City of London v. Proctor, Unpublished Decision (5-24-2001)

CourtOhio Court of Appeals
DecidedMay 24, 2001
DocketNo. 01AP-34.
StatusUnpublished

This text of City of London v. Proctor, Unpublished Decision (5-24-2001) (City of London v. Proctor, Unpublished Decision (5-24-2001)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of London v. Proctor, Unpublished Decision (5-24-2001), (Ohio Ct. App. 2001).

Opinion

OPINION
On May 11, 2000, a complaint was filed in the Franklin County Court of Common Pleas on behalf of the city of London in Madison County, Ohio.1 The complaint sought both declaratory and injunctive relief. At the heart of this litigation is the "State Route 142 Road-Widening Project," involving the widening of a main thoroughfare, East High Street, also known as State Route 142, in London.

The named defendants in the lawsuit were Gordon Proctor, Director of the Ohio Department of Transportation ("ODOT"), and the "Committee o[n] East High Street c/o * * *" five individuals with addresses on East High Street (hereinafter, collectively, the "committee"). The committee opposes the road-widening project ("project"), citing several objections, including construction and traffic-related concerns, as well as aesthetics resulting from the loss of trees.

The underlying facts giving rise to this case are gleaned from the complaint filed by the city, along with certain documents attached thereto and other exhibits contained elsewhere in the record.

The project was formally initiated by the city in August 1992 pursuant to Emergency Ordinance 186-92, which approved the widening of State Route 142 from a two-lane to a three-lane road; added sidewalks, curbs, and gutters; and improved drainage and storm sewers. The ordinance authorized the city to enter into agreements with ODOT as necessary to complete the planning and construction of the project.

The planning process continued until May 1997, when another ordinance, Emergency Ordinance 146-97, was passed, directing the city to enter into agreements with ODOT "as necessary to complete the project."

Pursuant to Emergency Ordinances 186-92 and 146-97 (the "enabling ordinances"), the city and ODOT entered into a contract (the "project agreement") whereby ODOT agreed to undertake the planning and construction of the project, which was to be financed from state and federal funding sources estimated at approximately $5,200,000. These funds will not be available after June 30, 2001, as the money must be reallocated if not expended by that date. For that reason, resolution of this litigation must be expeditious.

The city, invoking reliance upon the project agreement, entered into a separate agreement for engineering studies necessary for the planning and construction of the project. According to the complaint, the city agreed to pay $400,000 for these studies.

The project agreement required ODOT, on behalf of the city, to secure legal title to rights-of-way necessary for the project. The complaint averred that, at the time of the filing of the complaint, ODOT had substantially fulfilled its obligation to obtain the requisite rights-of-way, expending over $500,000 and acquiring approximately seventy-seven parcels of property from certain city residents. Among some of the parcels already appropriated by ODOT are those previously owned by two committee members. At the time of the filing of this complaint, several other appropriation actions remained pending in the Madison County Court of Common Pleas. According to the record, those actions cannot proceed until this litigation is resolved.

On August 10, 1999, the committee filed an Initiative Petition with the Madison County Board of Elections, seeking to repeal the enabling ordinances.

In the November 1999 election, the petition was approved by a majority of the voters. As a result, ODOT advised the city that ODOT would not move forward on the project until issues related to the constitutionality of the ordinances and/or the Initiative Petition were resolved.

The city alleged that the passage of the Initiative Petition resulted in the following: (1) ODOT's inability to advance the project and its refusal to fulfill the terms of the project agreement; (2) disruption of all "reasonable expectations" pursuant to the project agreement; (3) substantial impairment of, "in effect abrogating," the contractual relationship between the parties; and (4) irreparable harm to the city if the issues are not resolved "almost immediately" because the city will lose the $5,200,000 state and federal funding if construction is not commenced by June 2001.

The relief sought by the city in this action is both injunctive and declaratory. The city's complaint primarily sought a judgment declaring that the Initiative Petition is unconstitutional, and that the project agreement is valid and enforceable. The corresponding injunctive relief sought was that necessary to proceed with the project.

At the July 20, 2000 initial status conference, the parties presented the pertinent issues to the trial court. Acknowledging that time was of the essence, the trial court entered an order modifying the case schedule which ordered the parties, inter alia, to file expedient dispositive motions. Discovery proceedings were to occur immediately.

A brief, two-page answer to the complaint was filed by the committee's counsel on August 1, 2000.

The city ultimately filed a Civ.R. 56(C) motion for summary judgment on August 14, 2000. The committee responded with motions to dismiss and for a change of venue, both of which were ultimately overruled.

On August 22, 2000, the committee's counsel filed a motion seeking an additional sixty days during which further discovery could be conducted to enable counsel to prepare a memorandum contra the city's motion for summary judgment. The trial court overruled the motion. Instead, on August 25, 2000, the court journalized a scheduling order modifying its earlier case schedule. The entry, journalized August 28, 2000, provides, in pertinent part:

The Court has reviewed the Affidavit attached to the Motion [seeking the extension of time for discovery purposes] which was filed pursuant to Civ.R. 56(F) and finds, and counsel agreed at the status conference, that these facts can be stipulated. Discovery is not necessary.

The order proceeded to set a deadline for stipulations to be "signed, agreed to and filed with the court no later than September 7, 2000." The court also ordered that contemporaneous responses by all parties to all pending motions to be filed no later than September 21, 2000. Replies were to be filed by September 28. Finally, the court informed the parties that it would "issue a decision on all motions no later than October 15, 2000."

Notwithstanding the court's modified case scheduling order, counsel for the committee filed a motion on September 5, 2000, seeking yet another extension of time and a court order compelling the city to produce certain public records for discovery purposes.

Unsuccessful in obtaining further extensions, the committee finally filed its memorandum contra and cross-motion for summary judgment on September 21, 2000.

Pursuant to a decision rendered December 5, 2000,2 and journalized January 4, 2001, the trial court ultimately granted the city's motion for summary judgment. The trial court's entry reads, in pertinent part:

(a) the Project contract between Plaintiff and Defendant ODOT is valid and enforceable; and

(b) the Initiative Ordinance is unconstitutional pursuant to Article I, Section 10 of the United States Constitution and Article II, Section 28 of the Ohio Constitution and, therefore, void ab initio.

Therefore, this Court issues the following permanent injunction:

(c) directing Director Proctor and ODOT to proceed with the Project pursuant to the Enabling Ordinances and the terms and conditions as set forth between ODOT and Plaintiff; and

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Glimcher v. Reinhorn
587 N.E.2d 462 (Ohio Court of Appeals, 1991)
Ball v. Hilton Hotels, Inc.
290 N.E.2d 859 (Ohio Court of Appeals, 1972)
Gates Mills Investment Co. v. Village of Pepper Pike
392 N.E.2d 1316 (Ohio Court of Appeals, 1978)
Mergenthal v. Star Banc Corp.
701 N.E.2d 383 (Ohio Court of Appeals, 1997)
Helton v. Scioto County Board of Commissioners
703 N.E.2d 841 (Ohio Court of Appeals, 1997)
GTE Wireless of Midwest Inc. v. Anderson Township
731 N.E.2d 201 (Ohio Court of Appeals, 1999)
Harless v. Willis Day Warehousing Co.
375 N.E.2d 46 (Ohio Supreme Court, 1978)
City of Middletown v. Ferguson
495 N.E.2d 380 (Ohio Supreme Court, 1986)
Berk v. Matthews
559 N.E.2d 1301 (Ohio Supreme Court, 1990)
State ex rel. Grady v. State Employment Relations Board
677 N.E.2d 343 (Ohio Supreme Court, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
City of London v. Proctor, Unpublished Decision (5-24-2001), Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-london-v-proctor-unpublished-decision-5-24-2001-ohioctapp-2001.