City of Omaha v. Yancey

135 N.W. 1044, 91 Neb. 261, 1912 Neb. LEXIS 214
CourtNebraska Supreme Court
DecidedApril 20, 1912
DocketNo. 16,979
StatusPublished
Cited by11 cases

This text of 135 N.W. 1044 (City of Omaha v. Yancey) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Omaha v. Yancey, 135 N.W. 1044, 91 Neb. 261, 1912 Neb. LEXIS 214 (Neb. 1912).

Opinion

Rose, J.

Contractors who had been directed to build 50 feet of sidewalk along the east side of Fifteenth street between Ohio street and Spring street in Omaha made and left unprotected an excavation in the sidewalk space at that place. Lizzie Wright fell into it and was injured. In an action against the city for damages for personal injuries caused in the manner stated, she recovered a judgment for |5,000. The city paid the judgment and brought this suit against the contractors and their bondsmen to recover the amount so paid. Prom a judgment in favor of the city for the full amount of its claim defendants have appealed.

The first point urged by the contractors as a ground of reversal is that they are not bound by the judgment in the case of Wright against the city, because they had not been notified of the pendency of the action in which it was rendered. This position cannot be maintained. Two abstracts were filed, one by defendants and the other by the city. The latter states that a formal notice by the city attorney to the contractors, advising them of the action of Wright against the city, of the nature of the suit, of the court and docket number, of their right to make a defense and of their liability for the payment of any judgment which might be rendered against the city, was served personally on each of the contractors July 17, 1903. The suit against the city had been commenced June 6, 1903, and the case was tried at the October term, 1904. This [263]*263notice, if properly given, was sufficient. It is argued, however, by the contractors that the proof of notice, as stated, is incompetent, but it is not found in their abstract, nor' is there anything therein to show it was erroneously admitted. While the city’s abstract contains the evidence showing proof of notice, it does not show that the contractors objected to its admission or excepted to the ruling admitting it, and the bill of exceptions, under the circumstances disclosed, will not be examined 'for the purpose of sustaining this assignment of error.

The only other assignment argued by the contractors is that the trial court erred in holding them liable for an injury occurring subsequent to the termination of their contract. They assert that the excavation was made November 25, 1902; that their contract terminated by its own terms December 31, 1902; that the injury to the plaintiff in the suit of Lizzie Wright against the city occurred January 20, 1903; and that they were not required to protect the public from the excavation after the contract expired December 31, 1902.

By formal, written contract duly executed the contractors bound themselves: “To furnish material and construct therewith, and maintain, in a good and workmanlike manner, permanent sidewalk in the city of Omaha, according to plans and specifications on file in the office of the board of public works of said city, and as hereunto appended, as may he ordered from time to time by the mayor and city council of said city, from the 1st day of January, 1902, to the 31st day of December, 1902,” and “to hold the said city harmless and free from all damages that may result through the injury of any person or thing by reason of any negligence or lack of care in or about the said work or property, and to guard all dangerous points and obstructions resulting from or about the said work, by providing and maintaining proper and sufficient safeguards and day and night signals for that purpose.” One paragraph of the contract is as follows: “If the contractor shall fail to construct any sidewalk that may be [264]*264ordered within sixty days after a written order to construct the same has been given, unless prevented by storms, cold weather or other equally good cause, then the city shall have the right to cause such work and all further work required by the contract to be done and charge the difference between what it would have cost under the contract and what it did cost to such contractor or his bondsmen.”

Do the phrases, “from the 1st day of January, 1902, to the 81st day of December, 1902,” in the connection in which they are used in the contract, refer to furnishing materials and constructing sideAvalks? Do they mean that the contract terminated on the latter date, and that work commenced before the end of' the year could not be completed by the contractors under the same contract in 1903? The city insists that those phrases refer to the ordering of sidewalks, and that it had a right, any time before the end of the year 1902, to order the contractors to proceed with neAV work, which could be completed in 1903, if necessary. The city’s interpretation seems to indicate the intention of the parties, as expressed by the entire instrument. The phrases, “from the 1st day of January, 1902, to the 3.1st day of December, 1902,” seem to limit the immediately preceding clause, “as may be ordered from time to time by the mayor and city council of said city,” rather than the more remote words “to furnish material and construct therewith.” There is no intimation in the contract that the city did riot haAre the right to direct the contractors, as late as December 31, 1902, to construct a sidewalk. Had such an order been given, how could it have been obeyed in a fraction of a day? The right of performance at a later date is clearly indicated by another provision. “If the contractor' shall fail to construct any sidewalk that may be ordered within sixty days after a written order to construct the same lias- been given,” says the contract, “unless prevented by storms, cold weather or other equally good cause, then the city shall have the right to cause such work * * * to be [265]*265done” and to charge the difference in cost to the contractor. This provision indicates an intention to give the contractors ample time to complete a sidewalk after having been ordei*ed to construct it. The contractors not only agreed to construct permanent sidewalk in good workmanlike manner according to plans and specifications on file in the office of the board of'public works, but they obligated themselves to so “maintain” such walks. They were also required to furnish materials and to perform their work “to the satisfaction of the board of public works and the city engineer.” If there should be an unfinished sidewalk, or if materials should be found unsatisfactory, on the last day of the year 1902, the contract, on that date, would clearly not be terminated in such a sense as to prevent the contractors from completing the sidewalk or from furnishing satisfactory materials to replace those rejected. In giving effect to every part of the instrument and to the expressed intention of the parties, it must be held that the dates fixing the beginning and the end of the period refer to the ordering of the sidewalk, and not to the construction thereof by the contractors. 'This interpretation permits the completion of work begun by the contractors and gives them the benefit of full performance, and relieves the city from the embarrassment of a divided responsibility for defects in materials or workmanship. These are factors which would naturally appeal to both parties in agreeing on terms. In this vieAV of the instrument the contractors Avere required to protect the public from the.dangers of their excavation, and this duty did not terminate at the end of the period for ordering sidewalks. For failure to do so they cannot escape liability on the ground that their contract had expired before the accident occurred. This assignment of error must therefore be overruled.

The bondsmen, F. A. Nash and D. P. Redman, are also seeking a reversal.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Baker v. Fabian, Thielen & Thielen
578 N.W.2d 446 (Nebraska Supreme Court, 1998)
Waite Lumber Co., Inc. v. Carpenter
290 N.W.2d 655 (Nebraska Supreme Court, 1980)
Moore v. Drexel Homes, Inc.
293 So. 2d 500 (Louisiana Court of Appeal, 1974)
Metcalf v. Hartford Accident & Indemnity Company
126 N.W.2d 471 (Nebraska Supreme Court, 1964)
In Re Idaho Mutual Ben. Assn., Inc.
53 P.2d 1171 (Idaho Supreme Court, 1936)
Willman v. Bumgarner
53 P.2d 1171 (Idaho Supreme Court, 1936)
Corcoran v. Leon's, Inc.
252 N.W. 819 (Nebraska Supreme Court, 1934)
Dawson Farmers Elevator Co. v. Opp
223 N.W. 350 (North Dakota Supreme Court, 1928)
Heyen v. State
210 N.W. 165 (Nebraska Supreme Court, 1926)
Town of Barnet v. Town of Norton
99 A. 238 (Supreme Court of Vermont, 1916)
Rouleau v. Continental Life Ins. & Inv. Co.
144 P. 1096 (Utah Supreme Court, 1914)

Cite This Page — Counsel Stack

Bluebook (online)
135 N.W. 1044, 91 Neb. 261, 1912 Neb. LEXIS 214, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-omaha-v-yancey-neb-1912.