. Ct. App. 2003).

Opinion

OPINION BY

JUDGE PELLEGRINI.

The City of Philadelphia (City) and Philadelphia Gas Works (PGW) appeal from an order of the Pennsylvania Public Utility Commission (Commission) adopting the recommended decision of the administra[97]*97tive law judge (ALJ) allocating each of them 100% of their relocation costs relative to the reconstruction of the Holme Avenue Bridge. Similarly, PECO Energy Company (PECO) appeals from that same order allocating it 100% of its relocation costs relative to the reconstruction of the Holme Avenue Bridge.

This case involves the deterioration and proposed reconstruction of the Holme Avenue Bridge (Bridge) where Holme Avenue crosses above the railroad tracks of Consolidated Rail Corporation (Conrail). The Bridge, which was constructed sometime between 1919 and 1921 and became a state bridge in 1961, is located in a residential neighborhood in the Pennypack section of the City.

On December 14, 2000, the Commonwealth of Pennsylvania, Department of Transportation (PennDot) filed an application with the Commission requesting, inter alia, approval to remove and replace the Bridge (Bridge Replacement Project) and for the Commission to allocate costs associated with the Bridge Replacement Project. In determining cost allocations, PennDot wanted the Commission to consider that the City owned a water main, sanitary sewer and storm sewer located near the Bridge, and PGW owned a gas main located on the Bridge, all which needed to be relocated and possibly changed, altered or adjusted. Also, PECO had two 45-foot terminal poles located on Holme Avenue which needed to be relocated in order to accommodate the Bridge Replacement Project.

At the hearing before the ALJ, William Messenger (Messenger), a structural engineer, initially testified on behalf of Penn-Dot regarding the deteriorated condition of the Bridge and opined that rehabilitation or reconstruction of the Bridge was not viable. Regarding the construction of the new Bridge, Messenger estimated the total cost of the Bridge Replacement Project to be approximately $2.3 million, which included an estimated construction cost for the Bridge alone of $1.7 million and $300,000 as a contingency item. Messenger testified that due to the placement of a new abutment that would be situated right on top of the existing sanitary and storm sewers, the sewers would have to be relocated, and the costs of relocating the sewers was not included in the $1.7 million estimate. He stated that he did not know what those costs would be.

Leonard Nardone (Nardone) also testified on behalf of PennDot stating that he worked for PennDot as the railroad coordinator for the district. He testified that the Bridge Replacement Project would utilize 80% federal and 20% state Bridge bill funds with a separate 10% contribution from Conrail for “project costs” pursuant to an agreement between PennDot and Conrail.1 He also testified that PennDot would bear 100% of the storm water relocation costs because it provided drainage for the highway, but it would not cover any costs for the relocation of the sanitary and storm sewers because they were in a public right-of-way; therefore, the utilities had to move the sewers at their own costs. Nardone further stated that upon completion of the Bridge, PennDot would be the owner of the Bridge and would maintain, at its sole cost and expense, the Bridge superstructure and substructure and the [98]*98roadway between curbs on the Bridge and its approaches, and the structural integrity of the curbs and sidewalks following construction. He concluded by stating that PennDot did not agree to bear any costs of any non-carrier public utility other than the costs of relocating the City’s storm water facility.

Mark Waas (Waas), an engineering supervisor for the design branch of the Water Department of the City, testified that the City’s Water Department had three facilities at the existing crossing: a 12" cast iron water main located on the Bridge superstructure installed in 1996; a 10" vitrified clay sanitary sewer below the grade of the Bridge superstructure and crossing beneath the existing railroad tracks installed in 1955; and an 18" concrete storm sewer below the grade of the Bridge superstructure and crossing beneath the existing railroad tracks installed in 1955. Waas testified that all three facilities had an unlimited useful life with continued proper maintenance. However, in order to accommodate the Bridge Replacement Project, the City’s water main on the Bridge superstructure might have to be reconstructed because the City had inspected the storm water main and discovered that the storm water line west of the Bridge was crushed in places and inoperable. He estimated the total cost of reconstructing the water main to be $101,250, but noted that the Bridge was the most convenient location in the general vicinity for the location of the water main. Waas stated that there had been no cost sharing on the Bridge Replacement Project and it was PennDot’s responsibility as owner of the Bridge to bear the costs of relocation or reconstruction of the sewers. It was also Waas’ opinion that the 12" water main was located in a public right-of-way while the 10" sanitary and 18" storm sewers were located in private right-of-ways.

Michael Jones (Jones), the manager for distribution planning, testified on behalf of PGW. He explained that PGW had a 12-inch steel intermediate pressure main on the Bridge, which had been installed in 1956 and had an indefinite service life but required constant inspection, and that PGW needed the main to remain in service at all times so that it could serve its customers downstream. He stated that PGW had not submitted any requests of cost sharing, and it was PGWs position that it was not going to pay for relocation or replacement costs2 because it would be difficult and costly to relocate to any other location off the Bridge. Jones testified that PGW wanted PennDot to pay 100% of any relocation costs, but that PGW would agree to maintain its gas facility as redesigned and relocated if PennDot and PGW reached a consensus on the final design and relocation of the gas facility.

Finally, Serena Wilson (Wilson), a project engineer for PECO, testified that PECO had two 45-foot terminal poles located on Holme Avenue that had to be relocated in order to accommodate the Bridge Replacement Project at a total estimated cost to PECO of $80,344. She stated that PECO agreed to bear the initial cost of relocating its poles, but sought to be reimbursed 100% by PennDot, and that PECO also agreed to solely bear the cost of maintaining its facilities after the Bridge Replacement Project was completed.

After the hearing, the ALJ recommended that the Commission approve PennDot’s request to replace the Bridge because none of the parties disagreed with Messenger’s assessment that the Bridge [99]*99needed to be replaced. Regarding the cost allocations, the ALJ considered the benefit the utilities and their ratepayers received from the location of their facilities, whether any party was responsible for the deterioration of the Bridge, the availability of state and/or federal funding, the equities involved, and consistency with recent Commission decisions. The ALJ recommended that the Commission approve the allocation between PennDot and Conrail because it was just and reasonable.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

PECO Energy Co. v. Pennsylvania Public Utility Commission
791 A.2d 1155 (Supreme Court of Pennsylvania, 2002)
Greene Township Board of Supervisors v. Pennsylvania Public Utility Commission
668 A.2d 615 (Commonwealth Court of Pennsylvania, 1995)
Bell Atlantic-Pennsylvania, Inc. v. Pennsylvania Public Utility Commission
672 A.2d 352 (Commonwealth Court of Pennsylvania, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
822 A.2d 94, 2003 Pa. Commw. LEXIS 176, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-philadelphia-v-pennsylvania-public-utility-commission-pacommwct-2003.