City of Panama City v. T & A Utilities Contractors

606 So. 2d 744, 1992 Fla. App. LEXIS 11154, 1992 WL 301318
CourtDistrict Court of Appeal of Florida
DecidedOctober 22, 1992
DocketNo. 91-3149
StatusPublished
Cited by2 cases

This text of 606 So. 2d 744 (City of Panama City v. T & A Utilities Contractors) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Panama City v. T & A Utilities Contractors, 606 So. 2d 744, 1992 Fla. App. LEXIS 11154, 1992 WL 301318 (Fla. Ct. App. 1992).

Opinion

WEBSTER, Judge.

The City of Panama City (the City) appeals a final judgment entered in favor of T & A Utilities Contractors (Contractors) in a breach of contract action brought by Contractors. The City raises two issues: (1) whether the trial court committed reversible error when it granted Contractors’ motion for a directed verdict on the issue of liability, made at the close of the evidence; and (2) whether the trial court committed reversible error when it denied the City’s motion in limine to exclude the testimony of Contractors’ expert witness on damages, and when it denied the City’s motion for a directed verdict on the issue of damages. Contractors has taken a cross appeal in which it asserts that the trial court committed reversible error when it permitted a witness to offer his opinion, over objection, .regarding the reasonable cost to complete the work called for by the contract. Because we conclude that the trial court committed reversible error when it granted Contractors’ motion for a directed verdict on the issue of liability, we reverse.

The City and Contractors entered into a contract pursuant to which Contractors agreed to install new water mains in a specified part of the City, in return for the payment of $420,338.00. Shortly after the contract had been executed and Contractors had begun work on the project, a dispute arose regarding whether pipe being used met contract specifications. The City’s Director of Engineering Services demanded that Contractors provide “documentation from the manufacturer” that the pipe met contract specifications. When Contractors failed to produce what the City’s Director of Engineering Services and Manager considered satisfactory proof that the pipe being used met contract specifications within what they felt to be a reasonable time, the City’s Manager wrote Contractors a letter, in which he said, “The City has decided to terminate the contract due to the contractor’s failure to provide sufficient evidence of material suitability and disregard for the authority of the owner and the engineer.”

Approximately three weeks after the City’s Manager had sent the letter to Contractors, during a regular meeting of the City Commission, the Manager explained to the Commission what had happened and requested the Commission to award a contract to the company which had made the lowest bid for completion of the water main project. The Mayor asked the City Attorney whether “he had any problems with the cancellation of the contract and the procedure.” When the City Attorney responded that he did not, the City Commission voted unanimously to award the contract for completion of the project to the low bidder.

Contractors subsequently commenced this action. Its second amended complaint (the complaint) alleges that the contract had been entered into, and that the City had breached the contract (without explicitly identifying the nature of the alleged breach). However, the complaint also alleges that the City, relying on certain provisions of the contract, had terminated the contract; and that Contractors had “completely performed its work under the contract documents in a good workmanlike manner, furnishing all labor, materials and equipment in total compliance with contract documents.” Therefore, the only reasonable interpretation of the allegations made is that the City’s purported termination had been unjustified and, accordingly, was actually a breach.

The City filed an answer denying that it had breached the contract, and asserting as an affirmative defense that “[t]he contract with [Contractors] was terminated as a result of [Contractors’] failure to proceed ac[746]*746cording to the terms of the contract and specifications." Contractors then filed a reply, denying the affirmative defense. The case proceeded to trial on the issues thus framed.

As the foregoing discussion demonstrates, the issues framed by the pleadings were whether the City was justified in terminating the contract because Contractors had failed to comply with the terms of the contract; or whether Contractors had complied with the terms of the contract, so that the City’s purported termination actually constituted a breach. However, at the close of its case, Contractors moved for a directed verdict on the issue of liability on the grounds that, as a matter of law, the City’s Manager lacked the authority to terminate the contract; and that, as a matter of law, the City Commission had not ratified the purported termination of the contract by the Manager. Although such an issue had not been raised in the pleadings, the motion was effective in shifting the focus of the trial to that issue, and away from whether the City had been justified in terminating the contract. In reserving ruling on the motion, the trial court said:

I am not inclined to grant the directed verdict on liability at the close of the Plaintiffs [sic ] case because the Defendant has not had a chance to present evidence to respond or show justification for their [sic] actions. Right now the Plaintiff has just presented evidence^] and I am not sure if there’s any additional evidence the Defense can present on the issue of ratification. And if there is no other evidence to be presented on the issue of ratification[,] I agree with the Plaintiff’s argument that the City Manager did not have the authority to send the letter of January 5th to the Plaintiff terminating the contract without either prior approval from the City as the owner or some action of ratifying the City Commissioners [sic] authority to terminate the contract, so I will reserve ruling on the issue until close [of] the Defendant’s case and allow the Plaintiff to move for a directed verdict at that time based upon whatever evidence, any additional evidence to be presented by the Defendant in its case in chief.

At the close of all the evidence, Contractors renewed its motion for a directed verdict on the issue of liability. The City responded that, assuming that the Manager lacked the authority actually to terminate the contract without the approval of the City Commission, it was clear that, by accepting the Manager’s recommendation to award a contract to complete the project which had been the subject of the contract with Contractors, the City Commission had intended to ratify the Manager's decision to terminate the contract with Contractors. Despite the City’s argument, the trial court granted Contractors’ motion for a directed verdict on the issue of liability, saying:

The owner, the City, chose to terminate the contract, but ... the City did it through the City Manager[,] and the City Manager did it without any authority of the board and there’s nothing in the code that gives the City Manager the authority to, on its [sic ] own, terminate ... contracts_ [T]he City Manager powers under the code do not include the power to cancel contracts.... He did it on his own under the belief that he’s acting as an agent of the owner, the City. He had no power to do that under the City code. So, the question really is, did the City, the owner, really terminate the contract and, and properly.... [0]n that issue[,] they’re entitled to a directed verdict.... [T]he City did not ratify the actions of the City Manager ... in ... the same way[ ] that- it was required to form the contract.... [H]ere there’s no proof that the City Manager had the authority to sign the letter terminating the contract[] [a]nd[,] therefore, cancel the contract automatically^] and there’s no proof that the City ratified his conduct by resolution or act in a formal process_

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Topeka v. Imming
344 P.3d 957 (Court of Appeals of Kansas, 2015)
Frankenmuth Mut. Ins. Co. v. Magaha
769 So. 2d 1012 (Supreme Court of Florida, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
606 So. 2d 744, 1992 Fla. App. LEXIS 11154, 1992 WL 301318, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-panama-city-v-t-a-utilities-contractors-fladistctapp-1992.