City of Milford v. J. H. Hogan, Inc., No. Cv91-034239 (May 7, 1991)

1991 Conn. Super. Ct. 4661, 6 Conn. Super. Ct. 515
CourtConnecticut Superior Court
DecidedMay 7, 1991
DocketNo. CV91-034239
StatusUnpublished

This text of 1991 Conn. Super. Ct. 4661 (City of Milford v. J. H. Hogan, Inc., No. Cv91-034239 (May 7, 1991)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Milford v. J. H. Hogan, Inc., No. Cv91-034239 (May 7, 1991), 1991 Conn. Super. Ct. 4661, 6 Conn. Super. Ct. 515 (Colo. Ct. App. 1991).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.] MEMORANDUM OF DECISION ON MOTION TO CONFIRM ARBITRATION AWARD AND MOTION TO VACATE ARBITRATION AWARD The plaintiff, City of Milford entered into a construction contract with the defendant J. H. Hogan Inc. (Hogan) for construction of the Milford Courthouse. The contract between the parties provided for arbitration of disputes between them by arbitration under the Construction Industry Arbitration Rules. On December 12, 1988 the defendant made a demand for arbitration through the American Arbitration Association claiming that Milford breached the construction contract in several respects, including failure CT Page 4662 to pay for changes in the work and failure to make final payment under the terms of the contract. Arbitration was requested for:

A determination of all sums due, including, but not limited to, losses incurred both directly and indirectly as a result of delays in the prosecution of claimant's work including all extended field and home office overhead costs. Hogan also seeks a determination of the sums due it for lost labor productivity, loss of use of money, extra work, contract balance and interest. Claimant also seeks a determination that all fees and administration expenses in connection with this arbitration, including a reasonable attorney's fee, be awarded to claimant."

The arbitration panel selected consisted of an architect, a contractor and an attorney. The attorney was later disqualified, apparently because of contacts between him and representatives of Hogan. There were 20 days of arbitration hearings before the two remaining arbitrators. Hogan filed a pre-hearing memorandum with the arbitrators itemizing the damages claimed by it, which totalled $714,826.37. The memorandum stated that this amount did not include attorney's fees, costs of arbitration and similar costs which the claimant requested as part of an arbitration award. Milford had a counterclaim for its damages. No evidence was offered on the claim for attorney's fees during the arbitration hearings.

In its post hearing memorandum (Pgs. 31-35,) Hogan claimed attorney's fees as punitive damages alleging that the submission of "all disputes" to arbitration included attorney's fees, costs and punitive damages. It claimed that it was entitled to punitive damages because of intentional bad faith conduct by Milford in refusing to make payments called for under the contract, labelling this as "stall tactics and financial extortion." Attached to the memorandum was an affidavit from Attorney Lawrence Rosenthal of Pepe and Hazard, the attorneys for Hogan, and an affidavit from the billing manager from the law firm summarizing the bills and charges to Hogan for legal fees for the arbitration, totalling $124,621.14. The post-trial briefs of both parties were dated September 26, 1990, and Milford's brief did not extensively discuss the subject of attorney's fees other than claiming that there was no statute or contract provision allowing for attorney's fees so that the arbitrators could not award them. (Milford Brief of September 26, 1990, p. 44). Hogan's reply brief dated October 10, 1990, p. 21, referred CT Page 4663 to cases which it claimed allowed attorney's fees, and stated "the panel has the authority to award anything it wants." The city's reply brief of October 9, 1990 objected to claims for rescission of the contract, punitive damages and attorney's fees on the basis that evidence on those claims was not presented during the arbitration hearings. Milford claimed that presenting evidence in this way violated the concept of a fair hearing and rules 31 and 32 of the Construction Industry Arbitration Rules and its fundamental right of cross examination of witnesses and the right to offer evidence in opposition at the hearings.

On November 15, 1990 the arbitrators made their decision, awarding Hogan the sum of $651,049.37 and awarding Milford $45,216.61 on the counterclaim, for a net award to Hogan of $605,832.76. It also ordered that the administrative fees and expenses of the American Arbitration Association should be equally divided.

After the award was made Milford requested through the American Arbitration Association that the arbitrators break down their claim to clarify the dollar amounts awarded as to nine separate areas, including attorney's fees and interest on two of the defendants claims. The defendant objected at that time to reinstating the authority of the arbitrators for the purpose of clarifying the award. Milford then filed this application to correct or vacate the arbitration award, contesting interest and attorney's fees, and Hogan then filed a motion to confirm the arbitration award. At the suggestion of the court the parties agreed to request the arbitrators to reconvene and clarify their award only on the issue of attorney's fees and to indicate (1) whether any attorney's fees were awarded to Hogan and (2) if so, the amount of the fees awarded. The arbitrators responded that under the arbitration rules and the Connecticut arbitration statutes that they were not required to break down any awards and refused to do so.

Milford's application is made under section 52-418 of the General Statutes to vacate the arbitration award. While section 52-419 (a)(2) allows the Superior Court to make an order modifying or correcting an arbitration award if the arbitrators have awarded money upon a matter not submitted to them, the submission to them of the dispute under the construction contract was unrestricted. The failure of the arbitrators to state what amount, if any, was awarded for attorney's fees makes it impossible to reduce the award by the amount of any attorney's fees that were improperly awarded. CT Page 4664

Section 52-418 allows the Superior Court to vacate an arbitration award if any one of four specified defects exists. However, the factors stated in section 52-418 which allow an arbitration award to be vacated are not exhaustive and do not limit the scope of judicial review of arbitration awards in all instances. Stratford v. Local 134, IFPTE,201 Conn. 577, 583. Subsection (1) of the statute allows the award to be challenged if it has been procured by undue means. Subsection (3) allows an arbitration award to be vacated if the arbitrators have refused "to hear evidence pertinent and material to the controversy or of any other action by which the rights of any party have been prejudiced."

The party challenging an arbitration award has the burden of proving any claim of misconduct. Twin Towers Associates v. Gilbert Switzer Associates, 4 Conn. App. 538,540, cert. denied 197 Conn. 811. See also Lacey v. Williams,16 Conn. App. 711, 714; Schwarzschild v. Martin, 191 Conn. 316,327. In determining whether arbitrators have exceeded their authority or improperly executed the same under section52-418 (a), the court only examines the submission and the award to determine whether the award conforms to the submission. American Universal Insurance Co. v. Del Greco,205 Conn. 178, 186; Waterbury Construction Co. v. Board of Education, 189 Conn. 560, 563; Ramos Iron Works, Inc. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Morgan
313 U.S. 409 (Supreme Court, 1941)
Waterbury Construction Co. v. Board of Education
457 A.2d 310 (Supreme Court of Connecticut, 1983)
Schwarzschild v. Martin
464 A.2d 774 (Supreme Court of Connecticut, 1983)
Ramos Iron Works, Inc. v. Franklin Construction Co.
392 A.2d 461 (Supreme Court of Connecticut, 1978)
Welch v. Zoning Board of Appeals
257 A.2d 795 (Supreme Court of Connecticut, 1969)
Town of Stratford v. Local 134, IFPTE
519 A.2d 1 (Supreme Court of Connecticut, 1986)
Henderson v. Department of Motor Vehicles
521 A.2d 1040 (Supreme Court of Connecticut, 1987)
O & G/O'Connell Joint Venture v. Chase Family Ltd. Partnership No. 3
523 A.2d 1271 (Supreme Court of Connecticut, 1987)
American Universal Insurance v. DelGreco
530 A.2d 171 (Supreme Court of Connecticut, 1987)
Martone v. Lensink
541 A.2d 488 (Supreme Court of Connecticut, 1988)
Bennett v. Meader
545 A.2d 553 (Supreme Court of Connecticut, 1988)
Blaker v. Planning & Zoning Commission
562 A.2d 1093 (Supreme Court of Connecticut, 1989)
Board of Education of Waterbury v. Waterbury Teachers Ass'n
583 A.2d 626 (Supreme Court of Connecticut, 1990)
Twin Towers Associates v. Switzer & Associates
495 A.2d 735 (Connecticut Appellate Court, 1985)
Vincent Builders, Inc. v. American Application Systems, Inc.
547 A.2d 1381 (Connecticut Appellate Court, 1988)
Lacey v. Williams
548 A.2d 1357 (Connecticut Appellate Court, 1988)
Fraund v. Design Ideas, Inc.
551 A.2d 1279 (Connecticut Appellate Court, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
1991 Conn. Super. Ct. 4661, 6 Conn. Super. Ct. 515, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-milford-v-j-h-hogan-inc-no-cv91-034239-may-7-1991-connsuperct-1991.