City of Milbank v. Western Surety Co.

111 N.W. 561, 21 S.D. 261, 1907 S.D. LEXIS 29
CourtSouth Dakota Supreme Court
DecidedApril 2, 1907
StatusPublished
Cited by2 cases

This text of 111 N.W. 561 (City of Milbank v. Western Surety Co.) is published on Counsel Stack Legal Research, covering South Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Milbank v. Western Surety Co., 111 N.W. 561, 21 S.D. 261, 1907 S.D. LEXIS 29 (S.D. 1907).

Opinion

CORSON, J.

The plaintiff, the city of Milbank, instituted this action against the defendants to recover on the bond executed by them the amount of loss sustained by the plaintiff by reason of the defendant McDonald’s failure to carry out his contract to construct a system of sewerage in that city. A directed verdict and judgment being in favor of the plaintiff, the defendant, the Western Surety Company, has appealed.

[265]*265A large number of errors are assigned on the part of appellant, but the grounds upon which a reversal is claimed are grouped and summarized by counsel for appellant in his brief, and thus stated by him; (i) The bond declared on was given to secure the performance of a contract made by a corporation, namely, the Sioux Falls Construction Company, whereas plaintiff is endeavoring to hold us for the default of one A. D. McDonald; (2) the complaint failed to allege that the form of the contract for constructing the sewer was approved by the city attorney; (3) there is no allegation in the complaint that any preliminary measures such as are required by statute before installing a sewerage system were complied with; (4) because neither A. D. McDonald, nor the Sioux Falls Construction Company, although principals, was served with summons nor made parties to this action, nor is any reason shown for such failure; (5) because the city records fail to disclose that an affirmative vote was taken by the city council upon letting the contract for the performance of which, the bond in suit was executed; (6) because the evidence affirmatively shows that, without readvertising for bids, the city council let the contract in question for $1,000 more than the bid made by McDonald and that the same was therefore illegal and voi'd; and (7) the testimony fails to sustain the complaint in its entire scope and meaning.

It is disclosed by the record that the city of Milbank, in the summer of 1904, undertook the construction of a sewerage system, and that the contract for the same was let to one A. D. McDonald. To secure the performance of the contract of the said McDonald the appellant executed a bond with the Sioux Falls Construction Company in the sum of $7,000 for the faithful execution of such contract. The contract was let to McDonald, as the lowest bidder, for the sum of $11,276.35; but before the said contract was executed McDonald, claiming that he had made a mistake in his bid was awarded a further sum of $1,000, without any new advertisement for bids having been made. McDonald entered upon the performance of the contract and, after completing about 500 feet of the main sewer, he abandoned the same, giving the city notice that he would proceed no further. Thereupon the city notified the appellant company of such default within the time specified in the bond, [266]*266and thereafter proceeded to construct the sewerage system without making any new contract and completing the same at the extra expense of about $1,700, over and above the contract price agreed upon with McDonald. Demand having been made by the plaintiff upon the appellant for the extra amount so- expended, over and above the amount specified in the McDonald contract, and the appellant failing to pay such sum, this action was instituted to recover the same. On the trial of the action the defendant objected to the introduction of any evidence on the part of the plaintiff on the ground that the complaint did not state facts sufficient to constitute a cause of action. The objection was overruled by the court, and plaintiffs evidence admitted to> which ruling the appellant duly excepted.

It is contended by the apellant that the complaint is insufficient, for the reason that it is sought to hold the appellant responsible for the acts of A. D. McDonald, whereas in the bond it became surety only for the Sioux Falls Construction Company; but it is alleged in the complaint “that at the times hereinafter mentioned the defendant A. D. McDonald, was doing business, and executed the contract hereinafter mentioned under the name and style of the Sioux Falls Construction Company.” This we think was clearly sufficient as showing that, while the bond was nominally executed by the Sioux Falls Construction Company, the same was in effect executed by A. D. McDonald, and that appellant may properly be held as having entered into' the bond as surety with the said McDonald as principal. Herminston v. Green, 11 S. D. 31, 75 N. W. 819. It is further contended by the appellant that the failure to allege in the complaint that the form of the contract was approved by the city attorney rendered the contract void; but the complaint seems to have been amended on the trial to correspond with the proof that the city attorney did m fact approve the form of the contract. This evidence, we are of the opinion, was admissible, as the requirement of the statute that the contract shall be approved by the city attorney does not provide that the contract should be void in case such approval is not indorsed thereon, and the provision may be regarded as directory, and not mandatory. It is further contended that the complaint was insufficient, for the [267]*267reason that it failed to allege that the city had taken the preliminary steps required by the statute for installing the sewer plant, or constructing the same. But the fact being alleged that it was proceeding to construct such a system was sufficient, and the appellant having contracted with the city, as such surety, must be presumed to’ have done so' with full knowledge of all the facts contained in the records of the city, and is estopped from denying that it was proceeding regularly in advertising for bids for constructing the plant. It is further contended that the complaint was insufficient, for the reason that the Sioux Falls Construction Company and A. D. McDonald were not served with process; but such failure did not affect the appellant jvho was severally as well as jointly liable on his contract with the other defendant named.

On a motion made by the appellant to direct a verdict in its favor, it was further claimed that the evidence was insufficient to entitle the plaintiff to recover, for the reason that it did not appear by the records of such council that the contract was ordered to be executed by an affirmative vote of a majority of the council; and also that the evidence affirmatively shows that said council without readvertising added $1,000 to the price bid by the said McDonald, and also completed said contract without letting any new contract or advertising for bids therefor. The last contention was very fully discussed by the Court of Appeals of New York in the case of In the Matter of the Petition of John G. Leeds to Vacate an Assessment, 53 N. Y. 400, in which that learned court held that the requirement of the charter of the city of Brooklyn, that contracts should be let to the lowest bidder, after due advertisement, was not applicable' to a contract that had been abandoned, and in such a case the city might proceed to complete the work without further advertising. The court in its opinion, speaking by Chief Justice Church, says: “The laws of 1859 * * * providing for laying out sewer districts in the city of Brooklyn, authorizes commissioners to advertise and let the work to the lowest bidder and contains the following provision: The said commissioners shall, in no^ case, proceed with the construction of any sewer except upon the advertisement for proposals for the construction of the same as herein provided. This provision, I think, applies only to the contract for [268]*268the original construction of the sewer.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Paris v. Bray
175 S.W. 432 (Texas Supreme Court, 1915)
Whittaker v. City of Deadwood
122 N.W. 590 (South Dakota Supreme Court, 1909)

Cite This Page — Counsel Stack

Bluebook (online)
111 N.W. 561, 21 S.D. 261, 1907 S.D. LEXIS 29, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-milbank-v-western-surety-co-sd-1907.