City of Owensboro v. Nolan

46 S.W.2d 490, 242 Ky. 342, 1932 Ky. LEXIS 274
Court of Appeals of Kentucky (pre-1976)·Decided February 9, 1932·Published·Cited by 6 cases

Opinion

Opinion of the Court by

Creal, Commissioner—

Affirming.

In 1929, Owensboro, a city of tbe third class operating under the commission form of government, by and through its board of commissioners, contracted with Thomas Nolan to construct a system of sewers. Neither the validity of the contract nor any of the preliminary steps leading up to it is called in question. The sewer system which Nolan contracted to construct for the city has been fully completed, and by this action, instituted, in the Daviess circuit court, he is seeking to recover and enforce payment of the balance due under the contract. We find that the parties are in agreement as to the amount of the balance due. The real controversy is whether Nolan is pursuing the proper remedy, and whether he is entitled to the relief sought, and which has been granted him by judgment of the lower court.

Under the contract it was provided that monthly estimates should be issued as the work progressed, and that 85 j>er cent of each estimate should be paid within 10 days after the approval of same by the board of commissioners. The remaining 15 per cent of the estimate retained by the city was to be paid 60 days after the final completion and acceptance of the work. The contract also contained the following provisions:

1. “After full completion of the work to the satisfaction of the Board of Commissioners, it reserves the right to refuse the payment of 15 per cent reserved, or any amount due said contractors until it is satisfied that all subcontractors, workmen and employees of said contractor have been fully paid.”'
2. “No voucher in final payment will be issued until the contractor delivers to the Board of Commissioners a statement in writing, setting out fully the amount, kind and quality of the several materials used and incorporated into the work herein required *344 to be done; said statement to be sworn to by the contractor before a notary public or other officer authorized to administer oaths. It is further alleged that the Board of Commissioners shall have a reasonable time in which to verify the accuracy of such sworn statement before such final payment is made.”

As the work progressed, estimates were made and approved both by the city engineers and by a firm of consulting engineers retained by the city to draw plans and estimates for the work, and to see that it was properly performed. These estimates were accepted, approved, and paid by the city through its duly constituted authorities. The amount paid to the contractor on such estimates aggregates a sum over $800,000.

For the purpose of securing funds for the construction of the sewer system, the city issued and sold bonds to the amount of $1,200,000. These bonds were sold to Ualdwell & Co., bankers and brokers of Nashville, Tenn., and the funds derived from the sale of the bonds were deposited with that 'Company which gave bond to indem- ■ nify the city against loss with the Southern Surety Company of New York as its surety. After the money was deposited with Caldwell & Go. it appears that this com-' pany went into the hands of a receiver and some or all of the funds going to pay for the work as it progressed were provided by or through the surety company.

On August 3, 1931, the board of commissioners of the city approved and ordered the payment of $8,558.26 on an estimate for work done in July, and which had been approved by the city engineer and the consulting engineers. $5,000 of this amount was ordered paid to the First National Bank & Trust Company of Owensboro, on order of the contractor. On September 4, the city paid the $5,000 due the bank, but did not pay $25.50 interest accruing subsequent to the time the estimate was approved and ordered paid. The draft or check for the balance of $3,558.26 was not paid. On August 17, the board of commissioners approved and allowed an estimate for $2,898.52 for work done in August, and this sum was paid to the contractor. This estimate showed the completion of all work on the sewer system under the contract. This estimate also showed the total amount retained by the city to be the sum of $157,875;56, representing 15 per cent of the estimates approved and *345 allowed as the work- progressed. The commissioners approved the estimate as to the sum which had been retained by the city and allowed and ordered same to be paid on the 16th day of October, 1931, subject, however, to any and all sums that might be owing to the city by the contractor and to an order from him to the Highland Park State Bank of Highland Park Mich., for the snm of $35,000 accepted by the city and further subject to any and all claims against the contractor in connection with or growing out of the performance of his contract with the city.

On November 13, 1931, the contractor filed his petition in equity against the city and its mayor, city commissioners, and treasurer, reciting the foregoing and other facts, which it is unnecessary for us to enumerate here, and prayed judgment for the unpaid balance of $3,558.26, the estimate of Augmst 3, 1931, with interest from that date, and also the sum of $25.50 interest accruing on the amount ordered paid to the First National Bank & Trust Company of Owensboro out of that estimate, and for the .sum of $157,875.56, the amount which had been retained by the city under the contract and which had been allowed and ordered paid to him on October 16, 1931, with interest from that date, less the sum of $4,590 which plaintiff owes the city of Owensboro, and less the sum of $35,000 which the city should pay direct to the Highland Park State Bank under the order referred to in the petition. He also prayed for a mandatory injunction ordering and directing the defendants to pay the balance due him. Motion of the city to require plaintiff to give bond for costs was sustained, and the bond was given.

By amended petition, plaintiff alleged that he had completed, fulfilled, and performed all the requirements of the contract and had shown such performance by his sworn statement made before a notary public, setting out fully the amount, kind, and quality of the several materials used and incorporated into the work required to be done, and which had actually been done by him, and, as required by the court, he filed with his petition as a part thereof the original plans and specifications referred to and made a part of his contract with the city. He also filed as an exhibit with and as a part of his petition a copy of a letter written and transmitted to the defendants by the consulting engineers, showing the completion and fulfillment of the contract by plaintiff as set *346 out in the petition. This amended petition sets out a list of persons and firms to whom plaintiff is indebted for work or materials in connection with the performance of his contract, and alleged that he had paid in full all subcontractors, workmen, and employees for work performed, and had paid for all materials except those set out in the petition as amended.

The city interposed a special demurrer to the petition because the city clerk had not been made a party. The demurrer was sustained by the court, and a second amended petition was filed making the city clerk and other officials parties defendant.

Free access — add to your briefcase to read the full text and ask questions with AI

City of Owensboro v. Nolan, 46 S.W.2d 490, 242 Ky. 342, 1932 Ky. LEXIS 274 (Ky. 1932).

46 S.W.2d 490 (City of Owensboro v. Nolan) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

O'Mara v. Town of Mt. Vernon
185 S.W.2d 675 (Court of Appeals of Kentucky (pre-1976), 1945)
Horton v. Horton
92 S.W.2d 373 (Court of Appeals of Kentucky (pre-1976), 1936)
Caldwell & Co.'s Ancillary Receiver v. Landrum
83 S.W.2d 876 (Court of Appeals of Kentucky (pre-1976), 1935)
Nolan v. City of Owensboro
75 F.2d 375 (Sixth Circuit, 1935)
Estes v. Woodford
55 S.W.2d 396 (Court of Appeals of Kentucky (pre-1976), 1932)
Griffin v. City of Owensboro
50 S.W.2d 514 (Court of Appeals of Kentucky (pre-1976), 1932)