City of New York v. Herdje

68 A.D. 370, 74 N.Y.S. 104
Appellate Division of the Supreme Court of the State of New York·Decided January 15, 1902·Published·Cited by 7 cases

Opinion

Jenks, J.:

An inspector of buildings testified that on April 13, 1901, he went to the premises- and examined them thoroughly without seeing any signs of work begun by excavation or otherwise. He further testifies that he passed by the premises every other day; that on May 28, 1901, he saw excavation work doing, and that the contractor told him that he had begun work on May 27, 1901. On the other hand, the defendant testifies that he began work at' about eleven-thirjy a. m. of April 12,1901, the day the permit was granted, by causing two laborers whom he had “ picked up ” in the street to dig holes in each lot. Doenecke testifies that he entered into a contract with the defendant before twelve m. of April 12, 1901; that he told the defendant to get two men to go to work, whereupon the defendant hired two men on the street, who began to dig on the premises before twelve m., and that he (Doenecke) stayed there about fifteen minutes. On cross-examination he testified that his cellar digger commenced actually digging ” there after the middle of May — not the twenty-eighth of May. The learned referee found that no work was actually begun upon the construction of the proposed buildings on the premises after the approval of the plans and the grant of the permit before the enactment of chapter 334, Laws of 1901, or, in other words, before April 12, 1901. (See said statute and, particularly, § 165 thereof.) There is no such preponderance of evidence as would justify a conclusion with reasonable certainty that the finding was erroneous, and, therefore, it should not be disturbed.. (Lowery v. Erskine, 113 N. Y. 52; Burton Co. v. Cowan, 80 Hun, 392; affd. on opinion below, 150 N. Y. 583 ; Shute v. Jones, 78 Hun, 99; Slattery v. Haskin, 3 App. Div. 48.)

Section 4 of said statute reads : “ A tenement house not now completed, but upon which work has been actually commenced after approval of the plans therefor by the department of buildings, shall be subject only to the provisions of this act affecting now existing tene[372] ment houses.” I think .that the section does not free the defendant from the provisions of the act of 1901, for the reason that although plans had been approved, yet work .thereon, had not been, actually . commenced at the time of the passage of the act; namely, April 12, 1901. On April 25, 1901, this section was amended by chapter 555 of the-Laws of 1901 so as to read as follows: Buildings'in process of erection.— A tenement house not now completed, but the excavation for which shall have been commenced in good faith on or before the first day of June, nineteen hundred and one, after approval of the plans therefor by the department of buildings, and the first tier of beams of which shall have been set on or before the first day of August, nineteen hundred and one, shall be subject only to the provisions Of this act affecting now existing tenement houses; provided that the plans for said house were filed in said department on or before the tenth day of April, nineteen hundred and one, and were in accordance with the laws in force at the time of filing, and that the building is built in accordance with such laws.”

It appears that on the said twenty-fifth day of. April the notice of revocation of the permit was sent to the defendant. The learned counsel for the appellant contends that inasmuch as the ground alleged for the revocation was not that the plans for said house were not filed on or before the tenth day of April, but that no work had been actually commenced at the time of the passage of the act, the ground assigned for the revocation of the plans was a provision of law which did not exist at the time of the revocation. ' He points out that the complaint made in July, 1901, asked for relief for noncompliance with the unamended section i, and that the conclusion of the learned referee was based upon a violation of the said unamended section. But I am of opinion that if the defendant incurred any liability pursuant to the unamended section, that was not affected by the subsequent repeal thereof. Section 31, chapter 677, Laws of 1892, reads: “ The repeal hereafter or by this chapter of any provision of a statute, which repeals any provision of á prior statute, does not revive such prior provision. The repeal hereafter or by this chapter of any provision of a statute which amends a provision of a prior statute, leaves such prior provision- in force unless the amendatory statute be a substantial re-enactment of the statute amended. The repeal of a statute or ])art thereof shall not [373] affect or impair any act done or right accruing, accrued, or acquired, or liability, penalty, forfeiture or punishment incurred prior to the time such repeal takes effect, but the same may be asserted, enforced, prosecuted or inflicted, as fully and to the same extent as if such repeal had not been effected ; and all actions and proceedings, civil or criminal, commenced under or by virtue of any provision of a statute so repealed, and pending immediately prior to the taking effect of such repeal, may be prosecuted and defended to final effect in the same manner as they might if such provisions were not so repealed.” In McCann v. City of New York (52 App. Div. 358; affd., 166 N. Y. 587) the court held that tlje foregoing section, while not attempting to interfere with future legislation, prescribed a rule of construction applicable when' not inconsistent with a general object of a subsequent statute or the context of the language construed or other provisions of the repealing law. indicating a different intent. I think that the principle of that decision applies to this proceeding. In reaching this conclusion, I am not embarrassed by the complications that the question arises upon a penal statuté, or by the consideration that the amendment of the said section 4 restores any right to the defendant, inasmuch as the proviso excludes the defendant because his plans were filed neither on nor before the 10th day of April, 1901, but subsequent théreto, namely, on April 12, 1901.

Free access — add to your briefcase to read the full text and ask questions with AI

City of New York v. Herdje, 68 A.D. 370, 74 N.Y.S. 104 (N.Y. Ct. App. 1902).

68 A.D. 370 (City of New York v. Herdje) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

People ex rel. Publicity Leasing Co. v. Ludwig
172 A.D. 71 (Appellate Division of the Supreme Court of New York, 1916)
Powell v. City of Rochester
93 Misc. 227 (New York Supreme Court, 1916)
Southern Leasing Co. v. Ludwig
168 A.D. 233 (Appellate Division of the Supreme Court of New York, 1915)
Washington v. Atlantic Coast Line Railroad
71 S.E. 1066 (Supreme Court of Georgia, 1911)
Czermak v. Wetzel
114 A.D. 816 (Appellate Division of the Supreme Court of New York, 1906)
Williams v. Whittell
69 A.D. 340 (Appellate Division of the Supreme Court of New York, 1902)