City of Lincoln v. Nebraska Public Power District

614 N.W.2d 359, 9 Neb. Ct. App. 465, 2000 Neb. App. LEXIS 213
CourtNebraska Court of Appeals
DecidedJuly 18, 2000
DocketA-98-866
StatusPublished
Cited by24 cases

This text of 614 N.W.2d 359 (City of Lincoln v. Nebraska Public Power District) is published on Counsel Stack Legal Research, covering Nebraska Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Lincoln v. Nebraska Public Power District, 614 N.W.2d 359, 9 Neb. Ct. App. 465, 2000 Neb. App. LEXIS 213 (Neb. Ct. App. 2000).

Opinion

Hannon, Judge.

In 1968, the parties contracted with respect to the Cooper nuclear power plant (Plant), a nuclear electric generating station that the Nebraska Public Power District (NPPD) was about to build near Brownville, Nebraska. The Power Sales Contract provided that the City of Lincoln, Nebraska, doing business as Lincoln Electric System (collectively LES), was to receive 12.5 percent of the electricity generated by the Plant and that in consideration for that power, LES was required to pay 12.5 percent of the costs of operating the Plant. In 1993, the Plant was scheduled to be shut down (outage) for refueling and maintenance, *467 and this outage was extended. In 1994, the plant was shut down for a period that was not planned.

The operation of the Plant is under the regulatory power of the Nuclear Regulatory Commission (NRC), and during 1993 and 1994, it issued several notices of violations and imposed civil penalties upon NPPD in connection with the Plant’s operation. LES alleges the extension of the 1993 outage, the unplanned 1994 outage, and the civil penalties were caused by NPPD’s mismanagement as defined in the contract. LES sued NPPD to recover the damages it claims to have suffered because it did not receive power during those outages and for the increased costs it incurred to satisfy its power needs and the amount by which its 12.5 percent share of the Plant’s costs increased, all of which LES alleges resulted from NPPD’s mismanagement. LES maintains that the documentation generated by NRC’s self-inspections, NRC’s notices of violations, and reports from inspections by third parties that NPPD requested shows that the outages and civil penalties were caused by NPPD’s mismanagement of the Plant. Upon the basis of this documentation, the trial court granted a partial summary judgment to LES on the issue of liability for damages caused by the outages and for the penalties. Later, a jury determined LES’ damages to be $9.8 million.

Upon appeal, we conclude that the evidence of mismanagement by NPPD does not require an inference that NPPD was guilty of mismanagement as defined by the contract, although it might justify a finding to that effect, and that therefore the trial court erroneously granted a partial summary judgment on liability. Accordingly, we reverse, and remand for a new trial on liability and other factual issues.

By way of general background, the evidence establishes that from 1968 until 1993, there had been no serious difficulties between the parties. NPPD’s evidence takes the position that after the Three Mile Island event in Pennsylvania in 1979, the oversight of nuclear plants by NRC changed remarkably. For whatever reason, in late 1992 and thereafter, reports on the Plant’s operation and management were much less favorable and became critical of certain portions of Plant operations. NRC inspections found violations of its regulations at the Plant and *468 assessed civil penalties against NPPD in 1993 and 1994 totaling $700,000.

From the voluminous evidence, it appears that there was never any claim that the mismanagement directly resulted in a nuclear incident, or a near incident. However, it appears that the danger of a disaster from some sort of malfunction of a nuclear reactor quite naturally results in nuclear plants having many safety and fallback systems that are intended to function in the event some problem with the reactor might arise. Apparently, the nuclear industry spends a great deal of time checking and rechecking to be sure that safety systems will function when and if they are needed. It appears that there were failures of Plant personnel to find improper conditions in the operating and safety systems and that there was a failure of one safety system to work when it could have been needed, which were all taken by NRC as an indication that the systems had not been properly inspected and tested. There was one case where an improper condition was not reported as required. NRC and other inspectors attributed these failures to the failure of NPPD managers to have systems of inspections and supervision and to create a work atmosphere which would ensure such failures did not happen.

In reading the testimony and reports, one is struck by the vagueness of the reports and the testimony of the various inspectors concerning the shortcomings of the Plant’s management. As an example, a statement in a “Diagnostic Self Assessment” report, which is relied upon by LES to support its claim of mismanagement, states:

Ongoing problems with plant and system status control, procedure quality and adherence, the lack of a strong work control program, weak industrial safety practices, ineffective independent oversight and quality assurance program, and a general problem of inadequate programs that do not meet regulatory requirements, all reflect standards which have not kept pace with industry practice.

Except for three or four events where equipment was not as it was expected to be or did not function as it was supposed to function, the evidence is of the general opinion much like the above quote. LES does not, however, rely upon opinion evidence.

*469 The observation of the vagueness of the evidence is not intended to be critical of the persons preparing the reports, but is only a recognition of the difficulty that nuclear plant managers and inspectors necessarily have in practicing and communicating their art. Such vague terminology also makes it difficult to judge the management quality of NPPD against the standard set forth in the parties’ contract and industry standards, or against any other standard.

Contract.

The contract between the parties was made on May 21,1968, and it will continue until at least September 22, 2003, and perhaps beyond. The parties operated under the contract, and uncontested amendments to it, without difficulty until 1993. The contract provided that NPPD would own the Plant and that it agreed to make available to LES 12.5 percent of the energy generated at the Plant. LES was required to pay 12.5 percent of all expenses NPPD incurred in operating the Plant. The definition of delivery of power, power costs, and the methods of billing and payment are all extensively defined and provided for in the contract. But since there is no dispute concerning these provisions, they will not be summarized.

Section 9 of the contract provides in significant part:

The District may temporarily interrupt or reduce deliveries of electric energy to the Purchaser if the District determines that such interruption or reduction is necessary in case of emergencies affecting the ability of the District to produce or deliver power from the Nuclear Facility. In order to refuel, install equipment in, make repairs to, replacements, investigations and inspections of, or perform other maintenance work on the Nuclear Facility . . . the District [will provide a notice of outage].
Except as interrupted by Uncontrollable Forces, or as otherwise provided in this Contract, the District shall operate the Nuclear Facility and make power and energy therefrom available to the Purchaser in accordance with this Contract....

(Emphasis supplied.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Longs v. Johnson
Nebraska Court of Appeals, 2019
State v. Arellano
Nebraska Court of Appeals, 2017
In re Estate of Radford
297 Neb. 748 (Nebraska Supreme Court, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
614 N.W.2d 359, 9 Neb. Ct. App. 465, 2000 Neb. App. LEXIS 213, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-lincoln-v-nebraska-public-power-district-nebctapp-2000.