City of Mayfield v. Carey-Reed Co.

83 S.W.2d 891, 260 Ky. 43, 1935 Ky. LEXIS 419
CourtCourt of Appeals of Kentucky (pre-1976)
DecidedJune 11, 1935
StatusPublished
Cited by1 cases

This text of 83 S.W.2d 891 (City of Mayfield v. Carey-Reed Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky (pre-1976) primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Mayfield v. Carey-Reed Co., 83 S.W.2d 891, 260 Ky. 43, 1935 Ky. LEXIS 419 (Ky. 1935).

Opinion

Opinion op the Court by

Judge Rees —

Affirming.

The appellee, Carey-Reed Company, brought this action against the city of Mayfield to recover $4,679.77 alleged to be due for street and sidewalk construction work done on the “Paducah road” from Maple street to the north limits of the city, a distance of 400 or 500 feet.

In 1925 the city initiated an ambitious program for the construction of streets and sidewalks, and during the succeeding two years contracts in the aggregate amount of neárly $1,000,000 were let. Carey-Reed Company was the successful bidder for practically all of the work, and the last contract under the original program was completed early in the year 1927. In January, 1927, Carey-Reed Company approached the city council with a proposition to pave the Paducah road from the end of the first construction at the north line of Maple avenue north to the city limits. The company proposed to pave this section of street with amesite and to furnish the material f. o. b. cars at the mine, the city to pay only the freight and the cost of laying the material. It was represented to the city that amesite was a new type of road-building material which Carey-Reed Company was anxious to introduce, since it was the owner of mines producing the material, and for that reason it was willing to furnish it free of cost to the city at the mines.

In order to enable the city to levy an assessment against the property abutting on this section of street to pay the cost of construction, an ordinance was adopted providing for the original construction of the street. Various materials which might be used, including amesite, were named in the ordinance, and it also provided for grading the street and for the construction of a concrete curb and gutter and sidewalks where necessary. *45 The bid of Carey-Reed Company for paving the street with amesite on a gravel base was the only one submitted and was accepted. The contract was entered into on March 21, 1927, and provided that the work should be completed on or before June 1, 1927.

The work was completed on May 25, 1927, and on the same day the city engineer made an estimate of the materials furnished and labor performed, and certified these facts to the city and to the contractor. The engineer certified that the amount due under the contract was $4,679.77.

After receipt of the city engineer’s estimate of the total cost of the improvement, the city gave the notice prescribed by section 3573 of the Statutes to the property owners, who at once protested in writing against the acceptance of the improvement. It was their contention that the work had not been performed in accordance with the contract and that there were defects both in materials and workmanship. There was considerable bickering back and forth, and Carey-Reed Company made certain repairs to the street which had just been completed. In November, 1927, the street committee reported that the work had not been performed in compliance with the contract, and on November 28, 1927, the city council approved the report and formally rejected the work. Nothing further was done until October 24, 1932, when Carey-Reed Company brought this action against the city to recover the amount alleged to be due under the contract and asking that the city be required to assess the property abutting the improvement as required by law.

On December 9, 1932, the city filed a pleading styled answer, set-off, counterclaim, and cross-petition, in which it set out the proceedings leading up to the letting of the contract' for the improvement of Paducah road and alleging that the work was not done in a workmanlike manner or with proper' materials, and that the street was practically impassable from the time the work was completed. In the prayer the city asked that the plaintiff’s petition 'be dismissed, but, if that was not done, that the property owners be made parties defendant, and that the plaintiff, if granted any recovery, only be allowed to recover for so much of the work as complied with the contract, and that no per *46 sonal judgment be rendered against the city, but that it only be required to assess the property for a sufficient amount to pay any demand that might be adjudged to the plaintiff. No summons on the cross-petition was issued until December 27, 1933. The property owners answered on March 12, 1934, denying that the work had been done in compliance with the contract and pleading the five-year statute of limitations. Appropriate pleadings completed the issues, and proof having been heard, the court entered a judgment in favor of the Carey-Reed Company against the city for the sum of $2,290.58, with interest thereon from October 24, 1932, and dismissing the city’s cross-petition against the property owners. The’ city has appealed, and the Carey-Reed Company has been granted a cross-appeal.

A number of witnesses testified that holes appeared in the pavement immediately after the work was completed and that the street rapidly disintegrated and in a short time became practically impassable. There was little evidence to the contrary.

About eighteen months or two years after the work was rejected the city entered into a contract with the state highway commission which provided for the construction of what is known as a retread type of road on the section of street in question. The city paid $2,000 to the state highway commission, and the commission constructed the road in accordance with the contract, using the grades that had been established when the amesite paving was done. All of the evidence shows that the concrete ourb and gutter and sidewalks were constructed by Carey-Reed Company in the proper manner and that the excavation was done in accordance with the specifications.

The chancellor allowed the full amount claimed for constructing the curb and gutter, concrete sidewalks, and storm sewers and for other items which the evidence showed were properly constructed and of permanent value, regardless of the type of street paving. The amount claimed for 631 cubic yards of excavation was $283.95, and he allowed $200 on this claim, apparently upon the theory that it was worth that amount when the street was reconstructed later. He disallowed $1,-977.75, the amount claimed for laying the amesite paving and gravel base, and also two or three small items *47 aggregating approximately $250. The city received the benefit of certain portions of the work which complied with the contract and which was utilized when the street was repaved. The evidence supports the chancellor’s finding in this respect.

The city insists that it should be permitted to assess against the abutting property the amount found against it, but we think the chancellor was correct in adjudging that its right to make the assessments was barred by limitations. Section 3574 of the Statutes provides that:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pinnacle Development II, LLC v. RML Construction, LLP
410 S.W.3d 169 (Court of Appeals of Kentucky, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
83 S.W.2d 891, 260 Ky. 43, 1935 Ky. LEXIS 419, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-mayfield-v-carey-reed-co-kyctapphigh-1935.