City of McPherson v. Stucker

282 P. 703, 129 Kan. 262, 1929 Kan. LEXIS 62
CourtSupreme Court of Kansas
DecidedDecember 7, 1929
DocketNo. 28,916
StatusPublished
Cited by4 cases

This text of 282 P. 703 (City of McPherson v. Stucker) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of McPherson v. Stucker, 282 P. 703, 129 Kan. 262, 1929 Kan. LEXIS 62 (kan 1929).

Opinion

The opinion of the court was delivered by

Harvey, J.:

This is an appeal from an order of the court overruling a motion for a judgment on the entire record.

In order better to understand the question presented by this motion the record of the case must be considered. That portion of the record pertinent to our present inquiry may be stated as follows: The city of McPherson, desiring to build a concrete waterproof tower for its system of waterworks, after having plans and specifications prepared for that purpose, let a contract for the work to Stucker, Stucker & Strachan, by the terms of which the contractors undertook, for an agreed consideration, to furnish all of the material and labor and to construct the water tower in accordance with the plans and specifications, and warranted and guaranteed that the tower when so constructed would not leak for a term of one year. The contractors gave the statutory bond, which was signed by the Fidelity and Deposit Company of Maryland as surety. The contract specified the particular kind of waterproofing to be used. This waterproofing is manufactured and applied to water towers by the Contract Waterproofing Company, of St. Louis. Stucker, Stucker & Strachan made a contract with the Contract Waterproofing Company by the terms of which the latter company agreed, for a named consideration, to furnish the labor and material and apply its waterproofing to the tower after it was constructed, and in this contract warranted and agreed that the waterproofing would hold water and would not leak for a period of one year, and to secure the faithful performance of its contract it executed to Stucker, S'tucker & Strachan its bond, signed by the Fidelity and Deposit Company of Maryland as surety. The water tower was constructed by the contractors and the waterproofing applied by the subcontractor, but the tower did not hold water. The reason the tower would not hold water was thought to be in the waterproofing, and the Contract Waterproofing Company having been notified of that fact undertook to correct the trouble, but was unable to do so. After considerable effort to correct the trouble both the contractors and the subcontractor ceased further efforts, and the city of McPherson was compelled to, and did, let another contract, using different ma[264]*264terials for the waterproofing of the tower, and was successful in having it hold water. The cost of this work to the city of McPherson was about $6,000. The city sued the contractors, Stucker, Stucker & Strachan, and their bondsman for the amount it had thus expended, and as a basis for recovery alleged that defendants “did put in a waterproofing which material was defective and inferior and not such as required by the plans and specifications; that the work in putting it on was done unskillfully and not properly put on and it peeled off and did not stay, and the standpipe did not hold and retain the water.” Following the filing of this action, and before the issues therein were completed, Stucker, Stucker & Strachan, in writing, notified the Contract Waterproofing Company that the action had been filed and that the city predicated its right to recover upon the fact that the materials used in waterproofing the tower and the workmanship furnished by the Contract Waterproofing Company were inferior and unskilled, and specifically requested the Contract Waterproofing Company to come into said cause and defend the same, inasmuch as the city made no complaint of any part of the work except the waterproofing. The Contract Waterproofing Company declined to comply with that request. The city had not paid the contractors the full sum due them under their contract, and they counterclaimed for about $4,500 unpaid on their contract. They also took the position that since their contract with the city specified the character of waterproofing to be used on the tower, and that having been used, they were not liable for the defects in the tower resulting therefrom.

The case involving this last question reached this court (City of McPherson v. Stucker, 122 Kan. 595, 256 Pac. 963; 123 Kan. 584, 256 Pac. 963), where it was held in effect that under the contract between the city and Stucker, Stucker & Strachan the contractors had guaranteed a water-tight structure, and that they were liable to the city for the breach of that guaranty without regard to whether the fault lay in the part of the tower constructed by the contractors, or in that part of it constructed by the subcontractor. Thereafter the city amended its petition so as to predicate its right of action on the allegation that the defendants, Stucker, Stucker & Strachan, had “failed to produce a water-tight standpipe.” The defendants Stucker, Stucker & Strachan plead to that petition and also filed a cross petition against its codefendant, the bonding company, in which it alleged in substance that any defects in the tower [265]*265were the fault of the Contract Waterproofing Company, and contended that the bonding company, as surety for the Contract Waterproofing Company, was liable to the contractors for any sum they might be compelled to pay to the city. The bonding company contended it was not in court for the purpose of being sued on that bond, but only in court on the bond which it had signed for the contractors. On this point the trial court held against the bonding' company, and there has been no appeal from that ruling. The cause went to trial on the amended pleadings as between the city and the contractors, Stueker, Stueker & Strachan. At the close of the evidence the court instructed the jury, among other things:

“There is very little or no controversy in the evidence in this case and under our state law as it appears in this action the evidence is conclusive that the concrete work is perfect and under the contract made and entered into between the city and the defendants, Stueker, Stueker & Strachan, that they guaranteed or warranted a water-tight standpipe and that the standpipe as constructed by them with the Ferro-tite waterproof lining as furnished by the Contract Waterproofing Company failed to waterproof' the standpipe and prevent its leaking and the defendants thereby failed to deliver the thing agreed upon and they are liable for the natural and reasonable damages arising because of such failure.”

The only real controversy at the trial of the case was the allowance of the items claimed by the city as making up its expense or damage. A verdict was returned in favor of the plaintiff and against the defendants, over and above the sum the city owed the contractors under their contract, in the sum of $1,501. Stueker, Stueker & Strachan have paid this judgment. In the trial no issue was submitted to the jury with respect to the liability of the bonding company, that being specifically reserved for the determination of the court. Thereafter the bonding company filed an amended answer to the amended and supplemental cross petition of Stueker, Stueker & Strachan in which it alleged the failure of Stueker, Stueker & Strachan to construct the water tower in accordance with the plans and specifications in many details, and particularly with the concrete work, as a result of which the water tower had not been constructed so that it could be waterproofed successfully by the Contract Waterproofing Company. Thereafter the Contract Waterproofing Company, by leave of court first obtained, filed its answer to the cross petition of Stueker, Stueker & Strachan against the bonding company, in which it adopted the amended answer of the bonding company and made the same a part of its answer, and [266]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dennis v. Southeastern Kansas Gas Co.
610 P.2d 627 (Supreme Court of Kansas, 1980)
Kansas Turnpike Authority v. Watson
371 P.2d 119 (Supreme Court of Kansas, 1962)
Olmstead v. Fidelity & Deposit Co.
28 P.2d 722 (Supreme Court of Kansas, 1934)

Cite This Page — Counsel Stack

Bluebook (online)
282 P. 703, 129 Kan. 262, 1929 Kan. LEXIS 62, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-mcpherson-v-stucker-kan-1929.