City of Lincoln v. PMI FRANCHISING, INC.

675 N.W.2d 660, 267 Neb. 562, 2004 Neb. LEXIS 39
CourtNebraska Supreme Court
DecidedMarch 12, 2004
DocketS-02-1417
StatusPublished
Cited by2 cases

This text of 675 N.W.2d 660 (City of Lincoln v. PMI FRANCHISING, INC.) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Lincoln v. PMI FRANCHISING, INC., 675 N.W.2d 660, 267 Neb. 562, 2004 Neb. LEXIS 39 (Neb. 2004).

Opinion

Miller-Lerman, J.

NATURE OF CASE

The City of Lincoln (the City) filed suit in the district court for Lancaster County against PMI Franchising, Inc. (PMI), James E. Hershberger, and Sandra M. Hershberger to recover money that was loaned to PMI pursuant to a financing agreement in aid of an economic development program sponsored by the City. The Hershbergers were guarantors on the loan to PMI. The Hershbergers moved for summary judgment. The district court concluded that the City’s action against the Hershbergers was barred by the statute of limitations. The court, inter alia, granted summary judgment in favor of the Hershbergers and dismissed the petition. Following various procedural events recited in part below, the City appealed. We note that although PMI and the Hershbergers are all denominated as appellees, the substance of the City’s argument shows that the City’s appeal is limited to the court’s determination that the City’s action against the Hershbergers was time barred and to the court’s corresponding order granting summary judgment and dismissing the City’s action against the Hershbergers. We reverse, and remand for fiirther proceedings.

STATEMENT OF FACTS

On June 8, 1993, the City and PMI entered into a “Project Financing Agreement” pursuant to which the City agreed to loan $49,500 to PMI and PMI agreed to repay the loan. Paragraph 5 of the agreement provided for monthly payments of interest only for the first 24 months and amortized payments of principal and interest over the following 60 months, for a total term of 7 years. Paragraph 16 of the agreement provided that in the event PMI *564 defaulted on its obligations, the City was to provide notice of such default to PMI and, in the absence of a cure, the City could thereafter terminate the agreement. Specifically, if PMI failed to correct the default within 30 days of receipt of written notice, then under paragraph 16, “the unpaid balance plus accmed interest to the date of termination [would] become due and payable in full immediately on the date of termination.” The Hershbergers executed the agreement as officers of PMI. As part of the financing arrangement, each of the Hershbergers signed an individual guaranty for PMI’s obligations under the agreement. Each guaranty provided that the guarantor would unconditionally repay funds loaned to PMI “when due, pursuant to the financing agreement.”

According to the record, on July 7, 1993, the City disbursed $23,753.43 to PMI. In the Hershbergers’ answer, they do not dispute that “approximately $23,000.00” was loaned. TTie next document in the record is a December 10, 1993, letter written by James Hershberger to the City, reporting on the progress of the project and seeking a deferral of payments. Evidently, there was a failure of payment at some point, because, in a February 28,1995, letter contained in the record, the City wrote the Hershbergers declaring that PMI had defaulted under the minimum repayment terms of the agreement. The City’s letter stated that if the default was not corrected, the agreement would be terminated and the entire unpaid principal balance of $23,753.43 plus accrued interest would be due and payable. On March 21, James Hershberger sent a letter to the City stating that he wanted to meet to “discuss [the] terms of [the] agreement and a Repayment schedule.”

On September 20, 1999, the City filed a petition in the district court against PMI and the Hershbergers. The City filed a second amended petition on December 17, 1999, which is the operative petition. In the second amended petition, the City alleged that PMI had failed to repay the loan contrary to the provisions of the agreement and that the Hershbergers had failed to comply with the provisions of the guaranties. The City alleged that pursuant to the agreement, the City had sent a letter on February 28, 1995, declaring PMI to be in default. In the petition, the City alleged that the unpaid principal and accrued interest was due and payable. The City prayed for a judgment against PMI and the Hershbergers in the amount of the unpaid *565 principal of $23,753.43 plus accrued interest, as well as costs and attorney fees.

The Hershbergers filed an answer in which, inter alia, they admitted the loan of “approximately $23,000.00” and affirmatively alleged that the City’s action against them was barred by the statute of limitations. The Hershbergers also filed a counterclaim alleging that the City breached the agreement by failing to loan PMI the full $49,500, thereby causing the business which was the subject of the agreement to fail.

Although PMI was served, no answer or other appearance was filed on behalf of PMI. Eventually, during the course of the proceedings before the district court, a default money judgment against PMI was entered.

The Hershbergers moved for summary judgment on the basis that the action against them was time barred. An evidentiary hearing on the Hershbergers’ motion was held October 16, 2000. Various items of evidence, including correspondence, were admitted. The court agreed with the Hershbergers, and on January 31, 2001, dismissed the second amended petition as to the Hershbergers and, although it had not appeared, PMI. The court reasoned that the cause of action against the Hershbergers was barred by the 5-year statute of limitations pertaining to contracts contained in Neb. Rev. Stat. § 25-205 (Reissue 1995). Included in the court’s reasoning was the statement that the City was required to bring its action “within five years after the agreement was signed on June 8, 1993.” Because the City did not file its action until 1999, the court concluded that the action was time barred.

The City appealed the January 31, 2001, order of summary judgment to the Nebraska Court of Appeals. The Court of Appeals dismissed the appeal on the basis that the January 31, 2001, order was not a final, appealable order because it did not dispose of the Hershbergers’ counterclaim against the City. See City of Lincoln v. PMI Franchising, 11 Neb. App. xxiii (No. A-01-269, June 10, 2002). Upon remand, the district court entered an order dismissing the Hershbergers’ counterclaim. Further, upon remand, on December 3, 2002, the district court filed a nunc pro tunc order striking reference to PMI in the January 31, 2001, order and granted a default money judgment against PMI. The action having thus been concluded as to all parties and all causes of action, *566 the City filed a notice of appeal on December 6, 2002. A motion to dismiss the appeal as untimely filed was correctly denied by the Court of Appeals prior to the transfer of this case to this court’s docket.

On appeal, the City claims the grant of summary judgment in favor of the Hershbergers and the corresponding dismissal were error.

ASSIGNMENTS OF ERROR

The City generally asserts that the district court erred in determining that the 5-year statute of limitations under § 25-205 barred the City’s petition and in granting summary judgment in favor of the Hershbergers.

STANDARDS OF REVIEW

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Lincoln v. Hershberger
725 N.W.2d 787 (Nebraska Supreme Court, 2007)
Boutilier v. Lincoln Benefit Life Insurance
681 N.W.2d 746 (Nebraska Supreme Court, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
675 N.W.2d 660, 267 Neb. 562, 2004 Neb. LEXIS 39, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-lincoln-v-pmi-franchising-inc-neb-2004.