City of Osceola v. Gjellefald Construction Co.

263 N.W. 1, 220 Iowa 685
CourtSupreme Court of Iowa
DecidedOctober 23, 1935
DocketNo. 43060.
StatusPublished
Cited by4 cases

This text of 263 N.W. 1 (City of Osceola v. Gjellefald Construction Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Osceola v. Gjellefald Construction Co., 263 N.W. 1, 220 Iowa 685 (iowa 1935).

Opinion

Donegan, J.

In the fall of 1933 the city of Osceola entered into a contract with the defendant, Gjellefald Construction Company, whereby the construction company undertook to build a dam, filter, spillway, and reservoir for the waterworks system of said city according to certain plans and specifications which were made a part of the contract. The work was apparently completed and the city took possession of it and proceeded to use it. In February, 1935, the city commenced an action against the construction company and also against Aetna Casualty & Surety Company, the surety on the construction company’s bond, for damages alleged to have been suffered by the city because of the failure of the construction company to perform its contract. To the petition filed by the plaintiff city the construction company filed a motion to^ strike certain statements of the petition, and, subject to the ruling on this part of the motion, to make the petition more specific. Upon hearing, the trial court overruled the part of the motion asking that parts of the petition be stricken, and also overruled the part of the motion asking that the petition be made more specific, but ordered the plaintiff to amend its petition and set out an itemized statement of the repairs which it claimed it had made and the costs thereof. From this ruling of the trial court, the defendant construction company appealed.

A motion of the appellee to dismiss the appeal, on the ground that the ruling from which the appeal is taken is not an appealable order, was submitted and overruled prior to the submission of the case, and we, therefore, do not consider such motion in this opinion.

Appellee also claims, as one of the grounds why the ruling of the trial court should be affirmed, that the defendant Aetna Casualty & Surety Company did not join in the appeal and no sufficient notice was served on it as required by Code section 12834. The basis of this claim is that the firm of Thomas & Loth were attorneys for both defendants; that the notice of appeal was signed by this firm as attorneys for the *687 defendant construction company and was accepted by this same firm as attorneys for the defendant Aetna Casualty & Surety Company. The statute in regard to service of notice of appeal, section 12837, Code 1931, provides that,

“An appeal is taken and perfected by the service of a notice in writing on the adverse party, his agent, or any attorney who appeared for him in the case in the court below, and by filing said notice with return of service indorsed thereon or attached thereto with the clerk of the court wherein the proceedings were had.”

We think the record clearly shows that notice of appeal was served upon the Aetna Casualty & Surety Company by service upon the attorneys who appeared for it in the lower court, that it was properly addressed and service accepted by these attorneys, and that it was filed with the clerk of the trial court, as required by the statute. We find no basis for dismissing the appeal on the grounds contended for by appellee.

The portion of the petition alleging a breach of the contract and bond is as follows:

“That the dam and spillway were not properly settled, tamped and made water tight, and they were so built that they settled, dropped away from the cement facings thereon, leaked, and are in danger of being washed out. That they were not properly covered and faced with cement. That the cement used was not of sufficient thickness, richness or construction so that it would hold water or to. keep said cement in place and that water leaked through the same and was about to wash out the said dam and spillway.
‘ ‘ That plaintiff was compelled to repair said dam and spillway at a large expense to keep the same from washing out and losing all of said work and the water which it has saved.
‘ ‘ That the cement broke and settled and had to be repaired, that a large part of it is covered with water and it will be necessary to put in a retaining wall to hold back the water until the dam and spillway can be repaired. That the cost and expense of the retaining wall will be large. That the intake constructed.by the defendant Gjellefald Construction Company was not properly constructed. That it was not made of sufficient and proper material. That the work done thereon was *688 not done in a workman-like manner. That the same leaks and that it will cost a large sum to repair, fix and rebuild it.
“That the work done on the dam, spillway and the facing thereof and the covering thereon was not done in a workmanlike manner and was not made of proper material, and that it will cost a large sum to renew, repair and replace these things.”

The appellant in its motion asked that these statements be stricken as conclusions, and, alternately, that the appellee be required to make them more definite and specific in the manner pointed out in the motion. That these statements, as they appear in the petition itself, are conclusions and not statements of fact is quite apparent. In fact, the trial court so stated in his ruling, but held that the exhibits which accompanied the petition and were made a part thereof supplied a sufficient statement of facts to remedy any deficiency in this regard in the petition itself. Aside from requiring the appellee to amend and set out a more specific statement as to the amount and items of damage claimed for repairs that had already been made, the trial court held that the petition sufficiently stated in a general way that the bond had been breached by the use of improper material and by unworkmanlike construction, and that, as the appellant company must know what kind of material it used in the construction of the dam and the manner in which the work was done, these matters were peculiarly within the knowledge of the appellant, and no more specific statement thereof was required.

Under our system of pleading, section 11111, subd. 3, Code 1931, a pleading must plead ultimate facts.

“ * # * a pleader must plead the ultimate facts in the case. He cannot plead conclusions by themselves. A good pleading consists of the statement of the ultimate facts in the case, and, when so stated, the pleader has a right.to plead his conclusion based upon those facts.” Townsend v. Armstrong, 220 Iowa 396, 398, 260 N. W. 17, 18; Taylor County Farm Bureau v. Board, 218 Iowa, 937, 252 N. W. 498.

In a suit on a bond, as is the case at bar, section 11217, Code 1931, provides that “the party suing thereon shall notice the conditions and allege the facts constituting the breaches *689 relied on.” As stated in the Townsend and Taylor County Farm Bureau cases, if a petition states facts sufficient to constitute a cause of action, it may further state the conclusions to which such facts lead. The trial court, therefore, could properly have refused to strike the statements of the petition which were conclusions, if the petition contained a sufficient statement of facts, or, if the trial court required the plaintiff to amend and state sufficient facts to furnish a basis for such conclusions.

Appellant sets out fifteen alleged errors of the trial court in its ruling on appellant’s motion.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Eaton v. Downey
118 N.W.2d 583 (Supreme Court of Iowa, 1962)
Lagerpusch v. Lindley
115 N.W.2d 207 (Supreme Court of Iowa, 1962)
New York Life Insurance v. Clemens
297 N.W. 253 (Supreme Court of Iowa, 1941)
Osceola v. Gjellefald Construction Co.
279 N.W. 590 (Supreme Court of Iowa, 1938)

Cite This Page — Counsel Stack

Bluebook (online)
263 N.W. 1, 220 Iowa 685, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-osceola-v-gjellefald-construction-co-iowa-1935.